Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 1 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 28 Jan 2019, 14:33 

SPB/SFX

  • The vacuum section of the burthrough monitor was vented for some intervention  and is now being pumped again.
  • CSS component has issues with limit switches implementation. Will be discussed with AE and EET.
  • Jungfrau loop can be brough up once AE gets the fuse boxes formt he company.

FXE

SQS

SCS

  • Waiting for loops updates
  • DSSC can be switched on since no more works on the power lines are foreseen.

MID

  • ATT XTD6 being re commisisoned.
  •  Mono in XTD6 being commissioned.
  • Optics hutch commissioning ongoing.

HED

  • Loop 2 needed for commissioning. AE checks the status.
  • Modules for the attenuator also needed. AE checks the status.

 

OPT Lasers

XRO

  • Encoders for the mirrors in XTD6 are being checked.
  • Commissioning of benders in SASE3 planned for 8,9,10. Feb. SQS hutch will be interlocked and shutter opened.

XPD

VAC

  • Tunnel access schedule was updated: https://ttfinfo.desy.de/elog/XMLlist?file=/XFELelog/data/doc/Schedule/2018-12-12T08:13:57-02.xml&xsl=/elogbook/xsl/elog.xsl&picture=true

AE

  • The timing software needs to be updated. Today at 14:00. 

ITDM

DAQ in the tunnels has been updated.

A mail will be circulated with the new proposals for users.

SA1 will be switched to the new storage. Corrdinated with CAS. This will allow the users to access data on the online cluster without first migrating the data to the Maxwell cluster. System will be tested on Wed afternoon and Thu. In this time frame interruption of the storage systems can happen.

EET

CAS

AoB

Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 25 Jan 2019, 10:07 

SPB/SFX

  • Trigger for Jungfrau detector is needed. 
  • Commissioning of the instrument should start next week
  • Loop priorities for the donwstream components have been set with AE.

FXE

SQS

  • VAC interlock test will be done during next days after update of the loop.
  • Loop 4 has to be updated following some HW changes. Should run by next week since is needed for the preparation of the users run.
  • Digitizers crate is being tested by AE and CAS and will be installed/usable by the middle of next week.
  • Burst trigger - status and requirements will be discussed with BFernandes after this meeting.
  • MPOT test CY/TB Today at 13:30

SCS

MID

HED

  • Preparation of Hi res mono has been completed last week
  • OPT hutch CRL commissioning ongoing. ATT will follow (needed missing crate will be installed next week)
  • Chamber motion for the monochromator has to be checked 

 

OPT Lasers

XRO

  • Loops update in thetunnels have been completed. the MOV1 in SASE3 included also some PBLMs ==> XRD should check whether everything is fine afte the update.

XPD

VAC

  • Tunnels are ready for beam.

AE

  • EXAPOD in SPB can be tested.
  • HED need PPU in XTD6. To be re-checked.
  • The timing software needs to be updated. BFernandes circulated a mail with proposed date: Next monday at 14:00. In case of different suggestion, please contact Bruno. CAS suggests to keep the proposed date.

ITDM

ET

CAS

  • Data logger schould be working for every component now. ==> Meeting later with VAC and Laser group to define the use case and start a new optimization project.
  • VAC of HED Opt tests are ongoing (CY) before pumping down.
  • For the debug of gauges control is possible that a ZZ access will be requested. (CY)

AoB

  • Tunnel access schedule will be updated by HSinn after the Operation meeting with the latest information.
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 23 Jan 2019, 10:47 

SPB/SFX

FXE

  • Fixing session of the sample stage. No controls modification involved. Done by today.
  • Shutter controls from the hutch. Some works were supposed to be done by MPS. What is the status?

SQS

  • New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. ==> Master loop will be updated until tomorrow. Tests still planned for Wednesday. ==> Test successful. Now SQS has to decide whether to use the interlocks during next runs.
  • VAC interlock test will be done during next days after update of the loop.

SCS

  • Updated interlock definition will be given to AE by SCS==> Done.
  • Electronics and cabling for the laser hutch is coming next. MTeichmann will talk to EET to agree on priority concerning the cables production and pulling. It may be necessary for SCS to pull a few cables as soon as possible (by themselves?). Anyway, cables route will be needed. ==> EET is waiting.

MID

  • Loop commissioning priorities being discussed with AE. (as well as checking whether all the important PLCs are there)
  • Next Tuesday the cabling shoud be completely done. 

HED

OPT Lasers

  • in SASE1 the seeder was swapped. This affects the timing. Will be discussed with AE.
  • PP laser should also get the train id. Change request to be prepared soon.

XRO

XPD

VAC

  • Leak test for HED mono has to be performed
  • AE reports they got feedback that also SASE1 vacuum  needs to be tested. MD checks. 

AE

  • AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. ==> MOV 1 will be updated. Also CAS will be asked to save the motor parameters. NO EPS and MOV 2 loops update necessary for now. ==> SASE3 MOV 1 will be updated today.

ITDM

  • DAQ installations for SASE2 and 3 will be physically migrated in the balconies to separate them from SASE1. Will be completed in the next days. Will be finished before DAQ has to be operative.
  • DAQ SASE1 running for detectors test.
  • MID will also get DAQ working soon for AGIPD test.

DET

CAS

  • Data logger schould be working for every component now. ==> More info to come.

AoB

  • LIEN fixed the sliding doors in SASE3 experiments. Drag chains have been installed. Only 1 cable has to be ordered and exchanged. Will be done during the next shutdown.
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 21 Jan 2019, 10:43 

SPB/SFX

FXE

SQS

  • AQS chamber has been removed. The reaction microscope is now being installed. (Currently sitting next to the beamline)
  • New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. ==> Master loop will be updated until tomorrow. Tests still planned for Wednesday.
  • Mpots control and integration is still being debugged by CYoungman. Additional tests planned for tomorrow.

SCS

  • All the PLC hardware is now fixed, with the exception of some high voltage interlock controls, which is waiting for the E-plan to be finalized. 
  • Firnware update needed and planned for the next days.
  • Updated interlock definition will be given to AE by SCS
  • Electronics and cabling for the laser hutch is coming next. MTeichmann will talk to EET to agree on priority concerning the cables production and pulling. It may be necessary for SCS to pull a few cables as soon as possible (by themselves?). Anyway, cables route will be needed.
  • This morning the PLCs in the SCS raclroom went off. The information from TS is that the emergency power off button was pushed in the SCS experiment hutch. 

MID

  • Has to be clarified when the chiller is going to be back
  • Homing test motors in XTD1. Small issues found. Update needed.
  • MC2 Motors are working properly
  • Workin out commissioning priorities with AE and CAS based on the cables availability

HED

OPT Lasers

XRO

  • Tomorrow the M2 in XTD will be ready for commissioning
  • On Wednesday the MOV2 loop in SASE2 tunnels will be updated. CAS is saving the motor parameters right now.

​​XPD

  • Screens have been exchanged
  • XTD2 photonic science camera is back and working
  • XTD10 SQS2 pop in monitor back and working
  • All tasks foreseen for the Winter shutdown have been completed.

 

VAC

AE

  • AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. ==> MOV 1 will be updated. Also CAS will be asked to save the motor parameters. NO EPS and MOV 2 loops update necessary for now.

ITDM

DET

CAS

  • Data logger schould be working for every component right now.
  • On Wednesday the MOV2 loop in SASE2 tunnels will be updated. CAS is saving the motor parameters right now.

AoB

Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 18 Jan 2019, 11:05 

SPB/SFX

  • The interlock definitions in the tunnel were updated. They have to be tested.

FXE

SQS

  • Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). Happening today. After completion CAS and AE support is needed to switch the systems back on. ==> Completed. No issues.
  • AQS chamber has been removed. The reaction microscope is now being installed.
  • New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. 

SCS

MID

HED

OPT Lasers

XRO

​​XPD

VAC

  • Mono loop in SASE 3 has to bee updated (22nd). Agreed with involved parties. 
  • MOV2 Loop SASE2 also needs to be updated. Agreed with involved parties.

AE

  • AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. This task was not included in the shutdown list and therefore has not been planned. The issue needs to be reported in the operation meeting since a reshuffle of priorities and relative decisions are eventually needed.
  • CRLs for SPB will be controllable at the end of March/ beg. April as agreed with the instrument people. 

EET

ITDM

DET

CAS

  • It is pointed out that the CAS policy is not to implement changes in the software on Friday in order to guarantee the smooth operation of components during the week end. This should be also reported in the Operation meeting.

AoB

  • 22/23 January Fa. LIEN will fix the sliding doors in the SASE3 hutches.
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 16 Jan 2019, 10:20 

SPB/SFX

FXE

SQS

  • Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). Happening today. After completion CAS and AE support is needed to switch the systems back on.
  • AQS chamber is being removed
  • New interlock definitions have to be tested and implemented asap. AE will discuss a date to SQS, although Friday might me a good time.
  • SQS is eager to get the new trigger system from desy and AE and help testing it. It was noted that the trigger is linked to a specific SASE.

SCS

MID

HED

OPT Lasers

XRO

​​XPD

VAC

  • M2 mirror has been installed, the chamber closed. MCP is being mounted back. 

AE

  • VAC loops updates in the tunnels are ongoing and being coordinated with affected groups
  • Motion 2 in SASE2 loop needs to be updated. Being coordinated with AKoch.
  • SASE3+2 implementation of changes and commissioning ongoing.

EET

ITDM

DET

  • During some AGIPD test with cold detector Karabo lost connection with the PLCs. This was due to the installation of new CPUs for the SFX components. For 10 minutes was not clear whether the vacuum was OK and for safety purposes the detector has been warmed up. These works have to be properly communicated next time.

CAS

AoB

  • 22/23 January Fa. LIEN will fix the sliding doors in the SASE3 hutches.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 14 Jan 2019, 12:58 

SPB/SFX

  • D.23 Cabling ongoing. Minor problems concerning Chicane filling. 10 cables need to be routed through another chicane.  Being sorted out with EET.
  • Silicon oil pipe has been fixed and is undergoing pressure tests. So far successful.
  • Issue concerning tripping power plugs in D.09. Needs to be investigated (SPB/SFX <=> TS)

FXE

SQS

  • This week the AQS chamber will be removed. 
  • Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). TBaumann will agree the time with TS. Note from MTeichmann: Even though 1 hour was foreseen, for  SCS it took 5 hours. Be careful and plan accordingly.

SCS

MID

  • Commissioning ongoing. The homing function of motors in the optics hutch will be tested this week.
  • VAC system in the optics hutch operational. Some issues with the control of the ion pumps need support from AE (1 hour). ==> Tomorrow, 14, Marjan.

HED

  • Mono in XTD6 testing ongoing. Piezo and encorders need some adapter. 
  • Hi res mono vessel is being opened and will be closed again at the end of the week
  • Si- mono vessel does not need to be opened. 
  • Commissioning of the OPT hutch starting tomorrow (Loop 1 and 2)

OPT Lasers

XRO

​​XPD

  • All FEL imagers have been replaced (now with Al coating reducing reflections).
  • XTD2 XGM gauge has been replaced.

​​VAC

AE

  • VAC loops in the tunnels are being coordinated with affected groups
  • Motion 2 in SASE2 loop needs to be updated. Being coordinated with AKoch.
  • Test with the 3 triggers coming from the machine for the 3 SASEs are ongoing.

EET

ITDM

DET

CAS

AoB

  • Fridays OP/Readiness meeting is not taking place anymore.
  • A new Operation meeting is being set up.
  • TT will propose a time slot to put a replacement for the Op/Readiness meeting where technical issues and information spreading after the dispatch meetings can follow.
  • Issues concerning the handling of the maintenance day on monday has been raised by the groups. Has to be seen how to cope with that.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 09 Jan 2019, 10:04 

SPB/SFX

  • New Karabo release has been installed.

FXE

SQS

SCS

  • EET and AE should get in touch to discuss how to speed up the crates fixing. Some details need to be sorted out.

MID

HED

  • Mono in XTD6 need some work. Meeting today to discuss details with AE
  • HI res mono needs to be opened. Work being organized for next week.

OPT Lasers

  • The power glitches l2 nights ago caused a power loss between 1am and 7 am. The seeder in SASE 1 went off. It is being switched on again but this reduces considerably its lifetime. No problems in SASE3. Tha's probably because different protection voltage drops are used (20V/40V) for the fuses. TS will look into that to understand why and whether the situation can be improved.

XRO

  • M2 in SASE3 goes back this week and will be pumped during the week end.
  • Vac group busy ventin sections to replace imagers,

​​XPD

​​VAC

AE

EET

ITDM

DET

CAS

AoB

  • Power cut in the SQS/SCS rackroom needed to fix the emergency power off system. 1 hour needed for each rackroom. The redundant power line will not be affected. The following dates have been agreed:
    • SCS - MTeichmann will bring the PLCs ina safe state and give confirmation to TSchoen within 1 hour today
    • SQS - Power will be cut next Wednesday morning during the chamber switch. Exact time will be agreed next week.
    • Optical lasers are not involved in the power cut.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 Jan 2019, 09:55 

SPB/SFX

  • CRLs will be brought in the SPB lab in XHQ. The vacuum group is installing the replacement pipe.
  • SFX cabling starting today.

FXE

SQS

SCS

MID

HED

OPT Lasers

XRO

  • M2 in SASE3 is being replaced and the mechanics need to be re calibrated.

​​XPD

  • FEL imager screen in XTD2 has been replaced.
  • FEL imager screen in XTD10 will be replaced today or tomorrow.

​​VAC

AE

  • SASE2 VAC loop has been updated. 
  • The VAC group requested an update of all the motion loops in the tunnel due to some problems with the encoder readout. In principle this could be done next week, but AE will meet with VAC and OPT to discuss the details before.
  • MID/HED monos being commissioned.

EET

ITDM

  • There was a network update last week
  • This Wed/Thu the Maxwell clusters will be updated. No offline computing possible.
  • Most of the activities planned for the WS have been done.
  • Installation of new storage for SASE1 will be done in thenext days.
  • OS in the PCs in the control rooms need to be updated. This will be coordinated with the intruments.

DET

CAS

  • CY is now back working on the Mpots (SASE2 and 3). Changes have been implemented. SQS to perform tests. Documentation has also been updated and will be circulated probably next week.
  • Karabo training has been organized. The agenda will be circulated soon.
  • SPB Karabo upgrade has to be agreed with SPB/SFX.

AoB

  • Fridays OP/Readiness meetying moved to 9.30 from now on.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Dec 2018, 13:17 

SPB/SFX

  • SFX part1 cabling preparation ongoing (WCBs mounting and labeling). Good progress.
  • CRLs will be brought out of XTD9 tomorrow.
  • Scaffolding below D.23 has been removed. An official communication that now the area is completely accessible is still lacking.

FXE

SQS

  • For the loops 9-13 the HW is ready. CAS projects have to be prepared.
  • Some issues with middle layer devices have been notified to CAS (Cyril)

SCS

MID

  • Karabo 2.3.2 has been deployed apart from the AGIPD control (waiting for tests by DET group before update).
  • CY is now back working on the Mpots (SASE2 and 3)

HED

OPT Lasers

XRO

​​XPD

​​VAC

AE

  • SASE1 power was back yesterday. SPB and FXE have been brought up again yesterday afternoon. Today morning because of unplanned and badly communicated MPS works the power was cut again ==> additional, unplanned efforts needed.
  • Hazem will be OCD during Christmas, only for PLCs. 
  • No uTCA OCD during Christmas.

EET

ITDM

DET

CAS

  • 2.3.2 Deployed in SASE2
  • SPB update postponed to January
  • SASE1 planned for today
  • No OCD until 09.01.

AoB

  • Next Disptach meeting on 07.01.2019 at 9:30
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 17 Dec 2018, 10:36 

SPB/SFX

  • SFX part1 cabling preparation ongoing (WCBs mounting and labeling)
  • waiting for the power to come back

FXE

SQS

  • Some interlocks need to be activated. Discussion with AE ongoing. Will be probably done early next year.
  • Loops updates are being discussed/executed plus CRs status are being checked.
  • pnCCD CRD is being prepared. Information like what electronics can go in the Rackroom and what in the huctch due to cable length restrictions will be collected and spread to the relevant people (e.g. safety)

SCS

  • Successful beam time with users - many thanks to all the support groups
  • Fixing of crates and additional cabling is being prepared/ongoing.
  • DET group asked for a coordination meeting concering users requirements for the fast ccd in the next users run.

MID

  • Cabling ongoing
  • Support from AE to modify the Racks that will host the electronics for the MID and HED monochromators has been requested. PGessler will check whether support can be granted this week (other activities ongoing). The goal is to commission the two monochromators in the tunnel in the shutdown.

HED

OPT Lasers

XRO

  • MCP in XTD 10 has been removed. Also the M2 has been removed. The reference positions will be lost when the components are back (14.01.).

XPD

  • Screens in SASE3 are being installed. Venting of the line is being coordinated with the vacuum group. No reference positions lost is expected.

VAC

  • CRL in XTD 9 will be removed and stored in a labeled box, waiting to be installed in the SPB hutch. This will happen after the winter shutdown. Procedure to safely handling the berillium lenses is being finalized with Safety.

AE

  • Once the power in SASE1 XHEXP1 is back AE needs 1 day to bring the electronics back.

EET

ITDM

DET

CAS

  • Hotfix is being prepared. This will solve issues in the config tables related to units.
  • Deployment schedule is being updated (inc. deployment of 2.3.1. in SASE2)

AoB

  • General interest precutions concerning components should be circulated, if any, by the responsible groups in view of the holyday period.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Dec 2018, 10:17 

SPB/SFX

  • Radiation damage tests were successful. 
  • Instrument is set for the power cut.

FXE

  • According to the information available to AE the instrument should be set up. 

SQS

  • Successful users run in the last 2 weeks
  • Some interlocks need to be activated. Discussion with AE ongoing
  • Loops updates to be discussed/executed plus CR status will be checked
  • Triggers requests are being sicussed with BF

SCS

MID

  • Cabling ongoing

HED

  • Loop 1 will be operative probably today. CAS support for creation of scenes has been asked.
  • Cabling ongoing.
  • Additional Racks in A27 have been installed

OPT Lasers

  • As soon as the system is ready for the power cut in SASE1 a mail will be sent  to PSPO.

XRO

XPD

VAC

AE

  • XTD6 crate 219 has to be rebooted.

EET

ITDM

  • Maintenance and updates (e.g. online clusters ) has started  as indicated in the shutdown activities planning. Should go on until the end of the week.

DET

CAS

  • 2.3.1. will be deployed in SASE3 tunnels today
  • Schedule for 2019 has been circulated by HS to the readiness mailing list

AoB

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 10 Dec 2018, 09:50 

SPB

FXE

  • Timing tool has been tested during the week end. 
  • PP laser inch modes have been tested with the Gotthard detector.
  • Intra/inter train gitter test results being analyzed.
  • APG mode of the digitizers had issues. Experts from AE will be contacted.

SQS

SCS

MID

  • AGIPD saw light. Support groups, in particular AE and DET were thanked.
  • Beam stop saw also light. 
  • Small issues have been / are being fixed: leak of the silicon oil pipe, timing issues.

HED

XRO

XPD

  • CAS will run some test in SASE3 for the diagnostics after the latest time server development.

VAC

AE

  • PP laser motors issue reported onm friday has been investigated. It seems that the motor was emchanically stuck and it was possible to implement a workaround (more power fromt he controls) to make it work. It needs to be further investigated in the shutdown.

  EET

ITDM

DET

CAS

  • 2.3.0. has been released. Hot fix for minor issues (e.g. back compatibility of the GUI) is being prepared. This does not affect the tests made by AE, DET and ITDM
  • FOr sase1 PLC data has been recorded in preparation to the power cut.

AoB

Power cut in SASE1  

  • The plan is to cut the power in SASE1 in the XHEXP1 on Wednesday 12.12. around noon.  This will only happen after PSPO will receive feedback from AE, ITDM, FXE, SPB and Optical Lasers that everything is in a safe state.
  • The power could come back on Thursday (13.12.) morning if no problems occur.
  • The normal light could be affected. In any case the emergency lights and Radiation lights will be working. Working in SASE1 hutches and Rackrooms in this light condition is not safe w/o additional light and the suggestion is to postpone the activities when the light is back.
  • If the time plan needs to be changed due to the radiation damages tests being delayed, the relevant parties will be informed by PSPO.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 05 Dec 2018, 11:41 

SPB

  • pulse arrival time measurements to be done this week.
  • second Gotthard detector small issues being fixed (online data viewer fixes - ongoing)

FXE

SQS

SCS

MID

  • Loop 10 partially needed. Smaract stages are working withing loop10 since yesterday

HED

XRO

XPD

VAC

AE

  • AE agreed to power down the PLCs in SASE1 experiments and optical laser before the power interruption. Dates are being rediscussed since radiation damages tests are foreseen for Monday and Tuesday! (10-11.12). TBC.
  • The synch of the Gotthard detectors with 1 trigger does not work for long trains (synch is lost). Multiple triggers are needed and also possible (AGaller is already using them). AE can give support also to the other users.

  EET

ITDM

DET

  • SCS fast CCD temperature drift issue being addressed.

CAS

  • Tests of the 2.3.0. Karabo version are ongoing.  Karabo update for SASE1 will be deployed after the  PLCs are back again (ca. 2 days after the power is back). Proposed date by CAS is 19.12. but needs to be discussed again once the power is back.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 03 Dec 2018, 11:45 

SPB

  • pulse arrival time measurements to be done next week.
  • second Gotthard detector small issues being fixed

FXE

SQS

  • Successful experiments during the WE

SCS

  • Z-motion issue for the fast CCD. Has to be checked again with AE today

MID

  • Loop 7 is running
  • This week light is expected on the AGIPD
  • Mono commissioning issue: the pico motors position is not reproducible. ==> motor is now stuck, needs to be replaced.
  • Loop 10 partially needed. To be discussed with AE

HED

XRO

XPD

VAC

AE

  • The synch of the Gotthard detectors with 1 trigger does not work for long trains (synch is lost). Multiple triggers are needed. AE is looking into that involving A. Galler since he is an advanced user of the Gotthard. The solution will then be deployed to all the detectors.

  EET

ITDM

 

CAS

  • Tests with AE/ITDM ongoing. In the new version of Karabo/DAQ the filtering of slow data for device will be included.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 28 Nov 2018, 10:18 

SPB

  •  commissioning ongoing
  • Radiation test was not successful since the beam diameter was smaller than expected. 

FXE

SQS

SCS

MID

  • Loop 7 will run by today evening
  • Mono commissioning issue: the pico motors position is not reproducible. ==> the issue solved by itself. Tests ongoing.
  • AGIPD commissioning is ongoing. 

HED

XRO

XPD

VAC

AE

  • In sase3 the y axis of the nano motion system (sample environment) does not work properly uinder vacuum. JTolkien and C Dieter are on the issue.

EET

ITDM

 

CAS

  • Release tests ongoing. Release candidate being tested with AE.
  • OCD for SASE3 users experiment has been set up

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 26 Nov 2018, 10:35 

SPB

  • KB system commissioning ongoing
  • Agipd commissioning stopped
  • Radiation tests preparation ongoing.

FXE

SQS

SCS

MID

  • TueV Test successful.
  • Mono commissioning issue: the pico motors position is not reproducible. This is a show stopper for the Monochromator commissionig. Not clear whether also FXE has the same kind of problem. AE has been informed and will try to support taking into account also the requests by SASE3 for this week (commissionig for the users run)
  • AGIPD commissioning is ongoing. Chiller has to be replaced due to a leak.

HED

  • TueV Test for the optics hutch successful
  • Cabling ongoing. 
  • Fw export and crates/loops preparation ongoing
  • Screen is needed for first beam.

XRO

XPD

VAC

AE

  • OCD: intervention request during the WE to fix a train id issue. Should be ok now but the problem still needs to be reproduced and undertstood.

ITDM

  • Network intervention needs to be planned for the beginning of January. KW is clarifying the details. Will be included in the shutdown planning.

CAS

  • Release tests ongoing. Small issue with the DAQ has been found. Fix already in place. Final tst of the fix is being performed. 

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 21 Nov 2018, 10:13 

SPB

  • KB system and AGIPD commissioning ongoing

FXE

SQS

SCS

MID

  • TueV Test ongoing.
  • Mono commissioning to be done this week.
  • Loop 7 is needed for the middle of next week. As of now no fw export and cables for this loop appear to be there. AE/EET will have to check whether this makes sense.
  • AGIPD commissioning:
    • It seems that some cables needed for the loop 11 were not connected and some other are not yet installed. ILobato and K. Sukharnikov are now dealing with the issue. This delays the foreseen plan. The mitigation strategy for the missing cables issue is to have a list with these specific cables and ask Fa. Schulz to put these hight priority. It already worked with other cables/connectors. Discussion MID/EET/AE needed.
    • uTCA crate is now operational.
  • It is pointed out by CAS (C.Y.) that component having priority concerning cables and loops operation are AGIPD, DES, PDS, Mirror.  It has to be checked whether these are aligned with the actual priority list for loops and cables discussed with MID. 

HED

XRO

  • in XTD10 horizontal slits were moved to better scan the beam.

XPD

VAC

  • in XTD9 the B4C aperture in front of the monochromator grating was changed to a larger one. 
  • in XTD10 the current amplifiers for the XGM were successfully changed.

AE

  • OCD: intervention request during the WE to fix a train id issue. Should be ok now but the problem still needs to be reproduced and undertstood.

ITDM

CAS

  • Release tests with ITDM ongoing.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Nov 2018, 10:39 

SPB

  • Gotthard needs to be tested.
  • Pulse picker will be used and commissioning still has to be done.
  • Sample chamber encoder drift issue. Has to be investigated further. 

FXE

SQS

  • Beam during last WE: no major issues
  • Interlocks will be updated tomorrow
  • Some issues concerning direction of motors need to be fixed with AE.
  • AVC300 valve. Firmware will be available this week.
  • Digitizers and photonics camera are needed. Work ongoing

SCS

  • Motors for the Fast CCD cameras are not working properly and interlock about pressure for the detector is needed ==> Loop 7 needs to be updated, AE will take care of that.
  • When the CCD will inject data into the DAQ ITDM will be informed.
  • There was a request to CAS to provide values for the Monochromator at a rate faster that 10 Hz. This requires evaluation of the feasibility by the experts (CAS/AE). For the time being the middle layer will not be changed. 

MID

  • AGIPD commissioning:
    • Loop 11 needed. Today tests by AE. Until Tue. evening all the intelock tests should be done. From Wed. on operation.
    • uTCA crate needs to be operational too. According to AE can be done.
    • Thu. on: DQA tests.

HED

XRO

  • Temporary solution concerning Karabo topics management to alllow the reading of the Monochromator values by SCS. The definitive fix will come in the future.

XPD

  • XTD10 XGM repaired
  • XTD1 ph. science camera was replaced with the one previously installed in SASE1. Repair ongoing.
  • the company went bankrupt and was bought by a new company. For info contact A. Koch.

​​VAC

AE

  • OCD: intervention request during the WE to fix a train id issue. Should be ok now but the problem still needs to be reproduced and undertstood.

ITDM

CAS

  • Release tests with ITDM ongoing.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 14 Nov 2018, 10:23 

SPB

  • Lopp 5 update - will be agreed between SPB and AE
  • Smaract limit switches issues - AE will have a look. In the meanwhile also the company of the controlles has  been asked by SPB
  • KB motor steps have different size with respect to encoders. This issue is known and a workaround / solution has to be discussed with AE offline
  • Pulse picker will be used and commissioning finalized.
  • Sample chamber encoder drift issue. Hasx to be investighated further. AE can support.

FXE

SQS

SCS

MID

HED

XPD

​​VAC

AE

  • MID Loop 11 - Fw received. Being tested.
  • PLCs for optical lasers in SASE3 and 2 control being set up
  • SASE3 support for commissioning ongoing 

ITDM

CAS

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Nov 2018, 09:55 

SPB

  • More interlock updated will take place this morning.

FXE

  • Supporting the diagnostic and optics group for the testing of the beam feedback mechanism. 
  • A.Galler was informed by CAS (Vajid) that a Karabo update was requested to CAS last friday late afternoon. The update was stopped by FXE, but to avoid this in the future communication between the cvarious groups has to be improved.

SQS

  • Beam during the WE. NO issues.
  • Imaging processors are being used for cameras. There are issues with the averaging. CAS is informed.
  • Various loops updates needed. Will be agreed offline with AE.

SCS

MID

  • Loop 11 could be ready by next week. Today the FW export by EET is going to be available to AE.

HED

XPD

 

​​VAC

AE

TDM

CAS

  • Karabo 2.3 is now a release candidate. Testing starts today (2.5 wks internal tests). Info about new features of the 2.3. release are available on the white board in front of the mockup control room.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 Nov 2018, 10:44 

SPB

  • Karabo was updated yesterday. Test is ongoing. So far no issues.
  • The macros for cooling down and warming up the detector do not work properly. If the button is pushed twice the setpoint changes continuing e.g. cooling down too much. Marcin will bring the issue up with CAS (HS).

 

FXE

SQS

SCS

  • Issue was found with Elmo controllers crates: due to a problem in the EPLAN macro the ground is not connected to the motor cables. The mitigation strategy will be discussed by PG, LW, MF and MT in a meeting.

 

MID

  • AGIPD will move in the hutch today.
  • PCs are being installed. Karabo need to be deployed.

HED

XPD

 

​​VAC

AE

TDM

CAS

  • Karabo 2.3 is now a release candidate. Testing ongoing.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 05 Nov 2018, 12:25 

SPB

FXE

SQS

  • Crates for Loop12 have been installed. Loop will probably run by today or tomorrow.
  • Loop 2 and 3 need to be updated because of interlock definitions.
  • Issue with  valves behavior in Loop 3 and 5. AE will check.
  • Encoder w/o 5 V. BB checks.
  • Pfeiffer Motor valve issue will be fixed by next week.

SCS

 

MID

  • AGIPD will move in the hutch this week. Preparation ongoing.
  • Loop11 will be ready early next week

HED

XPD

  • Several tests planned for the end of the week, including the feedback device by CAS. PRCs will be made aware of the activities in the tunnels.

VAC

AE

  • PPL update in SASE1 today.
  • Update of the Loop 5 (AGIPD) tomorrow

ITDM

CAS

  • Issues in the calibration pipeline will be coordinated with the relevant groups (DET, AE) before and during the next chapter's meeting.

AoB

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 29 Oct 2018, 13:25 

SPB

  • A smaract stage sensor had issues. The behavior changes whether the chamber is pumped down or not. The Issue is being addressed by AE.

FXE

  • Users are acquiring data with the Jungfrau detector. It is a success so far.
  • Successful users shifts.

SQS

  • Configuration of some motors is incorrect. BB looking into that.
  • It is required to change the sampling rate of the digitizers. CAS is on it.
  • MPOT issue: control is lost as a power supply channel trips. CAS: a fix exists, needs to be deployed.
  • Note from NC(AE): one has to check that the parameters and information written in the CRDs are consistent with what is being used in reality. This would make the time of the OCDs more efficiently used.

SCS

  • Interlocks tripping too easily: CAS will show SCS how to change the thresholds.
  • KB coordinated motion: bug has been reproduced by cas. Fix ongoing.
  • Full control of the scroll pumps still not possible. AE is working on it.
  • Loop 13 will be fixed (miswiring problems)

MID

HED

XPD

VAC

AE

ITDM

  • Issue with the office netword socket in D.09. Fixing ongoing. In general all the operation critical devices have to go to the control network sockets to avoid such issues.
  • Request from HS to add the generic XFEL unix user to the special group of doocs to change the bunch pattern. This has to be first discussed internally to CAS. AS will come back to KW and the others involved players as soon as this has been clarified in CAS.

 

CAS

  • CAS need  a time window to deploy and test the fix for the Lima Basler cameras in XTD6. No feedback since last friday. A.Koch tries to find out a possible time window and come back to ASIlenzi.

AoB

Groups are reminded to send GW (PSPO) the activities planned for the winter shutdown.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 24 Oct 2018, 11:25 

SPB

FXE

  • During the last users run there was a loss of optical laser. This was due to a mistake in CAS. Has been clarified already. It is pointed out by FXE that one should avoid  working on e.g. the control system during the users period. This is however, not always possible and a mitigation strategy is needed and requires discussions.
  • Successful users shifts.

SQS

  • Issues with motors have been fixed.
  • Loop 3 will be probably updated today.
  • In general several loops need to be updated, will be coordinated with SQS.
  • SQS has the night shift today. Eventual tests have to be done today during the day.
  • Motor valve can be implemented in the controls next week.
  • Would be nice to have the GATT pressure in our DAQ system. CAS is looking into that.

SCS

  • KB coordinated motion has been improved

MID

HED

XPD

VAC

AE

ITDM

AoB

Another issue related to the non independency of interlocks between the SASEs: FXE waiting for pulse on demand. In the meanwhile in SASE3 the pressure in the GATT increases and the apertures go in to keep the pressure high. As designed, the interlock stopps the beam for 1 or 2 seconds, but also in SASE1. FXE loses the pulse on demand. 

It is clear that this is a complex environment and finding a solution requires time and the experts both on the desy side and XFEL side (e.g.AE, CAS) on the table.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 22 Oct 2018, 13:46 

SPB

  • Issues with the detectors pipeline occured (also for FXE). In the future a test button to check the status of the pipeline wil be implemented.

FXE

  • Pulse on demand pump and probe experiment successfully performed.
  • The support groups got  the Jungfrau detector working for the users run. 
  • VAC sample environment  working.

SQS

  • MPS conditions update: Loops will be restarted tomorrow. Tests to then be done in the afternoon and on Wednesday.
  • Loop 4 and 5 motors need to be updated . To be discussed with AE when is the best time.
  • Pulse on demand capability needed. SQS will contact the CAS contact person.
  • Ph. Science camera can be connected again.

SCS

  • First shifts succesfull. Support from the support groups is appreciated.
  • DAQ groups that have been overlooked are now needed. ITDM asks SCS to send a ticked with the request and the required excel sheet.
  •  ITDM also points out, that only DAQ groups that have been already properly commissioned should be used during night shifts.
  • Minor problems with gauges. Will be discussed with AE.
  • Problems with motors (sometimes they work, sometimes not) has to be discussed in details with AE.

MID

 

HED

XPD

VAC

AE

ITDM

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 17 Oct 2018, 10:10 

SPB

  • KB motors issue: the motors do not go to the proper position. This has been communicated to AE. Analysis of the problem and fixing ongoing.

  • The leak of the AGIPD colling pipe has been fixed but the connectors were not cleaned since this requires time. It was decided to operate the detector and postpone the cleaning to the next shutdown.

  • Software update for the AGIPD should now avoid problems with the configuration of the detector.

FXE

  • Pulse on demand pump and probe experiment successfully performed.
  • The users would request the Jungfrau detector working for friday. Tomorrow there will be a meeting with FXE, DET,AE and the users to manage the expectations and discuss what can be delivered in terms of detector performances.
  • Von Hamos spectrometer motors sometimes go out of service. The origin of the problem is not clear. AE will investigate.

SQS

  • MPS conditions update: Loops will be restarted next tuesday
  • Issues concerning the motors of the newport stages have been fixed.

SCS

  • Coordinated motion does not work properly. The bug identification and fixing will be done offline in the lab. TF is preparing the test environment with 2 stages and Elmo controls. AE/CAS involved.

MID

 

HED

XPD

VAC

AE

ITDM

AoB

  • Yesterday a HZDR electrician had an electircal accident working in A23. He only got a burn, but he is fine. The accident report is being filed. After A23 has been checked it was opened again for the laser people. 
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 15 Oct 2018, 13:39 

SPB

  • Issue with the detector cooling pipes during the week end required intervention. Now fixed.

  • Commissioning ongoing.

  • Interlock definitions to be deployed probably tomorrow.

FXE

  • Pulse on demand capability successfully tested
  • Issue with the DAQ: crush of data aggregators. ITDM OCD has been notified and the issue is being investigated.
  • The users would request the Jungfrau detector working for friday. FXE asked for feedback about the status of the detectors integration to DET, CAS, ITDM. The feedback is needed to inform the users.

SQS

SCS

MID

  • Loop 4 is waiting for ion pumps cables to be commisisoned. as soon as the cables are there AV will inform CY and MID.

HED

XPD

VAC

AE

  • SQS/SPB interlocks will be propbably deployed tomorrow.
  • SASE3 master loop will be updated tomorrow.

ITDM

  • ITDM needs to know until when the photon commissioning in SASE2 tunnels is ongoing to update the DAQ servers. The information should come from HSinn or PRCs, who are not at the meeting. JS will try to contact them directly.  ==> HW was updated but still with the old configuration. Moving of data services to new aggregators needs discussion.

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 10 Oct 2018, 10:40 

SPB

  • Problems with the GUI not being accessible after update solved with the CAS OCDs 

  • Loop 5 and Master loop will be updated today. New MPS conditions included.

FXE

  • No issues

SQS

SCS

  • KB coordinated motion control has issues. CAS will ttry to reproduce the bug to make sure it's not Karabo related and eventually pass the issue to AE

MID

  • Loop 1 tech. commissioning done. Loop 4 is waiting for Ion pump cables to be delivered by Schulz.
  • Loop 2 and 5: beckhoff crates installed. As soon as it is needed the firmware can be uploaded.

HED

XPD

VAC

AE

  • SASE3 EPS loop being updated to comply with the new D3 directives. EPS being updated. Then final tests needed.

ITDM

  • ITDM needs to know until when the photon commissioning in SASE2 tunnels is ongoing to update the DAQ servers. The information should come from HSinn or PRCs, who are not at the meeting. JS will try to contact them directly.  

CAS

  • To preventy the copy of entire projects with all the relative subprojects and additional problems, the GUI servers in SASE2 have been updated. This is being done also for the other beamlines.
  • The milestones of the SASE2 Technical commissionig Task Force headed by CY have been achieved. Starting from today CY is no longer taking care of the SASE2 tunnel activities planning and coordination. It has to be discussed in the Friday meeting how to go on, since the planning and coordination of the shutdown activities is needed.
  • Concerning the SASE3 radiation protection issue in the tunnel, it is stated that CAS are implementin the requested software solution, although Karabo was not designed to manage personal safety functions. To this aim, it is needed to understand whether the concept is going in the right direction. The large scale issue is being managed by Safety (ZA). A report about the situation will be given on Friday by THaas.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 08 Oct 2018, 10:37 

SPB

  • Ready for users.

  • DAQ tests to be done on the SPB side.

  • MPS definitions being defined.

FXE

SQS

  • Loop 7-10-14 are running. 13 and 12 to come.
  • Crates for the loops 1/4/5 have been/are being modified.
  • Interlocks definition update. NJ, BB and SQS are clarifying the requirements.
  • Interlocks not working for the loops 3 and 5. Info sent to AE. Being worked on.
  • Still no beam available

SCS

MID

  • No issues.

HED

  • Beam in XTD6
  • Some CRLs arms are deactivated to avoid accidentally focusing on the shutter.

XPD

VAC

AE

  • MPS update for SPB is ready and has to be done. This includes the interlock definition for the detector's z motion.==> being reviewed by SPB.\
  • SASE3 EPS loop being updated to comply with the new D3 directives. Today a test with Z.Ansari will be performed.

ITDM

CAS

  • To preventy the copy of entire projects with all the relative subprojects and additional problems, the GUI servers in SASE2 will be updated. Only 1 server is running at the moment.
  • The milestones of the SASE2 Technical commissionig Task Force headed by CY have been achieved. Starting from today CY is no longer taking care of the SASE2 tunnel activities planning and coordination. It has to be discussed in the Friday meeting how to go on, since the planning and coordination of the shutdown activities is needed.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 01 Oct 2018, 10:49 

SPB

  • Maintenance of the AGIPD ongoing.

FXE

  • No issues to report.

SQS

SCS

MID

  • Loop4 is ready but after the electrical shutdown form last week the PLCs racks aha to be re initialized (not powered right now). This is done by AE and is ongoing.

HED

  • HR mono commissioning ongoing. Being pumped down.
  • Pulse picker tested. Logic has to be slightly changed. CR will come soon. 

XPD

  • FXE diamond screen for beam position measurements  has been installed in XTD9. Section being pumped this week.

VAC

  • 3rd mirror chamber  in SASE2 being pumped now.
  • XTD6 all vacuum gaps are closed.
  • FXE MONO will be pumped probably on Wednesday

AE

  • SASE3 Master loop has to be updated. 
  • MPS update for SQS being worked out. Conditions have been clarified with SQS.
  • MPS update for SPB is ready and has to be done. This includes the interlock definition for the detector's z motion.

ITDM

  • Commissioning SQS - CAS support needed to configure the DAQ for the cameras.
  • DAQ links for Basler cameras in MID are needed. This will be done asap.

CAS

  • 2.2.6. hot fix will be released probably today. It will include fixes for the DAQ middle layer device.

AoB

Status of the redundant power for the racks in the SASEs according to Technical Services:

  • All the works have been successfully done: the foreseen racks get now 2 working redundant power lines.
  • The power is back and no further interruptions are planned/needed.
  • This week a visual inspection and relative "Abnhame" will take place, without any actual electrical works being involved.
  • All eventual / additional interventions will be scheduled for the winter shutdown.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 26 Sep 2018, 10:42 

SPB

  • Maintenance of the AGIPD ongoing.

FXE

  • Beamtime was successful
  • FXE imagers cannot be seen by the people in the BKR and that's a problem to efficiently communicating with them about e.g. beam stability issues. According to CAS a Karabo client is available for that purpose. The issue should be addressed by the PRC with the help of CAS. 

SQS

  • Interlock definitions - clarifications with AE ongoing.
  • Loop 7-10-14 being deployed
  • Some crates for the first loops were taken off for modifications. They will be back this week.
  • Trigger signal has to be provided by AE. TB will ask BF today.

SCS

  • Some cables for XGM had to be pulled last minute. In the XGM foreseen crate there was no space for additional terminals and another BKF module was chosen. Now some cables are too short. MTeichmann will adress the issue to the EETf
  • Fast CCD interlock definitions: MT will check whether SCS is on schedule. Info needed by the DET group.
  • Digitizers expected this week. 
  • DAQ tests will be done.

MID

  • Loop4 is working now. VAC section being pumped.
  • Request to CAS for GUI training. Training will be announced for the 04.10.

HED

  • HR mono commissioning ongoing. Some switches will be recabled now by KS. Has to be done asap. Motors direction has been checked and is correct.
  • Pulse picker will be ready tomorrow. ==> Since all the tunnels are open at the same time, there is a conflict of resources pointed out by CAS.

AE

  • SASE3 VAC loop will be updated again today, then SASE2 VAC
  • MPS update for SCS and SQS being worked out. Today updates will be ready.
  • FXE MONO the damaged crates will be changed and loop will be update today. Commossioning starting as soon as teh motors are replaced (today or tomorrow)
  • Scroll pump feedback issue: the feedback signals coming from the controllers were not correctly read. AE foud a solution and already presented a CR fo fox the crates.==> the time slot has to be agreed with SQS and SCS.
  • New framework should be deployed forst in the SA2 tunnels. Will be discussed offline with CY.

ITDM

CAS

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Sep 2018, 09:58 

SPB

  • Last monday shift was cancelled since there were prooblems with the cooling of the AGIPD. Not possible to reliably cool it down. Maintenance of the cooling units plus investigation of the controllers ongoing.

FXE

SQS

  • Interlock definitions - clarifications with AE ongoing.
  • Loop assignment changed. Next loop to be brought up is Loop 10 (probably by next week by Hazem)
  • Network storage for the control PCs in the control room. Discussion ongoing (data policy, accesibility...). Is being done offline and will be reported to a larger audience when clarified.

SCS

  • Interlock definitions being finalized. Update of the loops will be done soon.

MID

  • Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. No major issues.
  • Loop4 needed for next week.
  • Request to CAS for GUI training. CY and AS have to clarify who organizes that in CAS. CY understanding is that Hugo Santos is going to do it. Will be discussed offline.

HED

  • Rack 2.19 shows messy cabling. KS will contact UBrueggmann to understand who is responsible for the devices in the racks. 

AE

  • This week all the modified crates for SCS and SQS will be reinstalled and loops updated by BB

ITDM

  • The upgrade of the DAQ in FXE was postponed to the next week on request from FXE.

CAS

  • Karabo 2.2.5. patch being released today

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 17 Sep 2018, 10:19 

SPB

  • Bug in the AGIPD cooling macro (setpoint resets itself to -59 C)  -  Jola knows about the problem. AS: Macro will be fixed.

  • AGIPD dark calibration: when new darks were injected with calling Steffen's script "xfel-calibrate",  error message "Disk quota exceeded" popped up caused by a GPFS-related issue -> issue was solved. In general the script was not tested (scratch space was used!). One should not release script without ITDM knowing and haveing thested it before. 

FXE

  • Commissioning going on in the last days. Not able to get 14 keV beam for next users experiments. They will stick with 9.3 keV.
  • Karabo stability issue (GUI) reported in the commissionig logbook.

SQS

  • Problem with the digitizers bandwidth has now been solved.
  • Loop 6 running w/o smaract stages.
  • Flow switches issues solved . Rewiring of PLC needed
  • Pfeiifer flow valves ready to be stested this week.
  • Loop assignment changed. Change request handed in. As soon as it is approved it will be clear what loop to bring up next.

SCS

  • Loop 7 is running. Needs to be connected to Karabo.
  • Loop 8 running too.
  • Readiness of loop 1 and 4 ==> Interlock conditions need to be implemented. 
  • It is unclear whether the homing capability has been implemented already and can be used. Discussion ongoing. The use case has to be clarified.
  • Network storage for the control PCs in the control room is requested. Scope definition and discussions with CAS and ITDM will be done offline.

MID

  • Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. This week Slit and ATT will be commissioned. No big issues so far.
  • Loop 4 being prepared by AE. Will be ready next week.

HED

  • Work in tunnel ongoing
  • HRMono- ready to start grouting. Mono will be here next week.

DET

  • FXE/SPB GPUs crash issue  - to be checked with ITDM - ITDM was not contacted.

ITDM

  • DAQ was upgraded to the user friendly version in SASE3. After having discussed with FXE in the meeting, it was decided to install it also in FXE. 
  • DAQ training requested by SQS

CAS

  • Karabo 2.2.5. patch being prepared. Will solve minor bugs and the crash due to empty data files.
  • 28 Mpot update requests were received by CY. Need to be planned and coordinated with H.Santos.

 

    Reply   Re: Status report after dispatch meeting 09.30, posted by Dennis Goeries on 17 Sep 2018, 14:30 

The GUI crashes reported by FXE will be fixed with the hotfix release coming ~tomorrow.

It is related to very high or low values in plotting widgets scratching the maximum floating point number (1e308 ~ infinity).

-- Wajid & Dennis

 

Adriano Violante wrote:

SPB

  • Bug in the AGIPD cooling macro (setpoint resets itself to -59 C)  -  Jola knows about the problem. AS: Macro will be fixed.

  • AGIPD dark calibration: when new darks were injected with calling Steffen's script "xfel-calibrate",  error message "Disk quota exceeded" popped up caused by a GPFS-related issue -> issue was solved. In general the script was not tested (scratch space was used!). One should not release script without ITDM knowing and haveing thested it before. 

FXE

  • Commissioning going on in the last days. Not able to get 14 keV beam for next users experiments. They will stick with 9.3 keV.
  • Karabo stability issue (GUI) reported in the commissionig logbook.

SQS

  • Problem with the digitizers bandwidth has now been solved.
  • Loop 6 running w/o smaract stages.
  • Flow switches issues solved . Rewiring of PLC needed
  • Pfeiifer flow valves ready to be stested this week.
  • Loop assignment changed. Change request handed in. As soon as it is approved it will be clear what loop to bring up next.

​SCS

  • Loop 7 is running. Needs to be connected to Karabo.
  • Loop 8 running too.
  • Readiness of loop 1 and 4 ==> Interlock conditions need to be implemented. 
  • It is unclear whether the homing capability has been implemented already and can be used. Discussion ongoing. The use case has to be clarified.
  • Network storage for the control PCs in the control room is requested. Scope definition and discussions with CAS and ITDM will be done offline.

MID

  • Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. This week Slit and ATT will be commissioned. No big issues so far.
  • Loop 4 being prepared by AE. Will be ready next week.

HED

  • Work in tunnel ongoing
  • HRMono- ready to start grouting. Mono will be here next week.

DET

  • FXE/SPB GPUs crash issue  - to be checked with ITDM - ITDM was not contacted.

ITDM

  • DAQ was upgraded to the user friendly version in SASE3. After having discussed with FXE in the meeting, it was decided to install it also in FXE. 
  • DAQ training requested by SQS

CAS

  • Karabo 2.2.5. patch being prepared. Will solve minor bugs and the crash due to empty data files.
  • 28 Mpot update requests were received by CY. Need to be planned and coordinated with H.Santos.

 

 

Entry   , posted by Adriano Violante on 14 Sep 2018, 13:38 
 
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Sep 2018, 14:52 

SPB

  • Testing of the 4 images preview mode for AGIPD will be done today.
  • Interlock definitions are being updated. Loop update will be done after the users experiments.

FXE

  • ​No issues to report

SQS

  • Problem with the digitizers bandwidth has been addressed by AE. ITDM has to reconfigure the DAQ. ==> Some issues still present. It seems because of lack of communication.  AE/ITDM/CAS/SQS meeting tomorrow to clarify.
  • Loop 6 being prepared. A couple of issues with Smaract and Technosoft controllers have to be addressed with the involvement of AE and CAS. ==> Still ongoing.

SCS

  • Loop 7 is running since this morning. More loops needed.
  • Missing crates for Loop 1 and 4 are finishing to be tested and will be installed back soon (Loop 1 crate already today). 
  • It is unclear whether the homing capability has been implemented already and can be used. AE to check. 

MID

  • Loop 1 still not deployed and needed. Plan is to commission the MID Opt hutch until the end of next week.

HED

  • Work in tunnel ongoing
  • CRL to be tested today
  • HRMono- ready to start grouting.

DET

  • FXE/SPB GPUs crash issue  - to be checked with ITDM

XRD

  • MCP in SASE2 have problems and the section has to be vented. The detector will be replaced on 23rd of Sep.

ITDM

  • Office network switches will be upgraded. Intervention cancelled! Will be probably done in the Winter shutdown.
  • DAQ to be upgrade to the user friendly version also in SASE3. ITDM to ask FXE whether they also want it.

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 10 Sep 2018, 10:33 

SPB

  • DAQ was updated and no big issues were found.
  • Some issues are being discussed with CAS and ITDM. Among them also the request to add more channels to the DAQ.
  • Interlock definitions are being updated. Discussions with AE ongoing.

FXE

  • ​The beam position at 14 keV  was significantly changed (horizontal offset by ca. 600 um) with respect to the position used before at 9.3 keV. The realignment of the beam took time. Test with LPD will be done today if no other issues with the beam are found.

 

SQS

  • Loop assignments will be re-checked with EET and NCoppola. After that the decision about what loop to bring up after Loop 6 will be made.
  • Problem with the digitizers bandwidth has been addressed by AE. ITDM has to reconfigure the DAQ. 
  • 4 uTCA boards (For the reaction microscope from the University of Frankfurt) are found to be wrong: the firmware seems to be incopatible with the intergration in Karabo. ==> AE confirmed that a different firmware can be uploaded and this will solve the compatibility issue with Karabo.
  • Loop 6 being prepared. A couple of issues with Smaract and Technosoft controllers have to be addressed with the involvement of AE and CAS.
  • New interlock definitions list hase been sent ot AE.

SCS

  • Interlock definition were sent to AE by M. Izquierdo. M. Teichmann is discussing the new interlock definitions with Nerea Jardon. 
  • FAst CCD interlock definitions being discussed with the detector group.

MID

  • Loop 1 can be probably deployed today

XRD

  • As already reported on Friday, In sase 3 tunnels the new interlock definitions do not affect the imagers, that remain unprotected from high intensity beam. This will be discussed by XPD with HS this week.
  • Reflection on the imagers issue: a solution involving a new coating has been found. If you have this problems, please contact AKoch for the implementation of the solution.

CAS

  • MPOT power supplies: CY got feedback from DET, SPB, SQS, SCS. Next monday a mail with the scheduling of the activities will be sent.
  • Eventual requirements for features to be implemented in the next Karabo release should be sent and discussed with CAS.

ITDM

  • Office network switches will be upgraded. Please refer to the previous entry in this logbook for the details.

HED not represented.

Entry   switch software update - ITDM request, posted by Adriano Violante on 10 Sep 2018, 09:12 

The office switched reported below have to be upgraded. Some of them belong to accelerator and some to us. Below you find the detailed list of the switches and the time schedule (assuming everything runs fine) for the update. ITDM needs feedback the latest today evening.  

if you see problems with the upgrade, please reply to this e-mail. If we do not receive complaints until this evening, we assume that everything is fine.

 

 

Monday, 24.09.2018, 06:00 - 08:00 am:

sw-hh-al-324.desy.de    XFEL_XHEXP1_SASE2_A21.UH3.03

sw-hh-al-325.desy.de    XFEL_XHEXP1_SASE2_A22.UH7.02

sw-hh-al-323.desy.de    XFEL_XHEXP1_SASE3_E21.UH2.03

sw-hh-al-322.desy.de    XFEL_XHEXP1_SASE3_E22.UH3.01

sw-hh-al-274.desy.de    XFEL_XHQ.1.174

sw-hh-al-298.desy.de    XFEL_XSDU1_UG01.001_R01_3175m

sw-hh-al-295.desy.de    XFEL_XTD1_SA2.R002_R26_2238m

sw-hh-al-296.desy.de    XFEL_XTD1_SA2.R005_R16_2384m

sw-hh-al-297.desy.de    XFEL_XTD1_T3.R007_R33_2500m

sw-hh-al-299.desy.de    XFEL_XTD1_T3.R010_2.1_2581m

 

Tuesday, 25.09.2018, 06:00 - 08:00 am:

 

sw-hh-al-287.desy.de    XFEL_XTD10_3.13_3297m

sw-hh-al-285.desy.de    XFEL_XTD10_3.4_3141m

sw-hh-al-286.desy.de    XFEL_XTD10_3.7_3209m

sw-hh-al-290.desy.de    XFEL_XTD2_T4.R009_R14_2590m

sw-hh-al-293.desy.de    XFEL_XTD3_T5.R005_R01_2846m

sw-hh-al-292.desy.de    XFEL_XTD3_UN1.R002_R16_2740m

sw-hh-al-288.desy.de    XFEL_XTD4_SA3.R001_R27_2838m

sw-hh-al-289.desy.de    XFEL_XTD4_SA3.R002_R48_2888m

sw-hh-al-291.desy.de    XFEL_XTD4_T4D.R006_R19_3057m

sw-hh-al-294.desy.de    XFEL_XTD5_UN2.R001_R04_2972m

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 05 Sep 2018, 12:19 

SPB

  • DAQ will be updated today by ITDM to make it more user friendly.
  • Smaract stages issue. Only 2 out of 10 are not working. For the planned experiments these are more than enough. The last 2 will be finxed at the end of the month.

SQS

  • While Cyril is not here the CAS contact person for SQS is Juri.
  • SQS would like to meet with ITDM to discuss how to make the DAQ interface more users friendly. KW reminds that on one side, the update being deployed in SPB helps, on the other side people should get proper training, and for SQS this did not happen so far. SQS will send a list of people who need training to ITDM.
  • Problem with the digitizers bandwidth is being addressed by AE. but was not known by CAS. Juri has to be involved in the discussion.
  • 4 uTCA boards (For the reaction microscope from the University of Frankfurt) are found to be wrong: the firmware seems to be incopatible with the intergration in Karabo. AE will check it.

SCS

  • Working together with BB to fix the issues with Loops.
  • Loop 4 being brought to life, as well as Smaract stages.
  • Interlock definition were sent to AE by M. Izquierdo. M. Teichmann did not know that and pointed out that Manuel is no longer an SCS member and thanks to this meeting he got the information. Has to be clarified.

MID

  • Today at 14:00 in XTD 6 the technical commissioning of imagers will be carried out . ILobato will attend.
  • First 2 loops for the MID Optics hutch being prepared.

AE

  • A request to improve the Mpot power supplies has been sent to CAS by many groups. CYoungman will send an e-mail to the relevand people and organize a meeting. The experiment groups have to also make sure that all the interested people are informed.

ITDM

  • Hibef has to decide the network structure to have. In the past they wanted to have a private network behing a gateway. Now the concept is being rediscussed. Discussion ongoing. CAS and AE will also be involved 

FXE, HED not represented.

Entry   Status report after dispatch meeting 09.30 , posted by Gerd Wellenreuther on 03 Sep 2018, 09:49 

SPB / SFX:

  • Experiments are ongoing, users collected data on Sat. and Sun.
  • There have been issues with the detector/DAQ due to operator error
  • There have been issues with the sample delivery
  • There was an issue with the X-ray / Laser interlock systems on Saturday, which was fixed the same day.
  • Beam time was partially lost due to these issues...

FXE, SCS, SQS, MID, HED:

  • Did not attend
  • Support points pointed out it will be much more difficult if the instruments do not attend this meeting to provide support in-time
  • PSPO announced the Dispatch meeting will be discontinued if the instruments will not attend (it is not considered useful with just one instrument attending on a regular basis)

Detectors:

  • Server for calibration data died, ITDM and DESY are working to revive it, S. Hauf will bring it up again.

CAS:

  • CY will have the usual meeting regarding SASE2

AE:

  • PBLMs in SASE3 being integrated.
  • SmarAct stages for SQS are being brought up
  • Vacuum group + AE working on SASE3 interlock
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 29 Aug 2018, 10:01 

SPB

  • New users run starting on Thursday. All set.
  • Discussions on image processors and scan tool with CAS were held. Ongoing.
  • Smaract stages issue. After the installation of a wall connection box by SPB only 2 axes out of 10 work. That's not an issue for the next users run but for the upcoming commissioning time it is. SPB will write an e-mail with details to AE support. 
  • Ion pump issue: pump not sending feedback to the PLC.  SPB will write an e-mail with details to AE support. 

SCS

  • Most of the crates needed for the forst run have been fixed by AE. Last crate will be ready today. Then Lopps 1, 2 and 3 can be brought up.
  • Loop 4 can be brought up after 2 crates have been modified. CR submitted already by AE. in progress.
  • With the ITDM support all the Basler cameras are now connected properly.

SQS

  • Coordinated motion has been set up by AE. Tests by SQS are being runned. Feedback expected.
  • For Loop 6 everything is prepared. If the cables have been installed AE can install the crates and switch on the loop. T. Baumann will check.
  • Pfeiffer flow regulator status unclear. AE will check.
  • Many small issues related to creates have to be fixed. AE and SQS to check offline.
  • Digitizers issue: when a couple of channels are used, the transfer rate goes down to 80 Mb/s. AE and ITDm to address the issue offline with SQS.

AE

  • Implementing new set of machine safety interlocks for SASE3 operation. No saftey PLC used. 3 signals are now provided to the MPS interface:
    • GATT pressure
    • Absorber open signal
    • Position of mirrors

The interlock conditions cannot be disabled/modified from Karabo. Karabo device already deployed.All ready for the test with D3 scheduled for tomorrow.

 

Entry   SASE3 loops will restarted at 11:30, posted by Alessandro Silenzi on 28 Aug 2018, 11:19 

This announcement is to notify you that the intervention planned to configure the interlocks as read-only will be carried out at 11:30.

A following message will notify of the end of the intervention

Alessandro

    Reply   Re: SASE3 loops will restarted at 11:30, posted by Alessandro Silenzi on 28 Aug 2018, 11:36 

 

Alessandro Silenzi wrote:

This announcement is to notify you that the intervention planned to configure the interlocks as read-only will be carried out at 11:30.

A following message will notify of the end of the intervention

Alessandro

Intervention completed.

SA3_SYS_EPS2MPS/DCTRL/BEAM_GATT_OK has now read-only interlock properties

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 27 Aug 2018, 09:57 

SASE3 general

  • Deployment of the new interlock definitions will be done in the next 2 days. Final test foreseen for Thursday.

SPB

  • Users collecting data. Problems of clogging of the sample injection, this could result in empty image files. Wil be checked by the users..

AE

  • FXE requeste a 2nd digitizer channel. Will be finalized with CAS.
  • SQS digitizers issies reported on Friday solved.

DET

  • FXE - LPD module is showing flickering. To be investigated after the users run.
  • AGIPD pipeline issues (crashing). Are probably caused by misconfiguration of the detector by the users. 

 CAS

  • XTD6 technical commissioning will be focussed of the MID CRL this week. No feedback from LBatchelor and MID received relative to the bellows. If no feedback is received, the bellows will be aligned in the central position and the motors disconnected.
  • Log for GATT almost ready (related to the new interlock definitions for the SASe3 operation)
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 22 Aug 2018, 10:08 

SASE3 general

  • Interlock definitions for the tunnels: today a meeting with AE/HSInn/CAS will take place at 14:00 to continue the discussion.PGessler pointed out that one has to make sure to implement a concept which is also OK with D3 to avoid wasting time. The common understanding is that HSinn is the interface to D3 at this moment.

SQS

  • Deployment of new interlock definitions needed. Definitions being prepared by SQS. Ongoing.
  • Loop 6 will be needed in the next days. A couple of cables for these 2 crates are missing. Should be there in a couple of days. SQS wants the loop running anyway.

SCS

  • Due to absence of beam, SCS is now focussing on the end to end test of components considered priority 2 so far.
  • Elmo motors of the FFT chamber need to be rewired. AE on it.

AE

  • Loop 3 SQS ready to be updated.

XPD

  • Exit slit imager for SQS repaired yesterday.
  • Procedure to correctly operate the XGM in XTD2 has been posted by J. Gruenert in the Photon commissioning team logbook.

CAS

  • XTD6 technical commissioning will be focussed of the MID CRL this week. Some tests were already done, others have to be done when L.Batchelor is back. AE support (N.Jardon) is requested.
  • For CAS top priorities are: SASE1 and SASE3 operation/readiness
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 20 Aug 2018, 11:46 

SASE3

  • If the bender of the M2 mirror is used the beam can be focused on the shutter and caouse damaged. This is a safety relevant issue that prevents SASE3 from getting beam. Interlock definitions related to the gas attenuator are being discussed to overcome the problem.

SQS

  • Digitizers being set up with ITDM and AE
  • Deployment of new interlock definitions needed. Definitions being prepared by SQS
  • Loop 6 will be needed in the next days. AE reports that it's almost ready and in the next days will be deployed.

SCS

  • Cabling almost 100% done.

AE

  • Problems with ELMO motors reported on 10.08. for the KB optics has been solved.

XPD

  • 2 screens were damagend in SASE3. One has a hole, the other one has surface damages.The imagers should be put in the interlock when multibunch mode is used. For the single bunch mode a warening signal is now appearing in the Karabo scene.

General

  • The next dispatch meeting will take place as usual this Wednesday at 9:30.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 30 Jul 2018, 10:42 

SPB

  • Middle layer for coordinated motion is being reifned.
  • Request to have the pulse picker ready asap as it is required for user period. AE working on that,
  • Scan tool has to be stested. CAS required.

 

FXE

  • Problem with the shutter in FXE hutch: when openning the shutter with more that 2 pulses the electron beam is dumped. Bypassing the MPS signal FXE is able to get into the hutch beam in 2 pulses mode. The problem seems to be at the interface with the MPS. FXE and AE will check offline.

XPD

  • due to the current beam parameters gas pressure has to be increased (10 ^-4 mbar range) in the XGM in XTD2 to reduce the error on the measures. 

General

  • The next dispatch meeting will take place on 20.08. It was discussed with AE that the existing time slots (9.30 on MOndays and Wednesdays) can be used voluntarily with the SASE3 experiments to exchange information with the technical groups.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 25 Jul 2018, 10:01 

SPB

  • Interaction region cabling being reworked. By the end of the week shoud be done.
  • For the 1st week of operation the Pulse Picker has to be ready -  on a good track.
  • For the 1st week of operation the coordinated motion and the Peltier system has to be integrated in the loop1.
  • Karabo Middle layer for coordinated motion being developed.
  • AGIPD z-motion encoder problems being addressed by AE/CAS
  • uTCA for timing being installed.

SQS

  • Trigger has been made available by AE. CAS devices ready today.
  • ITDM and CAS have to meet to get the DAQ running.
  • EPS signals being defined with AE.
  • Loop 1 update to be agreed after the radiation safety and othe important tests have been done.

 

CAS

  • Today between 12 and 14 the Karabo server will be unavailable in the SASE2 tunnels. 

General

  • Questions about the tunnel access and tunnel access schedule should go to Thomas Tschenscher and the PRC.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 23 Jul 2018, 13:45 

SPB

  • Controls for the pulse picker being prepared. High priority for SPB
  • Coordinated motion tests ongoing. High priority.
  • ATT motors need to be re checked in XTD9. The closing dates for the tunnels are not known excactly. SPB should phone BKR for the last information

SQS

  • Radiation safety test preparation ongoing. 
  • Loop 5 motors being tested.

 

CAS

  • in XTD6 the VAC loop applied labels for the max excursions of the bellows. 
  • PBLM commissioning ongoing
  • CRLs for MID to be repaired.

 

General

  • Starting from this Wednesday the dispatch meeting will be shifted back to 9:30.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 18 Jul 2018, 13:51 

CAS

  • 3 MID CRL motors in XTD6 need to be repaired. The work is being planned and the clean tent is being prepared.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 16 Jul 2018, 14:18 

SPB

  • Mirrors installed. Lid closed.  Las vacuum connection will be closed today. Then the electronics can be connected. 
  • Mock up pulse picker system ready
  • Some crates in the tunnels will be switched on today after updates of the interlock definitions to be ready for photons.
  • Train on demand technique is currently being discussed by FXE with DESY. SPB should be also involved.

SCS

  • Some problems occur during the test of the PLCs, plus after firmware update new problems showed up. Patrick Gessler will organize a meeting with SCS and Bernard to improve the communication and identify the error sources.

SQS

  • Tests ongoing. No relevant issues so far.

ITDM

  • Working on new proposals format.

CAS

  • XTD 6 open until the end of September.
  • This week due to lack of resources by AE only the last slit and one PBLM will be commissioned. The rest will be done next week.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 12 Jul 2018, 08:11 

SPB

  • Mirrors being installed. Tests continue. Karabo updated.

AE

  • Works in the tunnels SASE3 and 2 continue
  • Works on the SASE3 experiment preparation continue

General

Works to ensure the redundant power for Racks in SASE3 have to be performed. A suitable date has to be found. PSPO will coordinate that.

 

Entry   Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates, posted by Hugo Silva Santos on 25 Jun 2018, 09:45 

Dear All,

I would like to inform that we released last Friday (22.06) the Karabo 2.2.4 version. We got around five days delayed to prioritize issues regarding Karabo-DAQ integration and MDL devices that were found in the last steps of the test cycle. However, fortunately, those issues are solved. 

Based on this run, the new dates that we (CAS) are proposing to start the deployment in operation will be:

  • SA3: 28.06, Thursday (CAS references: Chris, Wajid, and Valerii)
  • SA2: 02.07, Monday (CAS references: Chris, Wajid, and Valerii)
  • SA1 + SPB + FXE: 03.07, Tuesday (CAS references: Alessandro, Dennis, Gabriele, Wajid)
    • SPB deployment should not impact AGIPD firmware test week, as agreed before.
  • BKR: 28.06? (Wajid and Jan, could you please agree offline?)
  • LAS, SQS and SCS dates have to be agreed with the respective contact persons.

-
Hugo

 

    Reply   Re: Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates, posted by Hugo Silva Santos on 10 Jul 2018, 11:23 

Dear All,

Please, see below the updates regarding Karabo 2.2.4.1 deployment:

  • SA3: 05.07, Thursday (references: Chris, Wajid, and Valerii) - Done
  • SA2: 06.07, Friday (references: Chris, Wajid, and Valerii) - Done
  • SA1 + FXE: 09.07, Monday (references: Wajidi) - Done
  • SPB: 10.07, Tuesday (references: Gabriele) - Done
  • BKR: 10.07, Tuesday (references: Wajid, Jan, Harald) ToDo
  • LAS, SQS and SCS dates have to be agreed with the respective contact persons. (references: Cyril, Riccardo, and David) In Progress
  • ITDM: We are working to understand and solve a problem reported by Nasser in Karabo 2.2.4 Configurator (references: Dennis, Cyril, and Nasser) In Progress
Hugo Silva Santos wrote:

Dear All,

I would like to inform that we released last Friday (22.06) the Karabo 2.2.4 version. We got around five days delayed to prioritize issues regarding Karabo-DAQ integration and MDL devices that were found in the last steps of the test cycle. However, fortunately, those issues are solved. 

Based on this run, the new dates that we (CAS) are proposing to start the deployment in operation will be:

  • SA3: 28.06, Thursday (CAS references: Chris, Wajid, and Valerii)
  • SA2: 02.07, Monday (CAS references: Chris, Wajid, and Valerii)
  • SA1 + SPB + FXE: 03.07, Tuesday (CAS references: Alessandro, Dennis, Gabriele, Wajid)
    • SPB deployment should not impact AGIPD firmware test week, as agreed before.
  • BKR: 28.06? (Wajid and Jan, could you please agree offline?)
  • LAS, SQS and SCS dates have to be agreed with the respective contact persons.

-
Hugo

 

 

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 09 Jul 2018, 14:32 

SPB

  • Mirrors installatiostarting now. Preliminary motion tests conducted last friday were successful. Still closed loop for encoders signal has to be implemented. AE will work on that.
  • AGIPD firmware updated. Remaining tests ongoing. New Karabo release will be deployed tomorrow.
  • Peltiers being tested. 

SQS

  • End to end tests procceding. Laser incoupling and NQS chambers being set up.
  • Loop 5 needed for next week.
  • M pot firmware issue is being adreesed by CAS
  • It is not possible to switch the ion pumps on and off remotely using Karabo. AE and CAS to look into that.

 

AE

  • SASE3 exp. Loops preparation ongoing
  • SPB Loop 4 update being prepared
  • SASE3 tunnels interlock definitions are being updated for some diagnostic component
  • SASE2 MID CRLs being tested.

 

CAS

  • SPB 2.2.4.1 Karabo update scheduled for tomorrow morning between 7 and 9.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 04 Jul 2018, 14:47 

SPB

  • Mirrors installation ongoing. Lid is open. Movements are being locally tested. Test of synch. motion with PLC to happen likely tomorrow.
  • AGIPD firmware being updated. On friday all the tests should be finished and on Monday the deployment of Karabo 2.2.4. could happen. 

AE

  • SCS support ongoing
  • SQS Loop 4 being prepared
  • New Interlock definitions are being / will be added for SASE1 and 3 
  • SASE3 VAC loop updated today
  • MPS plc has to be rebooted and the kernel has to be updated. The intervention will be done today between 16:00 and 17:00. No timing during the intervention. B. Fernandes will send a mail to the readiness mailing list before and after the completion of the work.

ITDM

  • Maxwell cluster foxing postponed until 15:00

CAS

  • An issue with the middle layer ofthe new release was found. Hotfix being developed and will be released today or tomorrow. NO ITDM migration affected.

 

 

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 02 Jul 2018, 14:03 

Info about tunnels accessibility

concening the XTD10 + XTD2 situation: 

According to my information these two tunnels should be open and will be closed tomorrow at 15:00.

XTD10 will be opened again on Friday 8.00 and then stay open until next week latest until Thursday July12, afternoon (depending if Martin can find somebody to search). 

XTD6 + XTD1: as said before: It will be opened tomorrow at 8:00 and closed again at 15:00 

Both will be opened again on Friday. 

Concerning the interlock test in general, the old table from MPS is still valid (if you add the info that the tunnels are searched the previous working day after 15:00). 

 

SPB

  • MIrrors installation ongoing. Almost all the beamline is vented. Only exception being the AGIPD, that will be vented this eveving.
  • Mirrors movement test to happen AE to agree with SPB about a point in time.
  • Motor parameters could be retrieved after the power cut last week.

AE

  • Tunnel commissioning ongoing
  • SQS/SCS loops being prepared.

ITDM

This Wednesday the Maxwell cluster will be not available from 9 to 12 due to mainteinance.

CAS

  • Karabo 2.2.4. will be deployed in the SASE2 tunnels today. Control system will be down until 15:30. PLCs will keep running. 
  • Karabo 2.2.4 deployment date soe SPB will be agreed offline.
Entry   Status of the power in SASE1 - Update, posted by Adriano Violante on 28 Jun 2018, 15:08 

Dear colleagues

 

 electrical power to SASE1 rooms, except FXE-experimental hutch OUTLETS, is

ready to use. FXE experimental hutch outlets will need about one more hour.

 

Kind regards

 

Dipl.-Ing. Torsten Schön

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 27 Jun 2018, 14:55 

SPB

  • Electronic and instrumentation will remain OFF until the electricity comes back tomorrow (will be announced by TS on the logbook)
  • MIrrors installation will start next week
  • Mirrors movement test to happen, then Loop 4 and 1 to be updated 
  • In order to make the calibration of the motors easier after the powering up, they should not be moved before.

SCS

  • New cables arrived. Testing ongoing.
  • Loop 1,2,3, up. 1 has to be updated. Coordination AE/MTeichmann ongoing
  • Loop4 and 5 being prepared by AE

AE

  • XTD6 DPS and MCP being commissioned.
  • SCS issues with Beckhoff modules being fixed.
  • AE and CAS to agree on interlock reset procedure. 

CAS

  • Karabo 2.2.4. will be deployed in the SASE3 tunnels tomorrow at 10:00. It will take approx. 2 hours. 
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 25 Jun 2018, 13:34 

SPB

  • The power shutdown has been delayed to tomorrow and power is supposed to come back on Thursday at 12:00. Torsten Schen will send an E-mail to readiness when the power comes back on Thursday.
  • Pumps are in a safe state since they currently get external power.

AE

  • Loop 4 SQS up and running. New SASE3 loops being prepared.

ITDM

  • GPFS space issue. Meeting with the experiments on Thursday.
  • MID controls, timing and signals cables have to go through the drag chain (40 m). ITDM and AE will discuss the issue with MID to evalueate problems due to the cables length.

CAS

  • XTD6 closed tomorrow. This will generate some delay of the technical commissioning. 
  • Karabo 2.2.4. deployment schedule proposed by Hugo Santos with an entry in the ELOG this morning.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 20 Jun 2018, 14:12 

SASE1 Experiments

Due to the interlock PLCs reprogramming, the emergency off circuit will be triggered tomorrow and power cuts will occur. Due to that, the AGIPD in SPB is being put into a safety state. ITDM and AE are informed. FXE and Optical lasers were also informed. The order is: Experiment in a safe state==>PLCs switched off==>Servers switched off. 

SPB will put all the motors to zero position and the parameters will be saved by a script prepared by CAS (AS). 

Next week Mon-Wed the planned power cut will also occur. 

SCS

  • Control room being put into operation - New cables to arrive soon. AE addressing the so far known issues.

AE

  • SASE2 MOV2 loop is up.
  • Master timing will be down due to maintenance by DESY on Thursday, from 9:00 to 17:00

ITDM

  • GPFS ran out of space in the week end. ITDM/DET/CAS meeting tomorrow. Then the experiments will be presented a way to go.
  • On Monday we would like to replace the dns/dhcp server in the balcony room. In principle we have the secondary one working at DESY but experience shows everything gets slow and in particular Karabo may have big problems. Due to the power off in SASE1, this will be scheduled for monday afternoon.

CAS

  • Issues with DAQ observed. Conflict on data aggregators. This was found to be a typo in the DAQ code. Fixing of the DAQ required but the release of Karabo 2.2.4. can proceed.
  • Coordinated motion for SPB, SCS, SQS: Follow up tests by AE to be done this week.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 18 Jun 2018, 15:42 

SCS

  • Tests  continue - List of issues sent to AE. Bernard will take care of that as soon as he's back.

SQS

  • Issues with KB motors (ELMO) reported and will be addressed by AE. Also the list was sent to BB.
  • Loop 4  is not up yet. Will be probably by next week.
  • MC2 motors configuration procedure has to be clarified with AE. SCS also interested. Meeting will take place. 

AE

  • SASE2 MOV2 loop will be up on Thursday. XGM already up.
  • Master timing will be down due to maintenance by DESY on Thursday, from 9:00 to 17:00

 

ITDM

  • GPFS ran out of space in the week end. This was due to the calibrated data from the users proposal being completed in the last weeks. ITDM and DET groups will meet to discuss size and strategies to deal with calibrated data.

XRO

  • In SASE3 a slit is reported tomove left if the command "move to right" is given. CAS to look into that.

CAS

  • Karabo version 2.2.4. Test being ultimated.
  • Issues with DAQ observed. Work ongoing to fix it.
  • Coordinated motion for SPB, SCS, SQS: There was a demo (successful). RBean will send minutes around.

General

  • Next Dispatch meetings will take place on Wednesday, at 13:00.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 13 Jun 2018, 10:48 

SCS

  • Tests  continue - List of issues sent to AE.(4/5 in total). Some of thema are related to cabling. EET will be notified.

SQS

  • Loop 1 - 2 issues with cables found. EET to act on that. Motors test continue
  • Loop 3 - Motors test continue
  • Loop 2 is up and running.
  • Loop 4  probably will run tomorrow.
  • In general, (motors, gauges...) parameters have to be saved in order to be restored when a loop is restarded. Info have to go from SQS to AE about which parameters have to be saved.

AE

  • EPS in SASE2 running. MOV2 will be up until tomorrow.

ITDM

  • Transceiver changed ion SCS yesterday, for SQS will be done today. No rpoblems with the network have been noticed/reported by SCS.

CAS

  • Karabo version 2.2.4. being tested with PLCs. 

EET

  • Firmwares fo all the SCS loops have been generated.
  • Firmwares up to Loop 5 for SQS have been generated.
    Reply   Re: Status report after dispatch meeting 09.30, posted by Hugo Silva Santos on 13 Jun 2018, 11:07 

Hi All,

Just adding more info:

CAS

  • Karabo version 2.2.4rc. being tested with PLC 1.27. Waiting for AE support to update the test environment to 1.28 (Jan, Nerea, and Bernard are aware).
Adriano Violante wrote:

SCS

  • Tests  continue - List of issues sent to AE.(4/5 in total). Some of thema are related to cabling. EET will be notified.

SQS

  • Loop 1 - 2 issues with cables found. EET to act on that. Motors test continue
  • Loop 3 - Motors test continue
  • Loop 2 is up and running.
  • Loop 4  probably will run tomorrow.
  • In general, (motors, gauges...) parameters have to be saved in order to be restored when a loop is restarded. Info have to go from SQS to AE about which parameters have to be saved.

AE

  • EPS in SASE2 running. MOV2 will be up until tomorrow.

ITDM

  • Transceiver changed ion SCS yesterday, for SQS will be done today. No rpoblems with the network have been noticed/reported by SCS.

CAS

  • Karabo version 2.2.4. being tested with PLCs.

EET

  • Firmwares fo all the SCS loops have been generated.
  • Firmwares up to Loop 5 for SQS have been generated.

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 11 Jun 2018, 10:27 

SPB

  • Beam delivery issues.
  • After several days of usage the Karabo GUI slows down. Servers are reported to have crashed a couple of times in the last shift.
  • Same situation with data aggregators. Once per shift they have to be restarted. This in known to ITDM.
  • Interlock system seems to work fine now, but the impression is that the people in BKR cannot correctly interpret the interloch signals coming from the experiments. The issue relates to the Interlock panels to be developed in BKR (Issue list, Friday's Operation meeting)

FXE

  • Reading the logbook it seems that some problems with the optical laser's shutter forced to stop the laser operation at about 3 AM. 

SCS

  • Tests  continue

SQS

  • Loop 1 one more ion pump will be implemented today by AE
  • Loop 3 - Configuration of the rest of the  motors expected today
  • Loop 2 should be up by tomorrow according to AE
  • Loop 4 and 5 are supposed to go up in the next 3 weeks 

AE

  • EPS in SASE2 should be ready today

ITDM

  • FXE reported missing images from Gotthardt detector in the H5 files. The data does not reach the DAQ. Tests have to be made, but cannot be done while SPB has beamitime. Tests foreseen for tomorrow.
  •  

CAS

  • Some issues with scanning tool reported - working on it
  • Some issues concerning data acquisiion from imagers were reported from SPB  - Valerii on it.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 06 Jun 2018, 09:46 

SPB

  • Ready for the Users run. No big issues.
  • The first 2 weeks of the shutdown will be used for cleaning and rearrangement of the hutch by SPB, in preparation of the mirrors instalaltion. PLCs update and Technical interventions by TS or external companies have to be carried out in this period. 

AE

  • XTD6 VAC loop running.
  • CRL XTD1 working
  • Loop 2 SQS experiment still not running due to small issues being solved.
  • Loop2 SCS was restarted yesterday after some fix

ITDM

  • Gpfs should be fixed by now.

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 04 Jun 2018, 10:46 

SCS

  • List with the problems encountered so far during the end to end test was sent to AE. Bernard will get the info and eventually inform EET if problems with cables are found.

SQS

  • Elmo motors for KB system were ocnfigured and are being moved right now. If problems arise AE will be contacted.
  • It was not possible to control the turbo pump controllers via PLC. Bernard will have a look. In general also tirbo pump cables can and will be checked with the test box.
  • Loop 2 is being prepared including the MC2 motors. Should be ready by tomorrow.
  • SQS would like to start setting up the digitizers environment in Karabo. uTCA crates can be used on the HW side. AE acan support that.

AE

  • XTD6 VAC loop is being patched. Small problems with the cabling of the CRL occured but solved. 

XRD

  • XTD6 components being cabled. 2 Imagers still need to get the EPS signals. in 1/2 weeks ready for local tests.

ITDM

  • One IBM storage server failed. Reasons not clear. No impact on the performance of the system.

CAS

  • This Week VAC loop in XTD 6 will work.
  • For the MOV 2 loop still  EPLAN exports are needed.
  • MOV1/MOV2 interfaces have to be defined.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 30 May 2018, 10:55 

AE

  • CRLs in XTD1 being implemented
  • GATT and EPS loop in SASE3 being updated

SCS

  • Tests continue - No issues so far

SQS

  • ELMO controllers have to be configured for the mirror motors test. Slit motors have lower priority. Cables can be tested w/o being physically connected to the motors, but to configure the ELMO controllers the cables have to be connected to the real motors. Tomorrow AE is available to support these activities.
  • Basler cameras set up and working.

ITDM

  • SPB AGIPD test today or tomorrow

CAS

  • Hot fix for SPB released yesterday. This will address the issue of crushings when instantiating a new device. Has to be tested with SPB. 
  • XTD 6 will have no electricity for the racks today since Wille is completing the cabling. MTCA being shut down accordingly.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 28 May 2018, 10:28 

General

  • For the upcoming emergency off test in SASE1 SPB and FXE should propose  a possible date in the next shutdown to be then discussed with AE.
  • The machine is down due to the failure of a cryocompressor. Beam will be probably coming back tomorrow morning. Tomorrow morning will be also confirmed whether SPB and FXE cold use the beamtime for the user run.

SPB

  • In the week end there was a failure of the PP laser shutter. It was possible to find a very temporary solution to circumvent the problem.
  • The beam has been unstable for most of the time. No drift, mostly gitter. Reasons are unclear. The instability was also measured with the XGM in XTD2. SPB is analysing the data collected to be able to quantify the instability. 
  • DAQ tests for AGIPD were planned for tomorrow but the request is to shift them to today to take advantage of the missing beam.

FXE

Some issues were reported: LPD readout of the data, Fast digitizers mainly. The details have to be clarified with the DET and ITDM groups.  

AE

SQS loop 3 is up and running. 

SCS

  • Tests continue

SQS

  • FMB Oxford will be working on the mirror tank starting form tomorrow until next week. Acces to the hutch is limited.
  • There will be a meeting with AE to discuss the set up of the motors for testing (especially for the mirrors). SCS will also participate. 

ITDM

  • SASE3 projects updated. Performance increased.
  • Possible to move the AGIPD test for SPB to today

CAS

  • Camera device had to be reinstanciated 4 times during the week end. Investigation ongoing.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 23 May 2018, 12:44 

General

  • Please remember to send the list of the tasks you planned for the next shutdown to Monica Areste by the end of the week.
  • Please remember to send the list of the alignment works needed until July to Gerd Wellenreuther.

AE

SQS loop 3 is almost ready. 1 crate is currently in the AE lab but should be installed soon. The loop 3 is needed by SQS for the motor tests with FMB Oxford next week.

SQS

  • Due to a pump that stopped working (Caverion) this morning there was water on the floor of the laser hutch and part of the experiment hutch.  Some cables (not powered and packed) saw water. These are being checked. Also lasermet boxes on the wall saw water. Lasermet is checking that.
  • For the testing SQS requested the test box to AE 

SPB

  • Final DAQ test ongoing. Slow data acquisition OK. This is needed for the users program this week. Fast data acquisition (inc. AGIPD) will be tested next week.

ITDM

  • Patch released for Slow data acquisition FXE/SPB. LPD acquisition OK. AGIPD issues being investigated.

 

Entry   MPS update Info from AE , posted by Adriano Violante on 16 May 2018, 13:52 

The MPS comm for SASE 2 and FXE were tested and the only remaining part is to test the SPB to MPS changes. Tomorrow morning a  timeslot will be agreed between AE and SPB.

Entry   Summary of the dispatch meeting 09.30, posted by Adriano Violante on 16 May 2018, 11:37 

 

​​AE

  • SASE3:
    • -Request from Andreas Koch about interlocks for MCP and LED Power in SQS/SCS (this installation is unique in SASE3). For that purpose we have to update EPS, MOV2 and Master loop in SASE3. PRC will be triggered by E-Mail ==> AE updated the loop. Nerea is making sure that the MPS signals are enabled in the BKR 
    • Stepper motor for the mirror bender was found to be miswired. Has been already fixed. Similar issue (inverse wiring) was found in SASE1. Cannot be fixed now. It will be done in the next shutdown. For the time being one has to drive the morot the opposite way.
  • SASE2:
    • -We want to update SASE2 in order to get beam permission interlocks properly. Therefore we need to update, EPS, Vacuum loop and Master loop. PRC will be triggered by E-Mail ==> DONE. Not clear if some motor parameters for XRO devices were saved before. D. La Civita and CAS are checking that
  • SPB:
    • -Today we will deploy loop 12 and 13 and Master loop. In the Master loop we will add beam permission conditions, so we want to test it and therefore we will need to open all the valves in SPB as well as the last ones in the Tunnel. Has to be decided when it is possible with the SPB people. ==> DONE. 
  • FXE:
    • -All loops updated past week. Waiting for answer from FXE about when we can test the same beam permission conditions as in SPB. To be agreed with FXE.

ITDM

  • DAQ has to be upgraded to thelast verison of Karabo (just hotfix). Will be checked with Gero what is the best way to go.

 

Entry   Summary of the dispatch meeting 09.30, posted by Adriano Violante on 14 May 2018, 10:17 

SQS

  • Loop1 still being worked by AE. Not yet up and running. 
  • Loop 3 is needed to be up and running in 2 weeks since the mirror motors ar eincluded in this loop and they are needed for the final check with FMB.

SCS

  • Bernard has been added to the SCS operation logbook and he is getting al the updates concerning commissioning.
  • Testing of the Loop 1 motors ongoing., 2 out of 20 motors have problems. Being investigated.
  • Some connectors names are reported not to be consistent with the EPLANS. Martin Teichmann will check that with EET.

​​AE

  • SCS:
    • loop 2 running. Bernard has recommended that you start with commissioning of KBS_VDM, _HFM, _BFL, VFM motors because they are using MC2MOTOR soft device class (controller is Elmo).
    • Crate BKF00157 can be removed and refresh terminal will be added without interrupting the PLC - only equipment connected to this crate will not be available during this period of change.
  • SASE3:
    • -Request from Andreas Koch about interlocks for MCP and LED Power in SQS/SCS (this installation is unique in SASE3). For that purpose we have to update EPS, MOV2 and Master loop in SASE3. PRC will be triggered by E-Mail
  • SASE2:
    • -We want to update SASE2 in order to get beam permission interlocks properly. Therefore we need to update, EPS, Vacuum loop and Master loop. PRC will be triggered by E-Mail
  • SPB:
    • -Today we will deploy loop 12 and 13 and Master loop. In the Master loop we will add beam permission conditions, so we want to test it and therefore we will need to open all the valves in SPB as well as the last ones in the Tunnel. Has to be decided when it is possible with the SPB people.
  • FXE:
    • -All loops updated past week. Waiting for answer from FXE about when we can test the same beam permission conditions as in SPB. To be agreed with FXE.

 

DET

  • Working of the optimization of the python piece of code allowing the display of online images. Right now 30 images per second rate is possible.

ITDM

  • GPFS server fixed.

CAS

  • XTD1 CRLs will be integrated iin the control system in KW 22
  • 20.07 is the goal date for beam in MID and HED optics Hutch.  

 

Entry   Summary of the dispatch meeting 09.30, posted by Adriano Violante on 09 May 2018, 10:09 

SPB

  • Test on the mirrors peltier showed some issues due to the fact that the test boxes were different from the actual stuff. R.Bean will clarify it with FMB.
  • Loops 12,13 update to be done.
  • Magnetic turbos control: the serial communication has some issues. Being checked with AE and CAS

SQS

  • Loop1 cabled up. Some names haad to be corrected in the firmware. As soon as the export is delivered by EET to AE the formware can be uploaded, Probably today.
  • Upstream turbo pumps running using controlers in the rackrooms but still no PLC control.

SCS

  • Some issue with the movement of the motors found. AE is on it.
  • 1 crate does not have enough power to power up all the terminals. Will be solved today.

AE

  • The valves will be included in the interlock systems (SASE1 issue) - Loop ready to be updated - The MPS has to be disabled before updating the loop to avoid tripping of the beam.
  • FXE loops update started

 

DET

  • Hotfix for AGIPD ready to be deployed. Can start today. Details will be sorted out with SPB.

CAS

  • SASE3 Soft Mono is now technically commissioned. PBLMs next in the line.
  • XTD1 CRLs will be integrated iin the control system in KW 22
  • XTD6 priority on the MID beamline. 

General

It is not clear if and when the experiment in SASE1 could get beam during this week. Has to be checked with the PRC.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 May 2018, 10:36 

SPB

  • Loops 5,7,11, update and Karabo deployed.
  • Loops 12,13,8 update ongoing.

SQS

  • Loop1 cabled up. Today the formware will be uploaded.
  • Loop 2 will probably be ready on Wednesday

SCS

  • Out ov 50 valves tested 5 showed problems. Investigation ongoing to understand where is the problem (PLC, Cables, Valves)
  • In Loop 2 a problem with a crate containing Elmo controlers was found. AE on it. Next loop to be tested will be Loop 4.
  • 1 crate does not have enough power to power up all the terminals. CR already prepared. Will be solved soon.

AE

  • By the middle of the week the valves will be included in the interlock systems (SASE1 issue)
  • The EPS interlock definitions for the tunnels in SASE2 are being finalized by AE, XPO, XPD

ITDM

  • Failure of one IBM server for online storage. Fixing ongoing.

DET

  • Online preview and charge injection issues are being solved restarting the DAQ and re-deployng Karabo.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 02 May 2018, 11:17 

SPB

  • After re-compiling the relative karabo device, the configuration procedure of the AGIPD is now smoothand reliable.
  • PLCs update ongoing. AGIPD is in a safe state to allow the PLC update.

SQS

  • Meeting today at 11:00 with AE, EET, CAS to define the next steps of the end to end tests.

AE

  • SASE2 tunnels - Only VAC conditions are transmitted from the EPS loop to the MPS. All the other conditions were supposed to be not necessary for first lasing and were not implemented. Nevertheless this was not clear for the people working in the BKR (especcially for diagnostics) during the last days. It has to be discussed with the PRC (H. Sinn this week) whether these have to be implemented on a short time. In pronciple AE can do it if requested. Otherwise the definitions will be implemented in the next shutdown.

ITDM

  • Failure of one IBM server for online storage. Thanks to the implemented redundancy this will not affect the operation. The performances have to be checked.   IBM has been contacted.
  • On monday evening ITDM OCD received a call from BKR because of some problems with the DAQ in the tunnels. It seems that this was due to the fact that the system was not properly tested by the "users" before. Seems to be solved now.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 30 Apr 2018, 09:51 

CAS (C. Youngman)

Following the Technical commissioning phase for the SASE2 tunnel components, the need of a technical coordination activity is strongly pointed out. This is in particular important to make sure that the proper final tests are performed by the components owner  before e.g. first lasing attempts.

 

SQS (T. Baumann)

Lopp 1 being brought up. First tests to be started soon. The CAS and AE contact persons should be in involved in the tests as early as possible.

 

 

 

 

Entry   Lasing SASE3, posted by Adriano Violante on 27 Apr 2018, 10:21 

INFO

As reported by the PRC (J. Gruenert) during the operation meeting this morning, due to the first lasing attempt in SASE2 no lasing of SASE3 is to be expected until the middle of next week.

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 25 Apr 2018, 13:28 

SPB

  • Loops update: 1-4+8 this week. 5-7 Wed. next week. 11-13 end next week.
  • Smaract motors for PAM are needed and Nerea is on it.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests. Jola sick until 1st week of May. To be seen then.
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE. Interlock definitions  have to be checked next week when HSinn is back. 
  • During the switch on of the detector many Karabo devices had a problem even if no error messages were displayed. The problems disappeared restarting the devices. The errors could not be reproduced. Ot top of that it is possible to collect data only from 15 modules out of 16. The one missing changes every time the device is restarted. ASilenzi on it. 
  • Technofoft motor with magnetic switches do not work. In the tunnel the same configuration works, Will be investigated by AE/CAS/SPB
  • Motors upstream move sometimes by themselves. Discussion ongoing between AE SPB and CAS. To be adressed offline.

XPD

  • Access  of XTD1 today @14:00 to fix some EPS switches
  • SASE2 firsta lasing should be tried this week end + monday. CAS support requested. ASIlenzi checks with CAS whether this is possible.

AE

  • SCS exp: first loop running. 2 creates missing but loop is up.
  • MPS connection tunnels SASE2 done

ITDM

  • Online storage update patch to be installed today. The system should remain online but in some cases one could have some downtime (1-2 hrs)
  • MPS connection tunnels SASE2 done.

General

On Wednesday the meeting will be held at 13:00. Starting from next monday it will go back to 9.30

    Reply   Re: Status report after dispatch meeting 13:00, posted by Alessandro Silenzi on 25 Apr 2018, 18:10 

Regarding CAS Support for SASE2 Lasing:

CAS is happy to support in the frame of the On Call Duty system as it has been provided in the past.

Adriano Violante wrote:

SPB

  • Loops update: 1-4+8 this week. 5-7 Wed. next week. 11-13 end next week.
  • Smaract motors for PAM are needed and Nerea is on it.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests. Jola sick until 1st week of May. To be seen then.
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE. Interlock definitions  have to be checked next week when HSinn is back. 
  • During the switch on of the detector many Karabo devices had a problem even if no error messages were displayed. The problems disappeared restarting the devices. The errors could not be reproduced. Ot top of that it is possible to collect data only from 15 modules out of 16. The one missing changes every time the device is restarted. ASilenzi on it. 
  • Technofoft motor with magnetic switches do not work. In the tunnel the same configuration works, Will be investigated by AE/CAS/SPB
  • Motors upstream move sometimes by themselves. Discussion ongoing between AE SPB and CAS. To be adressed offline.

XPD

  • Access  of XTD1 today @14:00 to fix some EPS switches
  • SASE2 firsta lasing should be tried this week end + monday. CAS support requested. ASIlenzi checks with CAS whether this is possible.

AE

  • SCS exp: first loop running. 2 creates missing but loop is up.
  • MPS connection tunnels SASE2 done

ITDM

  • Online storage update patch to be installed today. The system should remain online but in some cases one could have some downtime (1-2 hrs)
  • MPS connection tunnels SASE2 done.

General

On Wednesday the meeting will be held at 13:00. Starting from next monday it will go back to 9.30

 

Entry   SASE3 MOV1 loop update, posted by Marijan Stupar on 25 Apr 2018, 11:42 

I will update the SASE3 MOV1 loop in 30 minutes. Please let me know if you would like me to postpone the update.

Best regards,

Marijan

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 23 Apr 2018, 15:35 

SPB

  • Timing tool for optical laser installed
  • Sample chamber's PLC will be updated next week due to ongoing tests until monday. Pending.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests. Pending. 
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE. Pending.

AE

  • SASE2 EPS Loop running
  • Updating PLCs for MPS in the tunnels. The update was stopped last friday due to a problem with the on/off funcionality of some ion pumps. The problem was found and the fixing requires an update of the VAC loops whoch will be done in the next hours/days. In case the loop update is not possible due to specific requirements the problem can be bypassed in Karabo. 

 

General

On Wednesday the meeting will be held at 13:00. Starting from next monday it will go back to 9.30

Entry   Tunnel closing after shutdown, posted by Gerd Wellenreuther on 18 Apr 2018, 15:06 

Dear all,

below please find the hottest and most up-to-date times for the closing of the tunnels after the shutdown:

XTD1: 23.04.
XTD2: 23.04.
XTD6: not before 02.07. 
XTD9: 27.04. after lunch
XTD10: 24.04. after lunch

Cheers, Gerd

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 18 Apr 2018, 13:43 

SPB

  • Karabo has been deployed  without major  problems! 
  • Now PLCs update follows. Sample chamber's PLC will be updated next week due to ongoing tests until monday.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests. 
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE

AE

  • Timing servers update - this Thurdsay, starting at 14:00 for 1 hour the trigger and train id signals will be not available.
  • Updating PLCs for MPS in the tunnels 

ITDM

  • Network stability problems in SASE3 are understood and a workaroung is being implemented.

General

Closing time of the tunnels on monday still not clear. To be clarified by PSPO.

Entry   SPB emergency power off tests, posted by Torsten Schoen on 17 Apr 2018, 14:23 

Dear all,

 the emergency power off test has been successfully performed in SPB.

Nobody can instantly cut the power to non hazardous racks (see racklist.xlsx managed by Ulf Brueggmann) by pushing the emergency off button anymore. The outlets in the experiment hutch do not go off. This is due to some missing cables. These will be installed in the next weeks and a new test will be planned for next shutdown.

Furthermore three racks for D.02 (SPB optics) and two racks for D.13 (SPB laser) cannot be powered off anymore by pushing the emergency off in D.09. The missing two emergency power off switching devices will be mounted in UV-XHEXP1-01-13-AV in the next shutdown. Until then the power to those five racks (D03-UH1 - D03-UH3, D13-UH1, D13-UH2) cannot be cut by emergency off buttons in D.02 or D.13.

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 16 Apr 2018, 14:20 

Summary of Karabo 2.2.3 deployment dates:

  • Karabo 2.2.3 deployed in SASE3 tunnels last friday ==> no major issues. DAQ can be deployed
  • Karabo in SASE2 Tunnels to be deployed today at 14:00
  • Karabo in SASE1 Tunnels to be deployed tomorrow at 08:00
  • Karabo in SPB/SFX experiment to be deployed today and tomorrow
  • Karabo in FXE experiment to be deployed on Wednesday

SPB

  • By tomorrow the mirror installation will be done.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests.
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE

AE

  • Timing servers update - this Thurdsay, starting at 14:00 for 1 hour the trigger and train id signals will be not available.

ITDM

  • Infiniband port fixing ongoing
  • GPFS bug to be fixed with a patch that should be issued on 24.04. To be checked whether it is still OK to install the patch or it is too late.

General

  • PSPO will ask HSinn for a detailed schedule concerning closing of the tunnels to fine tune the activities going on this week in the SASE2 and 3 tunnels
Entry   Emergency off test in FXE - Update and next steps, posted by Adriano Violante on 16 Apr 2018, 12:38 

Dear all,

 

I was just informed by Ulf Brueggmann that the emergency power off test was successfully performed in FXE.

The  reality is now reflecting the planned logic, exeption being the power plugs in the experiment hutch. They do not go off. This is due to some missing cables. These will be installed in the next weeks and a new test will be planned for next shutdown.

The tests will continue tomorrow in SPB/SFX.

 

 

 

Entry   Shutdown MicroTCA4 SPB and FXE, posted by NEREA JARDON on 13 Apr 2018, 13:50 

This entry is on behalve of Frank Babies, if you have any doubt about it, contact him:

On 16.Apr.2018 09:45am till Noon I have to shutdown the MicroTCA4 Crates Rackroom from FXE
"fxe-rr-sys-utc-1"
"fxe-rr-sys-utc-2"
because of the Power Down issue on Monday.

On 17.Apr.2018 09:45am till Noon I have to shutdown the MicroTCA4 Crates Rackroom from SPB
"spb-rr-sys-utc-1"
"spb-rr-sys-utc-2"
because of the Power Down issue on Tuesday.

This will affect timing system and MPS communication.

Entry   Dates TÜV Test SASE3 Intelrocks, posted by Adriano Violante on 13 Apr 2018, 13:01 

Interlock systems SASE3 - TÜV test

The pre test by D3 will be held on 20.06.

On 05.07.The TÜV Test for SASE3 will be done together with the SASE2 test and the repetition of the SASE1 test

Entry   Emergency off test in SPB/FXE, posted by Adriano Violante on 13 Apr 2018, 09:40 

Emergency power test will be performed at the following dates:

FXE - Mon. 16.04.

SPB - Tue. 17.04. 

Schedule

  • 10:00 Power will go off in SASE1 - Only redundant power line will stay ON
  • Reprogramming of the PLC of the Emergency power off system - Estimated 1.5 Hrs.
  • Power ON again ==> Emergency OFF test will be carried out. (info from AE: AE PLCs will not go off. uTCA crates will be shut down before)
  • About at 15:00 everything should be back to normal.

For technical questions contact T. Schoen and U. Brueggmann.

Entry   SASE3 E.21 and E.22 electrical power distribution, posted by Torsten Schoen on 13 Apr 2018, 09:05 

changes according to the racklist on the electrical power distribution cabinets for rackrooms E.21 and E.22 are done. Power supply should be stable now. Please note that there will be emergency power off tests prior to the final acceptance test of SASE3 electrical installations around mid of May. You will be notified about the exact time and date.

Entry   Karabo 2.2.3 installation, posted by Adriano Violante on 13 Apr 2018, 07:50 

Hi all, for your information below a message from Chris Youngman concerning Karabo 2.2.3 installations in SASE3.

"preparation work has concluded and we will definitely try to deploy Karabo 2.2.3 on SA3 machines TODAY 13.04.. SA3 s/w will not work from 8:00 on. Hopefully we will finish during the morning.

SA1 and SA2 installations should continue as normal."

Entry   Water cooling mointenance by MKK done, posted by Adriano Violante on 12 Apr 2018, 15:34 

Die Arbeiten an der Kühlwassersteuerung konnten innerhalb des genannten

Zeitraums abgeschlossen werden,

so dass die Kühlwasserversorgung nun schon einige Zeit wieder geregelt

läuft.

 

Großer Dank an alle Beteiligten, die den Ablauf der Abschaltung meines

Wissens auswirkungsfrei gestalten konnten.

Wir bitten über kurze Rückmeldungen zur Optimierung, sollten

Schwierigkeiten im Zusammenhang mit der Abschaltung entstanden sein.

 

Mit freundlichen Grüßen

Jörg Hanik

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 11 Apr 2018, 13:48 

SPB

  1. Detector z motion would be needed. AE checks the status of the crate. still pending
  2. MIrrors installation ongoing. NO ACCESS to D.02!!!!
  3. Laser Interlock change of logic by K.Witt will be done on monday at 9:00
  4. Karabo update installation dates being agreed with CAS. Probably early next week.
Entry   Karabo deployment dates, posted by Adriano Violante on 09 Apr 2018, 14:37 

FYI

Below the E-Mail from Hugo Santos with the Karabo deployment dates.

 

Dear All,

 

I would like to call your attention to the fact that we made Karabo 2.2.3 available last Monday (04/04, and the changelog 06/04). From the last Readiness Meeting, I got informed that we agreed and are allowed to proceed with the Karabo rollout planning on SASE3 and SASE2. (SASE1 still needs agreement):

  1. SASE3
    1. PRE-CONDITION: (AE) PLC version and (ITDM) DAQ should be interface-compatible, otherwise, the deployment will not be able to be performed. (No Karabo-DAQ and Karabo-PLC interface issues)
    2. Date: 13/04/2018 (Friday)
    3. Should be the first one because of the completeness of this system: VAC, PES, XGM and GAT loops, for instance, that have to be checked and run properly afterward.
    4. Downtime expected: 9:00 to 14:00
    5. (AE) PLCs version and (ITDM) DAQ should be interface-compatible, otherwise, the deployment will not be able to be performed.
    6. No major change regarding DET systems
    7. CAS Members for this specific task: Chris and Wajid.
  2. SASE2
    1. PRE-CONDITION: SASE3 Deployment task must be done and Karabo 2.2.3 running with PLC and DAQ (No Karabo-DAQ and Karabo-PLC interface issues)
    2. Date: 16/04/2018 (Monday)
    3. Downtime expected: 11:00 to 13:00.
    4. (AE) PLCs version and (ITDM) DAQ should be compatible, otherwise, the deployment will not be able to be performed.
    5. No major change regarding DET system.
    6. CAS Members for this specific task: Chris and Wajid.
  3. SASE1
    1. PRE-CONDITION: SASE2 and SASE3 Deployment tasks must be done and Karabo 2.2.3 running with PLC and DAQ (No Karabo-DAQ and Karabo-PLC interface issues).
    2. Date: (17/04/2018 - Tuesday - to be agreed)
    3. Downtime expected: to be defined
    4. (AE) PLCs version and (ITDM) DAQ should be compatible, otherwise, the deployment will not be able to be performed.
    5. No major change regarding DET systems.
    6. CAS Members for this specific task: Alessandro and Wajid

Finally, please, also see that as soon as we have the Karabo 2.2.3 running during the shutdown, we will have the most comfortable time to perform the setup, configurations and stabilize it, still, during the shutdown. This way we can handover the control system properly to the operators.

 

Please, if you do not agree or are not comfortable with something in this message, let me know as soon as possible. Otherwise, I will assume that it does not contain any showstopper and we (CAS) can proceed.

H.S.

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 09 Apr 2018, 14:25 

General

Emergency off test in SPB is shifted. Date to be agreed on Friday. FXE test stays on 16.04. TS will confirm that.

MKK will shut down the cooling water for Tunnels and XHEXP1 on Thursday startin from 11:00 for maintenance purposes.

  1. Based on the information we have the intervention could last up to 2 hrs. UBrueggmann is trying to check whether is possible to limit the duration of the intervention to bunches of 45 min. This could avoid the shut down of the Turbo pumps.
  2. UBrueggmann is taking care of opening the rack doors in the tunnels (all of them!) and close them again when the water is back. 
  3. The experiments should take care of opening the doors of the racks in the rackrooms. Also the main door.
  4. AV will speak with the important groups involved and then send a summary e-mail to staff today afternoon.

 

SPB

  1. Detector z motion would be needed. AE checks the status of the crate
  2. Quadrant motion - Suggestion from AE is to perform tests and implement it in the next shutdown.
  3. MIrrors installation ongoing. NO ACCESS to D.02!!!!
  4. Laser Interlock/Rad. Saf. interlock issue still being investigated.  No news from SRP.

 

SASE2 -CYoungman

Goal is to stop the HW changes by the end of Wed. Thursday final loops and firmware will be updated. Both in SASE2 and 3.

 

Entry   Emergency off test in SPB/FXE - Update, posted by Adriano Violante on 09 Apr 2018, 11:50 

Due to some delay in the installation of some necessary cables, the emergency power off test foreseen for today 06.04. in the SPB experiment will not take place.

The details will be reported by Ulf Brueggmann today in the dispatch meeting at 13:00. The needed cabling should be done this week, so that the test in FXE planned for Monday, 16.04 CAN take place.

TS will confirm the FXE date and propose the nex date for SPB this Friday in the Readiness meeting.

Entry   maintenance of the online storage system, posted by Janusz Szuba on 04 Apr 2018, 17:46 

On Friday, 6.04, there will be a maintenance of the online storage system. This will tackle the issues we had just before the last user beamtimes, when we decided to apply workaround to keep the system working. The availability of the storage system is not guaranteed, especially when faulty h/w parts needs to be exchanged.

Best, 

Janusz

Entry   Control network maintenance, posted by Janusz Szuba on 04 Apr 2018, 17:35 

Tomorrow, 5.04, between 9:30 and 12:00 there will be urgent maintenance of one of the two redundant main switches for the control network. The network connectivity during that time is not guaranteed, but also any major interruptions are not expected. For the two switches in sase1 tunnels with only one uplink, there could be short (~1min) interruption.

Best, 

Janusz

Entry   Status reports after dispatch meeting 13:00 4.4., posted by Gerd Wellenreuther on 04 Apr 2018, 13:43 

SPB/SFX:

  • Mirror installation next week

FXE:

  • Replaced broken diamond-window

SCS:

  • Installation of alignment laser
  • Mirror tank installation next week

SQS:

  • Not present / no issues.

SASE tunnels:

  • C. Youngman is coordinating the works in the SASE1, 2 and 3 tunnels, daily meetings are at 9:30 every morning.
  • Works have been scheduled and planned, most work to happen in SASE3 and SASE2.
  • Staff should be aware that works e.g. regarding the vacuum loops have been scheduled and are ongoing, in doubt contact C. Youngman, N. Jardon or V. Bondar

CAS:

  • Release test with Karabo 2.2.3 are concluding probably today, including test with PLC firmwares 1.26 and 1.27.
  • This would lead to a release for ITDM & Detectors by this evening. A timeslot is required to test the new Karabo with ITDM / DAQ.
  • Deployment at the beamline could potentially be in two weeks, if the test with ITDM and Detectors will conclude fine.

XPD:

  • Email to xfel-op-allhands was received, indicating that there could have been a shortage of cooling water for the magnets and racks supplied from XS4 and also XS2 (should be SASE2-branch only). If you have electronic racks in this area, check the temperature, email will be forwarded to readiness.

Detectors:

  • A single supermodule of the LPD-detector is flickering, is being investigated.

ITDM:

  • A rise of the temperature in the balcony room from 27° to 39° was observed in the morning from ca. 6:00 until 6:30.
  • This lead to damage at two power supplies.
  • There was no indication by MKK or TS about any kind of shortage or shutdown of the cooling water supply.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 28 Mar 2018, 15:22 

SPB

  • Sample delivery installed. Tonight will be commissioned. Experiment set-up starts tomorrow night

FXE

  • Digitizers were already implemented in the DAQ but there is an issue related to the Karabo device. CAS already looking into that.

AE

  • Follow up to the issue of re-setting pumps after interlock is triggered: loops updated. 
  • SASE2 MOV loop patched
  • Imagers in XTD1 have to be tested with Karabo

ITDM

  • On monday afternoon problems with the storage servers were reported. The issue is a defective board, whoch is meanwhile been deactivated. IBM is working on that. The system seems to be working in this state.

CAS

  • The next Karabo release will be able to handle better big loops. ASilenzi points out that the next update is really important since it adresses problems like the restart of time servers issue.

Readiness Meeting Issue list

  • Item 2 (XGM SASE3): After restarting of the CPP servers the XGM turbo pumps stopped, valves closed and it required a manual intervention to restore them. ==> Firmware updated. CLOSED

Operation Meeting Issuel List

  • Item 1 (Karabo rollout process): Testing steps of a new Karabo release have to be discussed with AE-ITDM-DET ==> Meeting took place. Closed
    Reply   Re: Status report after dispatch meeting 09.30, posted by Hugo Silva Santos on 29 Mar 2018, 09:48 

Update regarding Digitizer:

----- Forwarded Message -----
From: "hamed sotoudi namin" <hamed.sotoudi.namin@xfel.eu>
To: "Sergey Esenov" <serguei.essenov@xfel.eu>, "andre" <andreas.galler@xfel.eu>
Cc: "Djelloul Boukhelef" <djelloul.boukhelef@xfel.eu>, "Dennis Goeries" <dennis.goeries@xfel.eu>, "Leonce Mekinda" <leonce.mekinda@xfel.eu>, "Patrick Gessler" <patrick.gessler@xfel.eu>, "Hugo Santos" <hugo.santos@xfel.eu>, "Krzysztof Wrona" <krzysztof.wrona@xfel.eu>, fxe-instrument@xfel.eu
Sent: Wednesday, 28 March, 2018 17:37:28
Subject: RE: adqDigitzer

Hi everybody,

Today morning me, Andreas and Leonce have tested digitizer with software in 
FXE hutch. We tried the same configuration as it was and checked the log 
file, we observed that software was missing synchronization, that means 
either packets from digitizer have some problems ( missed or corrupted) , or 
buffers are too small in software. We reinitialized everything and problem 
disappeared ( at least for synchronization).
This afternoon I tested digitizer in our lab in APD mode with Raw data mode 
and also checked values; everything was fine. Because till today we have 
tested digitizer in fully load and enabled APD and raw data for all channels 
we observed no issues. I tried to set the same configuration which Andreas 
applied in their system ( APD for one channel and raw data for all channels) 
I encountered the same problems that he had mentioned in Email. Conclusion 
is that Digitizer has no problem when Algorithms are enabled for all 
channels. But when one algorithm is enabled for only one channel there is 
problem in packets, or even there is no packet from digitizer sometimes. 
Which gives timeout error.
Current solution is that to enable required algorithm for all channels and 
ignore result from unwanted ones.
I do really apologize for this inconvenience caused and will do my best to 
solve the problem in Firmware as soon as possible.

Best,
Hamed

Adriano Violante wrote:

SPB

  • Sample delivery installed. Tonight will be commissioned. Experiment set-up starts tomorrow night

FXE

  • Digitizers were already implemented in the DAQ but there is an issue related to the Karabo device. CAS already looking into that.

AE

  • Follow up to the issue of re-setting pumps after interlock is triggered: loops updated. 
  • SASE2 MOV loop patched
  • Imagers in XTD1 have to be tested with Karabo

ITDM

  • On monday afternoon problems with the storage servers were reported. The issue is a defective board, whoch is meanwhile been deactivated. IBM is working on that. The system seems to be working in this state.

CAS

  • The next Karabo release will be able to handle better big loops. ASilenzi points out that the next update is really important since it adresses problems like the restart of time servers issue.

Readiness Meeting Issue list

  • Item 2 (XGM SASE3): After restarting of the CPP servers the XGM turbo pumps stopped, valves closed and it required a manual intervention to restore them. ==> Firmware updated. CLOSED

Operation Meeting Issuel List

  • Item 1 (Karabo rollout process): Testing steps of a new Karabo release have to be discussed with AE-ITDM-DET ==> Meeting took place. Closed

 

Entry   XTD1 open, posted by Jan Gruenert on 27 Mar 2018, 14:18 

Info from BKR:  the southern tunnels were opened, thus XTD1 can be accessed now.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 26 Mar 2018, 13:10 

General

Due to the triggering of the emergency power off in FXE caused by electrical works being done on Sunday, FXE and SPB lost beam and electronics was switched off. In general the efficiency of the communication between groups has to be impoved. An important first step is the publication to a easy accessible site of the OCDs phone numbers list. PSPO will organize that.

Comment by PGessler

"It was clear to all, that currently the impact on operation due to emergency power off is severe, since the Racks with the PLC CPUs as well as the MicroTCA systems will be also switched off, what is not what was defined/specified. Therefore it was agreed, that no work on the power distribution/emergency off will be done until the defined date (for FXE 16th April). That work was done there nevertheless is extremely careless. The fact, that this was done on a Sunday and also during user time makes it even much worse then that.  It has to be completely followed up and made clear, that this is not acceptable and will not be repeated again!"

 

SPB

A run of 14 hrs acquiring data was a sort of stress test for the DAQ. It worked. ITDM would like to remove the data. Should be ok.

Due to the triggering of the emergency power off also SPB lost the beam. This was sort of strange since the power off signal was triggered in FXE. AE reported that this behavior is to be expected with the current configuration. This has to be discussed.

 

FXE

DAQ is recovering from the power off. 

Tripping of the interlock caused again by control unit of ion pumps in the week end. During the shutdown the responsible units will be replaced.

In general is is agreed to prepare an overview interlcok panel in the BKR. AE is on boat, CAS to be checked.

500 kHz operation is problematic for the machine due to heavy losses. They are only able to deliver 1 bunch at this rate. FXE will discuss this directly with the PRC (this week is Jan Gruenert)

 

AE related

Follow up to the issue of re-setting pumps after interlock is triggered: VAC and EPS loops need to be updated. HSinn was pushing to have it done as soon as possible without waiting for the shutdown. This is not riskless for the experiments. This will be discussed in a small round (AE, PRC, SPB, FXE)

ITDM

Due to the power outage many devices do not have proper train id. CAS should check it. Time servers also need to be checked.

FXE needs to use digitizers for the upcoming measurements session. These were not implemented in the DAQ. ITDM/FXE/CAS meeting needed to clarify and solve the issue .

 DET

LPD calibration had a problem but should be ok now. 

More supermodules coming.

Communication with upcoming userve concerning data format and other issue has to be improved according to the DET group. SPB suggests to tackle the issue offline.

Entry   FXE emergency power-off has been triggered, posted by Gerd Wellenreuther on 25 Mar 2018, 10:57 

Dear all,
apparently the Emergency Power-Off at FXE was triggered at around 10:00 - 10:30 (my estimate). As far as I know power has been switched on again. BKR / PRC have been informed. More information will be provided by TS / Torsten Schön soon.

Edit: T. Schoen is on site and can be contacted under 0160 977 287 97

Regard, Gerd

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 21 Mar 2018, 10:02 

SPB

On monday there was an issue with a detector related PLC due to misconnection of one EtherCAT cable. The issue has been solved and it "just" resulted in 3 of hours delay in  the AGIPD calibration activity.

FXE, SCS, SQS, XPD, XRO,ITDM no issues reported

AE related

uTCA in XTD 6 are installed 

VAC-Related

Marc Messerchmidt reported  abouit an entry in the DESY Logbook about a pump that triggered the interlock in the SASE1 tunnels. According to Nerea this this seems to be related to the old issue already known. VAC group is working on that. 

 CAS

CYoungman is working on the priority list for the components in SASE2 tunnels. Double checking with HSinn happening soon.

Access for Tue/Wed next week to XTD1 will be requested by CY through HS

Beam is in SPB/FXE this week due to the HERCULES project.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Mar 2018, 10:24 

No new issues to be discussed where reported by any groups.

The status and issues reported on friday are still valid. 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.03.., posted by Adriano Violante on 19 Mar 2018, 08:42 

Photon Run Coordinator (H. Sinn):

1.) SASE1: User experiment SPB could be finished sucussfully after several problems on the weekend (thank to FXE for providing night shift). Big progress in improving throughput of FXE insrument. Next D3 material test with 300 bunches on April 3, 9am. 

 

2.) SASE2: Transmission of electron beam to T5D dump (SASE2 beamline) this week sucessful. Switching between electron beamlines 

works nicely (minor problem witth dark current during switching).

Now air coil measurement going on. BBA needs to done before first lasiing starting on May 2nd. 

To be clarified today: To we need access to XTD in week 12/13.

 

3.) SASE3: Photon commissioning (with 24/7 shifts) finished sucessfully. Now specific tasks are done parasitically to SASE1 operation 

during regular working hours (organized by photon run coordinator). 

 

4.) General (stimulated by DESY operators): EPS system can lead to shutdown of DESY accelerator through MPS by many different channels (PLC in tunnels, Fast valves, PBLM etc). 

On DESY side, MPS provides overview of inputs, but structure difficult to understand and labels are not always conclusive, 

On XFEL side, no general overview panel for all SASEs+Instruments (scene) exists, but it required for facility operation. 

SPB

No issues/no report 

SQS:

- Cleaning of the hutches is ongoing. From 19.3. on, access will be limited. Furthermore, shoe covers have to be worn in E.06 and E.07.
- Electricity in E.22 is delayed. AE and ITDM will be informed about the status by PSPO.
- Vacuum will start the installation of the transfer pipe between the tunnel and E.07 on 19.3.
- SQS will start the installation of their instrumentation on 19.3.
- Some of our beamline components are currently stored at Hera South and must be transported to Schenefeld next week. However, there is an issue with the crane at Hera South. Kai-Erik has to look into this!

 

FXE (P. Zalden / A. Galler):

No issues/no report 

SCS (J.T. Delitz)

No issues/no report 

PP-Laser:

"The laser group has nothing particularly noteworthy to report, only that installation is still going as planned"

Vacuuum:

Installations in XTD6 are ongoing. Damaged vacuum pipes have been 
exchanged/ordered. Vacuum in XTD1 is closed. Control System in XTD1 is 

working and locally tested, Interlock-tests will happen after Easter.

 

XPD:

No issues/no report 

Advanced Electronics:

No issues/no report 

SASE2 Tunnels (C. Youngman)

Going according to plan. 1 week after Easter the movement and EPS loops are supposed to be brought up. 

ITDM (K. Wrona):

No issues/no report 

Detectors (J. Sztuk-Dambietz, P. Lang):

A module for AGIPD was replaced. 

No issues/no report

CAS (H. Santos):

DEMO for the coordinated motion was done during the week. Further tests needed. 

Schedule and discussion about the Karabo rollout process. See presentation bz H. Santos given in the technical meeting.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 14 Mar 2018, 10:06 

SPB (Weinhausen/Round/Mancuso):

  • Again on the fast valve was triggering the MPS interlock system. For XRO was not completely clear what happened. for AE everything is clear and it depends on the wrong MPS configuration with respect to missingl cables. The will discuss this offline and eventually bring back the issue. Linked to this, it is reported that the MPS panel is difficult to decipher for the experiments...

 

  • FXE (Galler):
  • 2 ion pumps went in error and the interlock was triggered. Issue clarified.

 

SASE2 Tunnels (Youngman)

  • Access schedule sorted out. Works in the SASE2 tunnels will be carried out in the period 4-19.04 plus the week before Easter. Discussion with AE on the status of the loops ongoing.

AE (Jardon)

  • It is reported by SPB (March Messerschmidt) that people in the BKR are confused about MPS signal that they are getting from XFEL. The different lables assigned to the signals have to be sorted out and communicated. Nerea and Marc will try to start this clarification offiline.
  • GATT Loop in SASE3 will be updated today
  • Check of the inficon gauges ongoing- eventually update required.

ITDM (Wrona)

  • Lots of data (14 Tb) collected during the last SPB shift.
  • Issue concerning speed of offline data transfer reported by SPB
  • For the user runs in May data will need to be deleted from the offline cluster. A procedure has to be established to clearly communicate with GLs and User groups.
  • SASE3 IT installations have been handed over to XFEL. IT setup ongoing. Network will be available in the experiments by the end of the month.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Mar 2018, 13:18 

SPB (Weinhausen):

  • During the night there was an interlock issue. The fast shutter was triggering the MPS interlock system. After several calls and request of support from SPB to the photon run coordinator and the machine run coordinator the problem was found and the interlock signal bypassed. This was due to some incomplete cabling of the fast valve. While this was knwe, after the last updated the correct configuration was not set up in the controlling PLC.
  • In general one has to note that the experiments do not have access to the MPS panels and there is no well established procedure when MPS interlocks are concerned. This will be reported in the PSO meeting.

FXE (Gawelda):

  • Before the beam shutdown FXE observed that the beam was very unstable.
  • 2 ion pumps went in error and the interlock was triggered. Again in this case is not clear who is responsible for the re setting of the interlock and the pumps.
  • Servers had to be restarted due to wrong train id after the cooling water accident
  • 0.5 MHz operation of the LPD successfully tested. 

SASE2 Tunnels (Youngman)

  • It is reported that the technical coordination of the necessary activities is missing.
  • A list of activities was sent by CYoungman to TTschentscher concerning SASE2 tunnels. In total 10 working days are needed to complete these tasks. This includes 1 week implementation and 1 week commissioning. Carefully planning with DESY is needed to avoid that the necessary 10 working days are scheduled around Easter, which will result in less effective days.

 

CAS (Santos)

  • HSantos is preparing a deployment plan for Karabo whoch includes the requirements and deadlines to be fulfilled by the other support groups (ITDM, DET, AE). The idea is to have this plan presented on Friday for discussion.

 

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 09.03, posted by Adriano Violante on 12 Mar 2018, 08:18 

Photon Run Coordinator (L. Samoylova):

Commissioning during machine studies Tue and Wed and parasitically during SA1 user operation at 
 SASE3 on Thursday and Friday 

SASE1

SPB

User operation, current status (Adrian): got few data from a test system on Saturday. The users’ 
sample delivery technology now seems to deliver nice & stable droplets, so if SPB 
get beam early enough today to set up for a measurement, a full data set could be collected. 
 

FXE

  • Instrument Commissioning
  • Measure beamline transmission (unfocused 550 µJ per pulse at the sample position, with lenses 
    115 uJ)

 Machine studies

  • Wed afternoon: a set of K-mono FEL spectra taken

https://ttfinfo.desy.de/XFELelog/show.jsp?dir=/2018/10/07.03_a&pos=2018-03-09T17:56:20 
 
SASE3

 Thu, Friday - a first experience of the SASE3 commissioning in 30 bunch mode during user operation: 

  • minimal number of undulators (12) for lasing, low intense SASE (XGM shows 10 uJ, linear 
    regime), SRA closed to 2 mm
  • MCP2 @ SASE3 - signal from 30 SASE pulses, consistently decrease with closing the slit down 
    to 0.5 mm

https://ttfinfo.desy.de/elog/XMLlist?file=/XFELelog/data/2018/10/08.03_a&xsl=/elogbook/xsl/elog.xsl&picture=true#2018-03-08T18:24:14 

  Problems:

 'unexpected' from photon side closing XTD1 two working days earlier, explicit schedule 

  • for the south branch tunnels access would be appreciated
  • power off in XHPSC on Thursday at 21:15, no cooling water in experimental hall that led to 
    increasing the temperature in the rack with the MicorTCA crate, the CPUs of the two MicroTCA 
    crates in SPB and one of the two crates in FXE were automatically switched off. SPB crate 
    1 did not come automatically back afterwards, as the result: no train IDs for SPB PLC 
    loops, no MPS for SPB, no Clock and Control for AGIPD, no triggers for SPB systems on 
    Friday
  • Saturday morning the MPS interlock takes into account the signal from one of three fast valve 
    on SPB shutter although these valves are disconnected to SPB EPS interlock. The MPS 
    bit had to be masked

Correction from SPB [12.03.2018 10:10]: This issue was not related to the XTD9 shutter, but to the 
optics hutch shutter. The fast valve in XTD9 is connected to the EPS, the fast valve 
in the OH is not yet connected to the EPS. After the restart of the EPS/MPS on Thursday 
/ Friday after the cooling water issue, the condition for the fast valve in the optics 
hutch was wrongly included in the MPS. 

SPB

1) Thursday 08.03.2018 (8 am - 8 pm) - SPB/SFX commisioning shift

    Notes:

          - everything running

          - RAW data overview very responsive with  data filtering as suggested by Steffen

          - Corrected data preview started very nicely and seem to provide only limited update rate after a few hours running

          - karabo DAQ deices (dataaggregators) need several rests, resulting in a full DAQ restart around 7pm

          - sometimes updates in KARABO were lost

          - preparation for users experiment - over night

 

2) Thursday 08.03.2018 (around 9 pm) - "cooling water" incident

     Notes:

         - vacuum pumps affected

         - AGIPD warmed up

         - uTCAs have tripped/shutdown (some infrastructure needs to replaced)

 

3) Friday 09.03.2018 - morning (User beamtime)

         - damaged uTCAs equipment was replaced but trigger setting needs to be input/ adjusted =  loss of the user beamtime

         - User experiment progresses

SQS:

Hutch cleaning Mid. March

KB tanks installation in parallel with SCS

9-14 air filter will be installed. After that date only clean works have to be carried out

Collision with KB tanks installation and other activities like Rad. Interlock test to verify

 

FXE (P. Zalden / A. Galler):

Setting up the experiment

IPM and XGM data manualy correlated. Would be nice to have the train id working to have the "live" correlation

 

SCS (J.T. Delitz)

  • cleaning of hutch next week (wk11)
  • we will start moving first components wk12-13, ie. ALAS and DPS
  • KB installation (positioning only, no AC+filter required) beginning April-depends on commissioning of precision climate zone (currently discussed with PI)

 

PP-Laser (M. Lederer):

SASE1 commisisonin gonoing.

Some misalignment due to the cooling water accident. To be investigated 

09.04 SASE2/3 laser tables will be installed.

 

Vacuuum (R. Villanueva):

SASE2--------->Good progresses on XTD1 control system deployment: Differential Pumping sectors are ready for first beam // First five vacuum sectors under vacuum and locally tested (already with Karabo). XTD6 tunnel installation phase progresses at good pace.

 

SASE1--------->In general, nothing additional to remark. We are working in a more robust interlock definition to prevent false triggering due of ion pump control signals.

 

SASE3--------->Complete vacuum system is working normally. Gas Attenuator is now under routinary operation up to 2-3 mbar with a UHV interface pressure after its DPS sector < 1*10e-9 mbar.

XRO 

SQS/SCS/XRO collaboration for the mirror coating ongoing

Installation of M5 in preparation

 

XPD (T. Maltezopoulos ):

XGM@XTD2, @XTD9, and @XTD10 are online.

 

XGM@XTD1 is in the loop and accessible from Karabo

(together with AE+CAS).

Currently I test XGM@XTD1 components from DOOCS.

 

XGM@XTD9 shows slightly higher energy then in XTD2.

I calibrate all XGM components twice, but still it remained.

Note that the beam pass the XTD9 XGM with -7 mm offset

(in beam direction 7 mm to the left, to the south).

With this high offset absolute calibration is not guaranteed.

 

Advanced Electronics (P. Gessler):

1 CPU for SPB broken due to the cooling water accident. Already replaced. Being configured

FXE grating integrated in the vac loop

 

SASE2 Tunnels (C. Youngman)

More coordination is needed, especially concerning the access to the tunnels. For the technical details, please see slides on the indico page https://indico.desy.de/indico/event/20115/

 

 

ITDM (K. Wrona):

No problems with overrheating

Problems with Train ID reliability after the heating. Should be checked and monitored online

Documentation of single devices have to be improved. + there is need for a tool to make the sanity check

 

Detectors (J. Sztuk-Dambietz, P. Lang):

LPD commissioning OK + DAQ working. Now LPD off because of cooling water problems.

CAS (H. Santos):

  • Sandor is in a meeting with the Detector group to align requirements regarding AGIPD and DA
  • We started to prioritize and address the (agile) missions of SPB and FXE. As part of this effort:
    • Alessandro started to develop the scenes link on the GUI. This feature is really required and has been present in several SRDs (For example, to link vac sections/loops).
    • We implemented the GUI combo box to select different GUI Server - it is part of the SPB Mission (Leonce)
  • Hamed and Sergey made good progress on the Digitizer. They will work on a demo/talk for the next PBS Meeting.
  • Wajid, Sergey, and Dennis fixed the X2Timer issue reported by FXE (hash/data inconsistency). It is already deployed and running.
  • Regarding the cooling incident. Wajid was the first contacted yesterday. After that Alessandro at 01:00. Today, during the morning, we reinstall Karabo at SPB-RR-SYS-UTC-1.

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 Mar 2018, 11:14 

SPB:

  • Monday morning Karabo failed. It was not possible to operate anything. Aftrer restart it took 2 hrs. to have the tunnel loop and Lopp 5 again operable . Other issues connected to that. CAS is on it.
  • AGIPD can be operated with some workaroung concerning the control system. No final fix available yet.
  • CSS can be operated locally.
  • Coordinated motion test probably on 14.03.

FXE:

  • IPM/XGM correlation data process ongoing. 
  • DAQ worked reliably
  • Scan tool operational for almost every component. Data storage works. Test ongoing.
  • PG points aout that no MPS definitions were given and no MPS is available for FXE yet. To be checked.

SQS

 

  • Corrdination of installations in the hutch with the TUV tests for Rad. Interlock needed.

 

SCS

 

  • Nothing ton report

ITDM:

  • FXE LPD slow data separation will be done today after the meeting
  • Some devices are setting the train id as "0". CAS is informed.

SASE3

MCP HV - Crate restarted. Now ok. There was a misconfiguration of Power/Karabo settings. This meeds to be avoided increasing the communication between people performin operations on the XPD components and the technical support groups.

AE

  • uTCA crate in SASE2 for timing being prepared, as well as PLC for VAC loop
  • Replacement of a uTCA crate in the balcony room for SASE2 needed
Entry   Details on SPB issues reported in the dispatch meetings, posted by Adriano Violante on 05 Mar 2018, 16:37 

Below some clarifications from R. Bean on the issues reported in today's dispatch meeting:

 

- AGIPD suffered many problems which affected the operability (not really a problem of the scene). It was just operable, although not at all efficiently. Problems with the pipeline / DAQ and Karabo controls for the AGIPD suggest that some reasonable amount of work is required to find and solve the problems which may not be independent from each other

- CAS OCD point already addressed with previous email: They were available, just we needed them rather more than we should have done

- The CSS is the large rail that carries the detector. We cannot move it via the integrated system because of a misunderstanding in the implementation of limit / safety switches into the eplan design of the crate. The cabling between rack room / device seems to be fine (but of course not really tested properly because the crate is not correct). We have to use the test crate to move it right now, which is rather tedious since the encoders / limits cannot be handled properly by that system. I am available to discuss the proper implementation of switches / buttons such that we don’t need a fourth attempt at this crate

- For the smaracts we still have axes that are not controllable via the PLC. It is these that would be beneficial if they are fully integrated 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 05 Mar 2018, 11:07 

 

SPB

  • Last night the beam disappeared between 4 and 8. 
  • AGIPD scene showed many problems, both concerning Karabo and Data preview. Detector is not operable.  To solve the issue a joint effort of all the groups involved, as well as the physical presence of experts during the shift is requested. 
  • CSS has to be moved out of the beam. As of now there are problems with cabling that need to be solved
  • Smaract stages are misbehaving. More support from AE (Mahadi) is requested
  • Status of the coordinated motion test was asked. Should be ongoing but the experts were not there.

FXE:

  • Testing fast intensity monitors and LPD 
  • DAQ worked very well
  • Scan tool must me tested
  • Correlation between LPD and fast intensity monitor is problematic due to train id problems. There is a new device to be deloyed on the XGM. Today or tomorrow will be seen whether this solves the issues.
  • BKR reported that the beam tripping was due to some FXE device close to the M3, but FXE is not aware of that. Info will be asked to Harald today during the PSO meeting.

 

Advanced Electronics (P. Gessler):

 

  • MCP HV problem in SASE3 - the power supply failed. The fixing shoud be done according to the priorities, Photon run coordinator decides.

 

ITDM (K. Wrona):

  • FXE slow data DAQ issues: these will be solved splitting the LPD slow data from the rest. small update of the software needed. 
  • Simultaneous acquisition from LPD and cameras is now available and working well.

 

Detectors (J. Sztuk-Dambietz, P. Lang):

  • AGIPD will operate with the old firmware due to problems with the new one
  • No calibration data available as of today
  • AGIPD is in a safe state

 

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.03., posted by Adriano Violante on 02 Mar 2018, 14:36 

Photon Run Coordinator (N. G. Kujala):

  • SASE1
    • Machine delivery 300 pulses upto XTD2 without M1 mirror in beam on Wednesday evening.
    • On Thursday 300 pulses deliver to FXE for radiation test.
    • Collected data using DAQ with 100, 200 and 300 pulses.
    • Large area Detector40 x 40 mm was set-up for radiation test at FXE for .
    • Damage test with 300pulses in FXE hutch with 0.5mm steel, 0.2mm copper and B4C block   
    • Vacuum at XTD2 absorber was stable and temp was also stable for 300 pulses
    • Harald setup piezo motors for M3 of SASE1.
    • Yesterday night beam delivery to SPB with single bunch.
    • ZZ for XTD9 on Tuesday by SPB for CRL test/check.
    • Vacuum on FXE branch in XTD9 was tripped on Tuesday early at 1am, which lost beam permission. Manually I have reset interlock.
  • SASE3
    • SASE3 commissioning is going on.
    • Commissioning the XGM and IMG correlations with Gas ATT and without Gas ATT;
    • SoftMono mirrors is commissioning
    • Gas attenuator commissioned and Raul made look-up table for pressure setting
  • 30bunches were operated in SASE3 with Gas attenuator

SPB

  • Ready for first commissionig
  • AGIPD power and cooling procedures OK
  • Feedback problems between Karabo and AGIPD. Being worked out

 

SQS:

  • Hardware installation starting Mid. March after  cleaning of the hutch
  • FMB will install the mirror tanks in April. Has to be synchronized with the remaning work in the hutches
  • Meetings with AE soon to strat planning the commissioning

 

 

FXE (P. Zalden / A. Galler):

  • Ready to accept first beam
  • Radiation tests done

 

SCS (J.T. Delitz)

  • Removing of wood cover: 05.02.2018
  • Cleaning: end of week 11.
  • End of march beginning of the installation of the first components (ALAS and TIM)
  • Waiting of the exact date for Interlock test to specify more exact the dates for the KB mirror system installation.

PP-Laser (M. Lederer):

  • LAS is now commissioning 3-stage NOPAs for both FXE and SPB.
    ​so far all in plan to finish in March

Vacuuum (R. Villanueva):

  • SASE1 
    • Nothing remarkable: the whole vacuum system works in a very stable way. We only had one incident on the output of 1-2 ion pumps that trigger once the interlock. For that we are investigating the causes .
  • SASE 3.
    • The whole vacuum loop (as required for the first lasing) down to the instrument front-end is under control and no special issues have appeared yet.
    • The SASE3 Gas Attenuator is under manually operation and most of the Photon Commissioning Members are familiar with it. Next steps are aligned with the deployment of the Pressure Feedback Control PID control available at Karabo level and to continue with the software-related tasks.
  • SASE2.
    • XTD1------->The complete vacuum string down to the front-end in the shaft building is under vacuum but in local mode operation (including XGM subsystem)
    •          ------->During this almost past week we already initiated the PLC local tests (i.e. US & DS Differential Pumping are already done), and in KW10 we aim to move on with the rest of the system (ion pumps and vacuum sector gate valves).
    •          ------->Absorber, V0 and Fast Valve wiring are in good progress and we think they could be ready for local tests by the beginning of next week.
    •          ------->The interlock tests are planned also for KW10.
    •          ------->Depending of the progresses of AE and CAS, we may even be able to deploy the first control scenes in Karabo.
    •  
    • XTD6 ------->The assembly works of the whole beamline there progress adequately and without remarkable "show-stoppers" that couldn´t be managed.
    •          ------->Vacuum Group and Optics group (N. Kohlstrunk) are having also special attention and dedication to the SDU vacuum chamber conditioning and preparation works for its upcoming in-vacuum mechanics installation.

 

XPD (T. Maltezopoulos ):

  • XGM in XTD1 is connected to DOOCS (together with DESY)
  • Synchronization of XGM@XTD1 microTCA next week
  • Local tests at XTD1 XGM were finished (together with AE)
  • XTD2, XTD9, and XTD10 XGMs are running 24/7
  • Change to 300 bunches went without problems
  • XTD9 XGM need SRG recalibration ... done meanwhile
  • Wajid, Joakim, Tommaso, and Theo will repeat  SASE3 DAQ Imager/XGM correlation today (need single shot operation)

 

 

Advanced Electronics (P. Gessler):

 

  • Broken terminal between SASE3 MOV2 PLC Loop and Master Loop were replaced last Friday without any side effects. The Train ID is now also provided from the MOV2 loop.
  •  So far, no PLC related export from the SASE2 Tunnel eplans of the vacuum, beam transport and diagnostics PLC crates are possible. Therefore we will build up the XLS file for the start up of the VAC and XGM loops next week. However, the related group plus AE and EETF should meet to evaluate, if an export is possible until end of March in order to use it for further installation work. Otherwise XLS files have to be crates manually again with support from all involved groups. Also consistent documentation is required between diagnostics on one side and vacuum and beam transport eplans.

SASE2 Tunnels (C. Youngman)

  • Table with the set priorities and deadlines available in Indico.

ITDM (K. Wrona):

  • Run Configuration Groups required for the user experiments for FXE and SPB/SFX have been defined and tested
  • Discussion after the meeting: Since the Karabo-DOOCS interface for XGM will be changed and it will affect also how the data arrive at DAQ data aggregators we need to modify and (re)test the BEAM_COND group.

 

 

Detectors (J. Sztuk-Dambietz, P. Lang):

  • AGIPD will operate with the old firmware due to problems with the new one
  • No calibration data available as of today
  • AGIPD is in a safe state

 

CAS (S. Brockhauser):

  • Gotthard for HIREX being operated
  • Progress on GATT commissioning by Valerii
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 28 Feb 2018, 10:55 

SPB:

  • Ion pumps running in the Mirror chamber. Vacuum level OK to run.
  • D.02 is now interlocked and is a clean area.
  • Mahadi and Alessandro are setting up a test system for the coupled movement. The test will probably be done between the 2 users periods.
  • 2 hours of parasitic beam can be used today to check the alignment of the CRLs. The CRLs will be then moved out of the beam to allow the FXE radiation tests tomorrow.
  • Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to have the primary limits included. CSS crate to be modified after clarification with AE/EET.
  • Test of the karabo brigde will be performed with users. It is not yet clear exactly when since this needs synchronization with several groups involved (CAS, ITDM, DET). 

FXE:

  • Radiation test tomorrow
  • LPD test measurements in thhe WE
  • Von Hamos spectrometer alignment until monday

ITDM:

  • SASE1 and 3 have the last DAQ update now. Stable in SASE1 so far.
  • Data sources arrangement being worked out. Today a 45 min session is foreseen with SPB.
  • SPB needs slow data acquisition from 2 cameras for users, apart from AGIPD.

 

VAC/Detector/XPD/CAS: nobody attended

Entry   Status report after dispatch meeting 26.02, posted by Monica Aresté on 26 Feb 2018, 12:09 

SPB:

  • Ion pumps running in the Mirror chamber.
  • Starting test with mirrors together with CAS this week.
  • In general everything in good position to receive beam.
  • Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to have the primary limits included. This will suppose a hardware modification.

AE:

  • SASE3: train IDs in loop2 are working, the problem was fixed last Friday.

ITDM:

  • Measurements for commissioning continues.

CAS:

  • H.Santos inform that CAS has not resources to run tasks for SASE2, this might affect the date for first lasing in SASE2. Priorities are SASE1 operation and SASE3 commissioning.
  • G. Wellenreuther will bring this topic to the PSO meeting.

FXE/VAC/Detector/XPD: nobody attended

 

Entry   Status and plans after Readiness Meeting 23.02. , posted by Gerd Wellenreuther on 23 Feb 2018, 15:54 

Photon Run Coordinator (L. Samoylova):

  • SASE1 tuning is ongoing (350 microJ)
  • SASE3 3000microJ
  • SASE1 interlocks enabled, SASE3 only vacuum interlock enabled
  • Soft monochromator is being commissioned
  • K-mono studies were carried out
  • HiRex was being commissioned
  • SASE1 and SASE3 DAQ was used
  • Gain curves should now be possible

 

SPB/SFX (M. Messerschmidt):

  • Recorded data with detector integrated in Karabo
  • problems with coupled motions persist, ran into & were not able to get out of end switches using Karabo
  • leak at mirror tank still has to be localized

 

FXE (P. Zalden / A. Galler):

  • Will be ready for beam by the end of the week
  • chamber was pumped, crystals mounted
  • I0 monitor was tested and commissioned
  • only have permission for <=2 bunches
  • scantool: Train IDs are not captured
  • DAQ-tests look good for LPD

PP-Laser (M. Lederer):

  • Final commissioning of the laser is ongoing
  • integration of the laser into DAQ during the April shutdown

 

Vacuuum (M. Dommach):

SASE1

  • nothing to report; Vacuum system ready of beam operation

SASE3:

  • XTD10 was open last Tuesday
  • Together with Diagnostic group Exchange of Turbo pump on XGM
  • Gas Attenuator commissioning ongoing

SASE2:

  • Working on cabling of XTD1 components and vacuum installation in XTD6
  • Installation of cleantent at HED-SDU ongoing.

 

XPD (J. Grünert):

XGM SASE3 

  • tuesday XPD made XTD10 access to repair SASE3 XGM vacuum
  • one turbo pump failed Saturday noon, decided to repair during access tuesday, exchanged pump
  • tuesday detected another vacuum trip in the differential pumping around the XGM
  • wednesday afternoon VAC made ZZ-access to „repair“ what tripped the vacuum interlock
  • wednesday to thursday night: checking proper and stable SASE3 vacuum operation - is ok
  • XGM is back in operation since thursday morning 8am

XGM status overall:

  • XTD2 and XTD10 XGMs in operation
  • When will the XGM in XTD9 be needed? ==> Harald and Liuba believe that beam might be sent to XTD9 this weekend, therefore they request to start XTD9 operation today afternoon

Imagers 

  • SQS Exit slit imager has been set to beam position and can be used for some basic commissioning (limited functionality)

thursday work with beam:

  • SASE1 KMONO studies: two cells studies, height adjustment of single cells using DAQ (until it crashed at noon), data analysis today
  • HIREX commissioning
  • SASE1 beam conditions recorded with DAQ

Correlation of beam intensity monitored by XGM and imagers

  • Required e.g. for the current Gas Attenuator Transmission Calibration
  • need to prepare a simple table of calibration values for all imagers which are used as supplementary intensity monitors
  • will discuss offline among photon run coordinators

SASE2

  • need to rearrange space in one rack to be able to put our last crate into tunnel XTD1: Wolfgang will contact Ulf and VAC
  • Request to CAS: 
  • DOOCS devices shall be created for SASE3 (as in SASE1) for undulator and phase shifter and electron beam energy

Advanced Electronics (P. Gessler):

  • SASE3: No train IDs are being delivered in loop 2. Repair could potentially / in the worst case affect all electronics. ==> Should be fixed right now to get it done.

 

ITDM (K. Wrona):

  • Configuration / Testing of DAQ continues

Detectors (J. Sztuk-Dambietz, P. Lang):

  • AGIDP ready for 100/64 bunch operation
  • there will be a two-day training for AGIPD-operators
  • LPD was tested with new Karabo / DAQ
  • LPD has hardware problem regarding power line for one module, to be fixed

CAS (S. Brockhauser):

  • The issue reported in the beginning of the week regarding the TrainIDs was identified. We have an integer overflow problem when connection is lost with the timeserver. That happens sporadically, and we are working to fix it since yesterday.
  • We released Karabo Hotfix 2.2.2.2 to fix an issue on the RunConfiguratorGroup at SA1 (ITDM already checked and it is working)
  • We have improved the communication protocol with AE on handling loops/PLC updates and related (re)establishment of the Karabo services.
  • AGIPD library is extended to supply information if detector is in stop or acquire state. The next step will add the "acquisition time" to enable scantool integration
  • The old digitizer is running and integrated with DAQ. Also, we will add the "acquisition time" to enable scantool integration
  • We started to call the Sprint Meetings (for the moment we focus on updating the priorities of FXE and SPB topics)
  • A list of 'potential' SA3 technical coordingation activities was sent to the 'Photon run coordinators' and PSPO listing what technical coordination tasks can be done parasitically during access period.
  • The SA2 technical coordination planning has started initially with the front line groups: ITDM, AE, VAC, then Beam transport.
    • ITDM have nearly finished the server installation (same as SA3), AE have responded with loop and MTCA plans
    • VAC and Beam Transport have so far not confirmed their meetings for this task

AoB:

E. Boyd: A test @ FXE with Cu-Target and 300 bunches is required. This will affect the areas / hutches around FXE

A. Mancuso: Will try to work around this, but in general a message one week beforehand would be required / appreciated.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 21 Feb 2018, 10:55 

SPB

  • KB chamber being pumped down
  • Smaract commissioning ongoing
  • Coordinate motion for VAC ready to be tested (probably tomorrow). It has to be agreed with Richard Bean
  • Clean-up slits Karabo middle layer deployed and working. - The same hase to be done for the power slits.
 FXE
  • DAQ test ongoing - fixing of bugs
  • After FXE has been moved into the new topic is not possible to read tunnel vacuum pressure anymore. Still the case.

 

  • XPD
  • XGM in SASE3 fixed (A turbo broke - replaced)
  • One exit slit Imager in XTD 10 commissioned

 

AE

  • PBLM moto problem was found to be due to a wrong Karabo-PLC linking. ==> FIXED
  • Soft mono commissioning started and AE support was required. DONE

ITDM

  •  Main problems with Train ID solved. Some problems still remain for some beckhoff loops in the tunnels==> AE on that.
  • Some way to document the change of data format for devices has and will be found by IDTM
  • Data source running for FXE. Changes have to be clearly communicated. 

CAS

  • Soft fix improving the GUI deployed. No 2.2.2 ready.
    
  • ​Issue with Karabo device returning the sensors data (e.g. cooling AGIPD) is being investigated. The Bug was found also in test environment but still random.
     

SASE3 - CY

  • GATT works
  • Inficon device to be improved (loop restart needed)
  • CAS will deliver a method to deal with the configuration changes asked by the experiments, redirecting the changes to the proper platform (Firmware (AE), Karabo...)
    Reply   Re: Status report after dispatch meeting 09.30, posted by Alessandro Silenzi on 21 Feb 2018, 13:49 

Small correction:

The coordinated motion is the KB-mirror's, not the Vacuum.

The postfix is 2.2.2.1 and includes features that were not included in 2.2.2

Karabo 2.2.2 is ready

 

Adriano Violante wrote:

SPB

  • KB chamber being pumped down
  • Smaract commissioning ongoing
  • Coordinate motion for VAC ready to be tested (probably tomorrow). It has to be agreed with Richard Bean
  • Clean-up slits Karabo middle layer deployed and working. - The same hase to be done for the power slits.
 FXE
  • DAQ test ongoing - fixing of bugs
  • After FXE has been moved into the new topic is not possible to read tunnel vacuum pressure anymore. Still the case.

 

  • XPD
  • XGM in SASE3 fixed (A turbo broke - replaced)
  • One exit slit Imager in XTD 10 commissioned

 

AE

  • PBLM moto problem was found to be due to a wrong Karabo-PLC linking. ==> FIXED
  • Soft mono commissioning started and AE support was required. DONE

ITDM

  •  Main problems with Train ID solved. Some problems still remain for some beckhoff loops in the tunnels==> AE on that.
  • Some way to document the change of data format for devices has and will be found by IDTM
  • Data source running for FXE. Changes have to be clearly communicated. 

CAS

  • Soft fix improving the GUI deployed. No 2.2.2 ready.
    
  • ​Issue with Karabo device returning the sensors data (e.g. cooling AGIPD) is being investigated. The Bug was found also in test environment but still random.
     

SASE3 - CY

  • GATT works
  • Inficon device to be improved (loop restart needed)
  • CAS will deliver a method to deal with the configuration changes asked by the experiments, redirecting the changes to the proper platform (Firmware (AE), Karabo...)

 

Entry   FXE Beam Shutter Key, posted by Eric Boyd on 20 Feb 2018, 12:29 

The FXE beamshutter key has been installed into the interlock system after satisfactory completion of the FXE Chicane and Radiation Protection Sticker Checklist. The FXE Experiment hutch is now ready to receive xfel beam as required by the FXE instrument group.

However, the bunch mode MUST be limited to 1 or 2 bunches until the new user chicane is tested with thirty bunches using the copper target. This can be done whenever the parameters can be practically put into place. The test will be similar to the hutch commissioning where once it has been confirmed that the beam is on target. I will take radiation measurements at the chicane. This is the only place where radiation measurements will be required. Please provide me as much notice as possible prior to the date and time that 30 bunches will be brought into the FXE Experiment hutch.

I have also place 3 additional area monitoring dosimeters in the FXE Experiment. One on the robot arm where the D3 pandora place holder is. One above the old user chicane on the D.05 side and one inside the new user chicane on the control room side.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Feb 2018, 09:56 

SPB

  • KB chamber being pumped down
    
  • interaction with AE is ognoing concerning update pf Loop 5 and AGIPD cooling procedure ongoing
  • Smaract commissioning ongoing
  • The goal is to be ready to start commissioning with beam on 01.03.
  • Slit Karabo middle layer - integtration and final fixing being finalized by A. SIlenzi
 FXE
  • DAQ test ongoing - fixing of bugs
  • After FXE has been moved into the new topic is not possible to read tunnel vacuum pressure anymore. Being discussed with CAS
  • Permission to use parasitic beam next week requested to the radiation safety group.

XPD

  • XGM in SASE3 requires physical intervention to be fixed. Access request for tomorrow.
  • DAQ groups definition ongoing and being clarified with ITDM

AE

  • PBLM moto problem was found to be due to a wrong Karabo-PLC linking. If the tunnel will be accessible tomorrow the issue will be solved. HSinn to decide on priority.
  • Soft mono commissioning started and AE support was required. It is not clear what priority does it have. Mahadi is anyway working on that today ad 14:00. If the intervention is found to require more time one has to see.

ITDM

  •  During the FXE DAQ tests many problems were found:
    • issues with digitizers
    • issues with scan
    • issues with images acquisition. In this case the problem has been identified (Train ID was 0). KWrona is in contact with CAS to fix the bug.

CAS

  • The issue reported by SPB about no data being read from AGIPD temperature sensors has been identified by Gero (CAS) and the fixing is ongoing. 

Report of the XTD10 interventions from last week - Tuesday and Wednesday - C. Youngman 

Many thanks to those who contribute to the "SA3 'further technical coordination push" onTuesday (no-beam XTD10 closed) and Wednesday (XTD10 open) mini-shutdown, below is brief summary. The status items were not highlighted during PSPO's readiness meeting AoB section but are useful to know. Those issues that were raised are contained in the conclusion section. 

We leave the SA3 beamline with a functioning interlock, but you should additionally watch and test your component and ensure that beam operation is possible.

The principle task on Tuesday was

  • for ITDM to shutdown and update f/w of the control server CPU hosts in the balcony room, and
  • for CAS to replace the Karabo 2.1.18, running since the Oct-Nov shutdown 2017, with Karabo 2.2.1 which is already running on the SA1 installation. 
    • A number of problems during the installation were addressed and a stable deployment was finally reached early in the evening.

The principle task on Wednesday were

  • test the updated GATT Ebara pump updated f/w and its s/w counterpart
  • test that GATT Bronkhorst Mass-Flow valve f/w worked: correcting conversion errors and the incorrect setting of property r/w attributes
  • test that GATT Inficon gauge f/w did not crash the loop and correct  conversion and r/w errors as with the the Mass-Flow valves
  • perform Beckhoff-local tests on one or more the DOD motor axes as they were expected to be wrongly wired (as seen in the Jan-Dec shutdown in the VSLIT)
  • update the s/w to reflect changes in the GATT f/w
  • address difference in the s/w introduced by the move to Karabo 2.2.1

The key-point task listed above have been attained with the following caveats:

  • There is a h/w fault which prevents the second Ebara pump being fully controllable remotely, it is currently locally controlled.
  • Bronkhorst f/w and s/w is usable, the conversion is correct, but additional s/w work is required to align the s/w
  • The Inficon f/w works (it does not crash the loop), the f/w conversion error is identified but not enough time was available to modify it.
  • some s/w issues remain which are being addressed (tagging of Ebara, Bronkhorst and Inficon s/w, correct configuration of the vacuum-section..)
  • the automatic update of project and scenes was not completely successful so project and scene owners should check and correct their scenes. The auto update procedure will be improved.
  • Some data logging information was lost, but e now have regained a standard implementation (not hot-fixed) which should improve the this.
  • After measuring that the DOD axes (1 of 10) were incorrectly wired it was concluded that all were incorrectly wired (as had been the VSLIT in the Dec-Jan shutdown)
    • Benoit and Daniele managed to rewire all 10 DOD axes during the mini shutdown and test 1 axis with Karabo.
  • PES tests of multi-board digitizer s/w and f/w were continued (with measurements at the crate), these are promising as 'raw' and 'processed' data are now concurrently available.

In conclusion - good progress was made and this type of 'commissioning' mini-shutdown (anything longer than ~4 hours which includes somebody elses longer ZZ) should be performed as often as possible.

This requires

  • that the photon run coordinator team know that there is a "list of task" to be performed which are not in the ZZ list
  • that a selection of these tasks can be performed within the time budget of a mini-shutdown and that these do not compromise SA3 tunnel operation
  • that the photon run coordinators inform the SA3 technical commissioning team (contact a member of the "SA3 tech coord" CAS team setup by Sandor, e.g. Chris, Valerii or Wajid ) so that they can organize the work in time (or report that they cannot as something or someone is not available).

During the next few days a "list-of-task" will be created. This could include technical commissioning actions for SA3: PBLM, ExitSlits, very end of beamline imagers where the status needs updating, etc.

Also remember that the CAS team tries hard to satisfy as many requests as possible, but prioritization will be done, so make your case thoroughly and don't expect it to simply happen (it has to be on the radar screen). In particular h/w, f/w and related s/w tests needing access will be done first and non-critical s/w work will be left until after tunnel closure. And remember to check your projects, scenes, and macros before you need them.

 

Entry   CAS OCD, posted by Jan Grünert on 18 Feb 2018, 17:20 

Here is a information from Sandor on CAS OCD Numbers
(this info is copied from the SASE1 commissioning logbook): 

during the day: 98053   (8:00 - 16:00)

overnight: 98054  (11:00 - 8:00 next day) 

during the weekend it is #53 or #54  (Saturday #53 8:00 - 8:00 next day, Sunday #54 8:00- 8:00 next day)

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.02., posted by Adriano Violante on 16 Feb 2018, 15:44 

Photon Run Coordinator Report to Readiness Meeting

The maintainance on Wednesday was very successful and all goals were reached (and some extras). 

Thanks to everybody involved in planning and execution! 

 

- Installation of Karabo 2.2.x in XTD10 went smoothly. 

 

- SASE1 tuning studies are ongoing. Still there are some things to be learned on compression and 

optimizations will go on Friday. Currently around 250 uJ.

 

Recent achievments in commissioning: 

SASE1: 

-Peter aligned CRLs in XTD2 to beam. 

-Naresh could work on Hirex

-Liuba and Ilia started pointing studies with imagers (?)

Problem: We found out that gate vales of vacuum are not connected to DESY MPS

(waek beam was hitting one closed valve behind Hirex for about 2 hours)

 

SASE3: 

- Gas attenuator commissioning started

- Calibration of SRA to optical center of beamline

- The undulator beam was steered 4 mm horizontally. The vertical steering requires movement of undulator center, 

which will be tried possibly on Friday

- Cross calibration of XGM to FEL imager started last night. 

SPB

- KB mirrors
        - installation of horizontal micron KBs finished (approx 8 working days were required)
        - pump carts attached, expected that one week is required before valves can be re-opened (Vacuum group needs ZZ to reconnect valves on the XTD9 side)
        - installation of vertical micron KBs in April
        - D02 will remain cleanroom during the intervening time, i.e. all companies / groups (internal and external) coming on site should be briefed. No access without permission and accompaniment
        - controls tests on elmos completed via Karabo, help from Nerea / Mahadi to get everything working as expected
- configuration of smaract motors
        - commissioning setup will be used during first beam week in March
        - Re-config of smaract controllers by Marcin / Grant / Mahadi mostly completed
- AGIPD
        - firmware update scheduled for this week will not be completed as DESY detector group firmware expert is not available
        - remain limited to 32 patterns per train
        - automatic cooling and powering procedures are not working reliably (requires investigation poss. CAS?)
        - AGIPD chiller fell into an error state after removal of a separate crate BKF00072 (SPB_IRU_LIC), loop 5 redundancy requires investigation (AE)
- Karabo
        - GUI is slow to update or does sometimes not update (request investigation by CAS)
        - devices (e.g. those reporting pressure / temperature) have to be re-started before updates are seen in Karabo (request investigation by CAS)
        - Users have questions about any changes in the implementation of the 'Karabo bridge’. Technical information on how information is broadcast from Karabo is required in order to ensure that users can adapt their monitoring software 

 
- data trial run
        - Robert suggested trial run for DAQ / user software plugin before the first experiment. SPB can contribute to the execution of these tests and involving users. Requires also action from CAS and ITDM teams

 

FXE

  • Diamond grating in XTD9 can be controlled remotely now
  • DAQ test ongoing
  • LPD calibration to be  performed

Laser:

  •  Installation according to the plan, no major delays. 

Vacuum

SASE1:     ZZ access to connect SPB valves

SASE3:     tripping of interlock seems to be understood, interlock conditions changed,

                if it happens again, the two effected gauges will be removed from interlock until April

           Gas Attenuator is operational, Raul did some tests yesterday, up to 1 mbar

           No feedback control on gas pressure, only manual setting of gas flow

           The device can only be operated by experts so far

Optics

  • see PRC section 

XPD

Last wednesday tunnel access:

  • „repaired“ SA1 IMGSR trigger (with AE)
  • „repaired“ SA3 XGM, restarted (but intentionally without HAMP)
  • better routing / fixing of purple Beckhoff loop Ethernet cables and fiber connections is needed

SASE3 vacuum interlock trips (which eventually led to XGM failure on Saturday and reoccured monday night again) were strongly investigated by VAC : now understood ?

work on cross-calibration between XGMs and Imagers (as backup intensity/position monitors when XGM is out of order) with Laurent

DAQ: work with Krzysztof and Luis to get SASE1 DAQ back in operation, and to start SASE3 DAQ (can we test today ?)

Current status of SASE delivery (max. µJ in SA1/SA3): yesterday 390 / 200, this morning 190 / 600

Request to CAS: please plan to send for "training" or "experience" some CAS people to BKR during beam operation, especially the people in CAS who do OCD.

On behalf of Natalia : report to AE on detected issues with the ELMO controller settinsome hours gs of the PBLM motors in SASE1

 

AE

- stuck trigger timing module in XTD2 restarted (related to SR imager)

- Gas Attenuator PLC loop updated

- PLC modules in SPB rack with SmarACT system rearranged according to updated documentation

- Two bugs in PLC Framework identified, which are fixed now in the current version, but is not deployed yet to most systems:

     - Access rights are not correctly transferred to Karabo. This leads to the fact, that in cases of very special parameters only read access is possible via Karabo (these are automatically injected parameters in Karabo). If you come to the problem of not being able to write such a parameter, please let AE know and we can set it directly to the PLC. This will be solved with the next PLC loop update.

     - A bug was identified, which could in the worst case lead to a full crash of the related PLC. This could be caused by a „re-init“ on a device on the PLC. Therefore do no re-inits on PLC devices. If you really see the need for a re-init of a certain device, please let AE know about this and we see, if this is required and how this could be done. Also this issue will be fixed with the next scheduled update of the PLC loop.

 

ITDM

  •  Cameras issue solved.
  • SASE3 DAQ testing to start
  • XGM data acquisition to be tested due to karabo/DAQ possible lost of information recently debugged.

CAS

+ Karabo 2.2.2 is released
+ 3rd control pc is set up in BKR
+ SASE3 is running Karabo 2.2.1
+ Karabo 2.2.1 is tested with DAQ
+ as we moved into weeks of commissioning, CAS OCD is regularly (basically every night) involved in and provides support for partly software and partly hardware issues
+ as experiments are coming, Data Analysis integration requests (eg. on Karabo Bridge) shall be channeled to Hans (and to the newly setup DA contacts: Thomas for SPB and Cyril for FXE) directly
+ the gui slowness problem reported by SPB needs to be checked if it comes from the GUI client or from the server and shall be tested with the new Karabo hotfix 2.2.2, too.

DET

LPD canlbration analisis ongoing

LPD Long integration time acquisition being tested

AGIPD: colntrol optimized and tested. Firmware being tested, the aim is to ioncrease the acquisition speed.

AGIPD: next week calibration data to be taken. 

AGIPD: Sensors in the centra area that underwent scattered beam to be checked.

CYoungman - SASE3

 - good progress was made and this type of 'commissioning' mini-shutdown (anything longer than 6 hours) should be performed as often as possible (Wed. shutdown). Next work items would involve: PBLM, ExitSlits....

LBatchelor - XTD6

XTD6: both CRLs (MID CRL2 and HED CRL2) ready for installation (lenses installed and aligned, chambers sealed). Installation should happen next week.

 

 

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 14 Feb 2018, 14:21 

SPB

  • MIddle layer karabo devices are responsible for the det. Karabo problems. Issue being addressed.
  • 2 mirrors in D.02 installed.
  • Test of the mirrors movements is done.
  • Mirrors cooling bars being installed

Vacuum

  • SASE3: 
    • Spikes of the downstream DPS gauges are responsible for the interlocks tripping. Probable cause is related to the beckhoff terminals of the DPS (different from the other gauges). Ongoing.

XPD

  • Pop-in monitor filters in XTD10 being changed
  • Exit slit imager after Mono XTD10 has ot be commissioned and scintillator has to be put out of the beam way.

 

AE

  •  It can happena that some parameters cannot be set using Karabo due to lack of writing rights. A fix has been found but we would need to update all the loops. Since the problem is just occurring from time to time, AE asks to report specific cases for whoch a solution will be found. Same things happens with the re initialization of some devices. In this case the PLC crashes.
  • Timing device in XTD 2 stopped working. Will be fixed today either by remote re start or by local intervention.

 

ITDM

  • Broken server replaced
  • Tomorrow there will be an update of the cluster between 9:00 and 10:00. DAQ will be down.
  • Reboot of the online cluster needed. To be agreed with Detector group. 1 hour downtime also in this case.

CAS

  •  In SASE3, deployment of new (2.2.1) Karabo happened yesterday and seems stable, but brittle. Analysis of the reason ongoing.
  • Today GAT final fixes plus testing will be performed
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Feb 2018, 10:03 

SPB

  • During operation Karabo crashed. As soon as detector is being operated the problem appears. Fixing is still ongoing.
  • 2 mirrors in D.02 are being installed.
  • Test of the mirrors movements has been performed.

FXE

  • Debug of implemented devices ongoing
  • Diamond grating in XTD9 has to be moved out of the beam way manually (no remote controls implemented due to long lead time of required beckhoff teminals). Access requested for Wednesday.
  • Vac group will check whether beckhoff terminals are available to allow the remote control of the dimaond grating

 

Vacuum

  • During the weekend the XGM in SASE3 was damaged. Details still unknown. 

AE

  •  SASE2 XGM local test ongoing
  • GAT loop update in SASE3 being done.
  • Local checks in XTD10 on Wed.

 

ITDM

  •  Slow data acquisition issue affecting imagers: solved
  • One server died over the week end. ITDM notified only today.

 

 

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 09.02., posted by Adriano Violante on 12 Feb 2018, 08:46 

General

"In the beginning of this meeting SM congratulated the whole staff of the European XFEL and in particular the commissioning team with the very important achievements 
- the first SASE3 lasing / bi-lasing at SASE3/SASE1. It happened yesterday late evening. More information will be given during our PBS meeting next week."

 

Photon Run Coordinator Report to Readiness Meeting

  • parasitic operation in SASE3 (closed 3 undulator segments) for photon commissioning with SR-beam
    • V0 opened, vacuum open down to XHEXP-shutters
    • photon beam detected down to FEL imager, yesterday until SR absorber beyond mirrors M1/M2 and MCP
  • photon systems supported tuning/search for SASE1 lasing
  • Progress in SASE3: 
    • First Lasing in SASE3/XTD10 
    • simultaneous lasing SASE1 and SASE3

SPB

  • During operation Karabo crashed. The problem is not clear yet. Det. loop was affetcted ==> AGIPD tests stopped!
  • 2 mirrors in D.02 are being installed.
  • Test of the mirrors movements is ongoing
  • Motors issues are being checked by AE (Mahadi)

FXE

  • Gotthard det. and digitizers back to work
  • Leak close to the diamond window being fixed

Laser:

  • Timing system has been upgraded - currently we can have any repetitive laser pattern for each laser, number of laser pulses in not limited to number of electron bunches, also we can have lasing when there is no x-ray (electron bunch)
  •  Installation according to the plan, no major delays. No commitment to experiments for laser availability in March.

Vacuum

  • SASE2:
    • XTD1 under vacuum up to XS2 shutter
  • SASE3: 
    • interlock problems solved, runs without problems since yesterday
    • GasAttenuator loop needs update. when is the best time to do that? to be agreed with PRC

Optics

  • issues mainly in the XPD section 

XPD

  • SASE1 : photon systems supported tuning/search for SASE1 lasing
    • tests of DAQ in SASE1 ongoing
  • parasitic operation in SASE3 (closed 3 undulator segments) for photon commissioning with SR-beam
    • V0 opened, vacuum open down to XHEXP-shutters
    • photon beam detected down to FEL imager, yesterday until SR absorber beyond mirrors M1/M2 and MCP
  • karabo update to 2.2.x in SASE3 tunnel scheduled for next tuesday morning
  • SASE3 DAQ urgently required
  • issues with in-vacuum goniometer motor control of KMONO
  • issues with IMGFEL to be understood - found a scintillator which works when we have FEL radiation

 

AE

  •  The need to properly plan the activities close to the tunnels closing is pointed put.
  • The need of a specific technical coordinator as in SASE3 for the SASE2 tunnels is pointed out

 

ITDM

  •  Sase3 DAQ not ready since Karabo is not yet up-to-date
  •  Slow data acquisition issue affecting cameras: being worked out.

 

CAS

  •  In SASE3, deployment of new (2.2.1) Karabo versionwas  delayed because of many people getting the flu.
  •  2.2.2 release test cycle ongoing

 

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 Feb 2018, 09:47 

SPB/SFX

- An AGIPD crate providing power broke down and has been fixed already by Kai-Eric Ballack. This delayed the data acquisition test planned by Jola. These are being done today.

 -Synch motion of mirrors will be tested with fake mirrors in D.09 as soon as the control is ready. Work is ongoing.

-First mirron in the SPB optics hutch will be installed today. 

- New Karabo release working smoothly so far.

FXE

- CRL in the tunnel being commissioned

 -Leak close to the diamond window being fixed. If everything goes fine ready for parasitic beam on Wed next week.

VAC

-Vacuum interlock tripped twice in the last 12 hours. Issue has to be clarified with CAS.

AE

-Reconfiguration of the SmarACT controllers between rotary and linear motion is being carried out. Marcin and Mahadi are the main players here.

ITDM

-Major safety update of the cluster has to be done. ITDM proposal is to do it next week. SPB and FXE opted for the early morning (between 8 and 10). Exact date will be announced by ITDM as soon as possible.

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 05 Feb 2018, 13:18 

SPB

- MIrrors installation (2 horizontal mirrors) in D.02 has started 

 -Synch motion of mirrors will be tested with fake mirrors in D.09 as soon as the control is ready.

SASE3 - CYoungman

- After SASE3 tunnels were closed it was discovered that was not pobbile to set values of the massflow (GAT loop). This required a remote intervention (firmware) that was supposed to be fast and easy  but it was not, and this required work until friday evening. Current status is: The gas attenuator secion closed and in static vacuum since the shutdown of a turbo pump was required. The system is in asafe status.The issues are being analized and solved with experts right now.

-It is important to establish a procedure to set priorities for ZZ access. The issue will be brought up in the PSO meeting

ITDM

 

-AGIPD p[roject is OK. Jolanta will start taking data already today

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.02., posted by Adriano Violante on 05 Feb 2018, 09:11 

SPB

- Loops update OK

- Issue with SmarACT controllers. AE is on it (see below).

- Synch motion of mirrors motion being worked out with AE.

 

FXE

 

- Loops update OK

- DAQ updated

- CRL in the tunnel have two encoders with problems. Can be disabled and are not a problem for operation.

- A leak before the diamond window was found. Being closed now.

- Preparation for timing tool commissioning ongoing

- The new user chicane will be probably cut next week.

 

Laser:

 

- SASE 1 commissioning and upgrade moves according to plan

 

- SASE 2 and 3:  so far we still have green light concerning access control, laser safety installations, network and sync for installation of laser tables starting at the beginning of April.

 

 

Vacuum

 

- SASE1 und SASE3 vacuum systems are ready for restart of beam operation

- update of SASE1 vacuum loop on Wednesday caused many problems (all ion pumps in error state)

 

Optics

 

- Test piezo motors XTD9 today

 

 

XPD

- XTD10: K-Mono, XGM, PES, filter chamber, imagers operational except:

- Karabo tests for Exit slit imager.

- Camera cables to be exchanged for 2 imagers, ZZ access 1h.

- PES, issues with digitiser and MPOD scenes.

 

- XTD2 and 9: All components operational, Hirex also including Gotthard.

 

- Next steps

- Progress on scenes and projects implementations.

- Compatibility with new Karabo, Karabo GUI.

- Test and improve usage of DAQ.

 

AE

 

- Coordinated motion of MC2 Based Motors were implemented and presented to first users in SPB and XPO as well as to CAS

- The issue with the SmarACT motor controllers observed in the past was due to an issue in the controller. It was solved with an firmware update and requird configuration with dip switches. For this the later usage (e.g. rotary, linear, etc stages) has to be defined. The modifications for SPB is ongoing.

- AE observed, that in some cases PLC related electrical work was carried out until the very last day of open tunnel, which require a PLC firmware update and successive test. Since there is also a risk in the firmware update as it could be, that during tests issues might be observed, there is no access anymore to the actual system and thus could not be solved without ZZ or new access time. We had issues due to this, where at least temporary workarounds were possible - but it could also be different. This is a high risk, which should be know to everyone involved and decided on, if we want to continue like this in the future. AE would prefer to stop with any electrical PLC changes at least some days before tunnel closure and allow firmware updates (possible Karabo changes) and full tests by the users of the components with Karabo in order to identify and solve possible issues.

- Another issue took place, where a change request for a PLC change was issued, but instead of waiting for the finally modified designs to then do the related hardware modification, the modification on hardware were done without any new designs. This creates many problems: no CAD design according to hardware exists, the current revision state of the module is not defined, no firmware structure could be exported and generated for the current design, etc. Therefore modifications without new CAD design and consulting AE is not allowed!

 

 

ITDM

 

- Sase3 tunnels: cabling issues solved.

- DAQ so far stable. Has to be tested at full load now with the new Karabo.

- DAQ update for Tunnels in SASE1 and 3 ongoing. Today and next Monday will be test days.

- Gateway update done: small issue with SSH connections, easily solvable==> the procedure will be posted in the logbook

- The Maxwell cluster will need to be shut down for 2 days next week due to upgrades.

 

CAS

 

-  2.2.1 has been deployed without real problems on FXE, LAS, SPB, SA1.

-    In SASE3, it is still 2.1.18 and it will be updated early next week

-    2.2.2 release test cycle almost finished. The release will be published early next week - This release will not be mandatory, but recommended based on the new GUI benefits.

-    SASE3 Tunnel most critical tasks were done, including the gas attenuator by Valerii. It was a really complex task that Valerii went deeply and get it done for us all!

-    Sergey keeps working in Digitizer with Hamed (AE) but based on the deadline they decided to go for the old protocol.

-    Andrea (Alessandro and Steffen) has been working on the AGIPD Library to report when AGIPD will stop to acquire data

-    Gabriele started discussions to address the DAQ for LAS with ITDM.

-    XGM's DOOCS integration has been updated to address TrainID issues. We must allocate 2-3 days to test it with Beam.

 

Entry   exflgateway migration, posted by ITDM Admin on 31 Jan 2018, 10:06 

Today late in the evening (~22:00), the exflgateway will be migrated to a new hardware. All users will be logged out before migration and home folders will be copied.

After migration is finished, you may experience ssh warning about ssh host key. For all centrally managed Linux this should be fixed the following morning. For all other, like Windows, or yellow desktops, you need to remove the old key and/or accept a changed one. 

Best 

Janusz

    Reply   Re: exflgateway migration, posted by ITDM Admin on 31 Jan 2018, 22:34 

The migration has finished, to avoid temporary problem with ssh you can use

ssh exflgateway -o StrictHostKeyChecking=no

until it will be resolved in the morning ( the usual update of all hosts ssh keys).

Home folder has been changed to /data/<user_name> and it is slightly bigger then before...

Let me know if there is still anything missing.

best, Janusz

ITDM Admin wrote:

Today late in the evening (~22:00), the exflgateway will be migrated to a new hardware. All users will be logged out before migration and home folders will be copied.

After migration is finished, you may experience ssh warning about ssh host key. For all centrally managed Linux this should be fixed the following morning. For all other, like Windows, or yellow desktops, you need to remove the old key and/or accept a changed one. 

Best 

Janusz

 

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 31 Jan 2018, 14:56 

SPB/SFX:

  • Fixing of Karabo scenes ongoing
  • Loop 5 need to be updated after discussion with DET group (Jolanta Stuk)
  • A meeting with AE will take place today to discuss the synchronous movement of the mirrors motor. 
  • The test on the NKB chamber of the indipendent movement should take place. It has to be double checked that such motors are implemented in Karabo.

CAS SASE3 (C. Youngman):

  • SASE3 tunnels closing today at 14:00. All the critical tasks were done. 
  • The day before the first lasing, a ZZ access is strongly requested. The request will be discussed in the PSO meeting.

ITDM:

  • Tomorrow the DAQ will be available for the AGIPD. LPD to follow. The goal is to have SASE1 ready next week as a whole.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 29 Jan 2018, 14:51 

SPB/SFX:

  • Problems with data loggers ==> no statements about the past.
  • Loop 5 upgraded
  • Alle the other Loops are not at the 100% of their potential but sufficient for the users.
  • Test on nkb mirror movement to be done.

 

XPO

  • In SASE3, 4 cameras have trigger problems. AE is working on that.
  • In SASE3, 4 cameras have accessibility problems. ITDM is working on that.

CAS SASE3 (C. Youngman):

  • Interlock for VAC, GAT and XGM loops are tested and OK
  • The rest is so far as it could go. For details refer to C. Youngman report.

ITDM:

  • Broken Linecard  replaced .
  • Update/switch for the gateway to the control network will happen in one late evening during this week. ITDM will write an entry in the logbook just before. 
Entry   closing of XTD10 shifted to Wednesday, posted by Martin Dommach on 29 Jan 2018, 10:32 

Dear all,

the closing of the XTD10 tunnel is shifted to Wednesday (January 31st.) at 2 p.m.

Best regards,

Martin

Entry   Link to "Access Request" gathering for tunnels after the shutdown, posted by Gerd Wellenreuther on 29 Jan 2018, 10:02 

Dear all,

please enter your access requests to the tunnels into the list provided by Winni Decking & Co.:

https://ttfinfo.desy.de/elog/XMLlist?file=/XFELelog/data/doc/Access-Requests&xsl=/elogbook/xsl/elog.xsl&picture=true

Can be also found through the usual XFEL-Logbook, and then clicking on "Access Request" on the left hand side.

Cheers, Gerd

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 26.1., posted by Gerd Wellenreuther on 29 Jan 2018, 09:29 

SPB/SFX:

  • Preparation for the mirror installation were ongoing as planned.
  • The Karabo and server update went smooth, but scenes were broken a bit more then anticipated so we are still testing on that part.
  • ITDM was working on DAQ update and Jola checked out the detector with the new Karabo successfully.
FXE:
  • did not attend / did not send any report

Vacuum:

  • SASE1:

    • Vacuum system ready for restart

  • SASE3:

    • loops were updated

    • final interlock test ongoing

    • GATT tests with Karabo

      • Vacuum possible

      • manual attenuation of the beam possible, no PID control

      • Controls of Ebara pump needs commissioning.

  • SASE2:

    • XTD1: under vacuum, leak test done, all pumps running

Diagnostics:
  • final checklist tour today 11h (because XTD10 closes tuesday), remove material
  • MCP: installed webcam, some trigger issue with MCP-CAM-BEAMVIEW
    • manipulator motors unstable
  • KMONO: found some wrong motion directions, urgent work ongoing today to correct this, AE support needed
  • PES: still no eplan available (laid some vacuum cables but of course unconnected)
    • consequence: further progress on PES Beckhoff system only in April
    • positive news: non-Beckhoff controls (HV, detector signals) operational ! 
  • IMAGERS: The imagers in motion loop 1 are operational for first lasing.
  • Some minor rework is planned until tunnel closure: default parameters, EPS, trigger in some cases

Laser:

  • SASE1 PP-laser commissioning: progress is according to plan.
  • SASE 2 and 3 laser safety and access control installations are in time for start of laser table installations in all laser hutches at beginning of April.

Detectors:

  • LPD is waiting for DAQ-test with new Karabo
  • DAQ-test for AGIPD is ongoing and okay so far
  • Some issues were found, but they are not considered critical for the operation

AdvancedElectronics:

  • Machine trigger is back to 10Hz, should again stay at 10Hz "forever", let's see...
  • PLCs have been updated in SASE3 tunnels, and many tests are ongoing, with little time left
  • Gas attenuator has an issue, AE is working on it, but it should not be a showstopper
  • XTD2: Some issues with the CRLs, but first local test has to be done, then remote-control test can be done using Karabo
  • MC2-based motors for synchronized movement of the mirrors are being done. Next week a test with the real nano-KB-system with fake mirrors will be done
  • Jan found some issues in the SASE3 kMono, and is working on them

ITDM:

  • Testing DAQ with new Karabo release, so far so good...
  • DAQ for LPD is being deployed
  • By the end of CW 5 the DAQ for SASE3 tunnels will be deployed
  • Meeting with the laser group to check requirements for data acquisition
  • Broken Linecard should have been replaced on the 26.1.
  • Paths to Online- & Offline-data folders have been given the same pathname
  • Update/switch for the gateway to the control network will happen in CW 5

CAS:

  • This week we have been prioritizing: SASE1, SASE3 & SPB (Karabo 2.2.1) Deployment.
  • We also have been working internally to speedUp the Karabo 2.2.2 tests and releases. This version will have, mainly, GUI improvements.
  • We also have been discussing XGM requirements and tests. We will perform more XGM-TraindID tests, but the final statement can be done only after tests again real beam.
  • FXE provided a "next steps list": Digitizer, OGT1_BIU, beam-position feedback
  • Sergey and Hamed are working and prioritizing Digitizer implementation

 

Entry   SASE1 Timing System Update, posted by Bruno Fernandes on 24 Jan 2018, 16:15 

Dear all,

the update to the SASE1 Timing system has been perform with no problems. The Timing board is now running firmware 1.24.0 and the doocs server was updated to version 7.8. I also updated the MCH firmware to version 2.19
 

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 24 Jan 2018, 14:48 

SPB/SFX:

  • Preparing D.02 for mirrors installation (next 2 weeks no access to D.02)
  • Karabo being updated - Detector being tested, seems fine so far.
  • DAQ tests foreseen for today
  • NKB movement (Loop3) should be tested to make sure that the controls work fine before interfacing the MKB with real mirrors inside.
  • AE will check the status of the CSS crate. If ready it will be mounted and tested after the MKB.

Advanced Electronics:

  • ATM for timing has to be replaced in the balcony rooms.  downtime expected to be  15 minutes. Will happen Today at 16:00

CAS:

  • Deploy SASE1 topic in the tunnel this week.Tomorrow at 13:oo CAS would like to make the switch. A.Silenzi will write an entry in the logbook to make sure everyone is on board with that.
  • Release of the version 2.2.2. being prepared. This would mainly improve the GUI performance.

XPO

  • FXE Mono local test performed and OK. To be tested through Karabo in Feb.

CAS SASE3 (C. Youngman):

  • Gas attenuator controls being completed and tested.
  • Soft MOno local test done and only small problems found
  • EPS loop in good state - interlock test tomorrow.
Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 22 Jan 2018, 13:28 

General remarks:

  • Stable beam only to be expected starting from 1.03. for SASE1 instruments commissioning
  • There is no guarantee for parasitic beam delivery to the experiments. If it happens at all it  will most probably be during the last week of Feb. This has to be agreed on the fly  with the BKR and H.S/ T.T.

SPB/SFX:

  • Preparing D.02 for mirrors installation (next week)
  • Karabo being updated

Advanced Electronics:

  • Trigger delivered by DESY should be back and stable at 10Hz. 
  • ATM for timing has to be replaced in the balcony rooms. Bruno Fernandes is trying to find a way to reduce the downtime down to 30 minutes. Will be scheduled in the next days.

ITDM:

  • 1 line card has to be replaced. Probably happens on Wednesday this week during the DAQ tests.
  • Tuesday afternoon the online storage units will me remounted with the same path of the offline ones.
  • This week a proposal for the in-house commissioning is going to be circulated.

 

    Reply   Re: Status report after dispatch meeting 13:00, posted by Bruno Fernandes on 22 Jan 2018, 15:12 

Hi everyone,

there was some miscommunication between us and DESY: only the Timing firmware and doocs server need to be updated, the RTM was already been replaced. This require update is similar to the one perform two weeks ago (see entry #449).

The time slot for this update is next Wednesday, 23rd January, between 16h and 17h. The update will affect all Timing Devices in SASE1. This operation should not take more than 10 minutes; during this time no timing signals will be generate (clocks/triggers/bunch patterns/etc.). Naturally, problems may occur during this update which will lead to increase down time.

If somebody sees a problem with the current schedule, please contact me.

 

Adriano Violante wrote:

General remarks:

  • Stable beam only to be expected starting from 1.03. for SASE1 instruments commissioning
  • There is no guarantee for parasitic beam delivery to the experiments. If it happens at all it  will most probably be during the last week of Feb. This has to be agreed on the fly  with the BKR and H.S/ T.T.

SPB/SFX:

  • Preparing D.02 for mirrors installation (next week)
  • Karabo being updated

Advanced Electronics:

  • Trigger delivered by DESY should be back and stable at 10Hz. 
  • ATM for timing has to be replaced in the balcony rooms. Bruno Fernandes is trying to find a way to reduce the downtime down to 30 minutes. Will be scheduled in the next days.

ITDM:

  • 1 line card has to be replaced. Probably happens on Wednesday this week during the DAQ tests.
  • Tuesday afternoon the online storage units will me remounted with the same path of the offline ones.
  • This week a proposal for the in-house commissioning is going to be circulated.

 

 

Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 22 Jan 2018, 10:36 

SPB/SFX:

  • 2nd AGIPD intervention will be finished today.
  • SE worked on a reliable procedure for nozzle exchange and trained the instrument scientists
  • SmarAct motors are in error, Mahadi / AE is informed. These motors are needed for user operation / commissioning.
  • loop 5 update still outstanding
  • Karabo update for loop 1-4 was done, seems to be ok. Full update is planned for beginning of next week.

FXE:

  • JJ X-rays finalized installation of the last components at FXE:
    • Diamond grating (in XTD9)
    • Spectrum analyzers
    • Timing tool
    • repositioning of the sample manipulator and working on better cabling
    • minor work on cables of FXE CRL to allow full movement along the beam direction
    • Johann spectrometer
  • FXE got the information from CAS that the Karabo update was successful and it’s ready for testing
  • FXE decided not not pursue the further commissioning of the new equipment due to the emergency power off tests
  • FXE is working on a more universal sample environment allowing faster and more reliable changes from solid to liquid experiments.

Vacuum:

SASE1:

  • vacuum system closed,
  • PLC loop update done,
  • ready for restart

SASE2:

  • XTD1 all devices in the tunnel and aligned

SASE3:

  • Soft Mono chamber closed yesterday, pumpdown, leaktest later today
  • GasAttenuator comissioning ongoing
  • Karabo scene developement

XPD:

  • SASE3 MCP detector technical commissioning:
    • HV tested OK (MPOD operational), today ADC/signal test
    • motors: rewiring done --> correct directions and limit switches
    • motors were intermediately ok, but are not stable (now there are again issues)
    • several PLC / karabo issues were sorted out, ok
  • SASE3 XGM:
    • test with Kr gas supply yesterday/today
    • test with gas plus HV
  • SASE3 PES:
    • ordered grounding works (cabling) to be done similar to what was done for the XGM
  • SASE2 XGM:
    • vacuum incident: vacuum operation of the XGM in XTD6 was unauthorized interrupted for some time, The rack had been powered down without prior information to XPD.
    • Reminder to all that rack near the XGMs shall be powered down only after informing and coordinating with XPD.

Laser:

 

  • SASE1 PP-laser commissioning and upgrade is continuing according to our plan.
  • Karabo upgrade to 2.2.1 was rather uneventful and successful.
  • Hutch readiness milestones for laser hutches in SASE 3 and 2 seem to consolidate:  15. March. If this continues to hold, we will start our Phase II installation of PP-lasers in E.04 and A.04 with laser tables at the start of April. Laser tables for the ILHs will be installed at the same time.

Detectors: Did not attend.

Advanced Electronics:

  • Replacement of the microTCA for the PES was done
  • microTCA update of the timing system was done
  • local test of the CRL can be done after the cables and the hardware have been fixed by the Vacuum group
  • All loops of FXE updated (firmware etc.)

ITDM:

  • Network ports for SASE2 in the racks have been fixed
  • DAQ in SASE1 needs fixing of hardware, foreseen for CW 4
  • Test of DAQ with new Karabo release is on its way, should be done by Wednesday 24.1.

CAS:

 

  • Karabo 2.2.1 has been deployed on FXE, LAS-LAB, LAS-PPL, and 3 SPB loops without any real problems
  • migration continues next week on SPB
  • BKR will be equiped with a 3rd Karabo Control PCs (we work with Tim already on it)

 

Entry   Event #16 back (for good) to 10Hz , posted by Bruno Fernandes on 19 Jan 2018, 16:06 

Event trigger #16 is now back to 10Hz and it will still that way.

Entry   Event #16 back to 1Hz , posted by Bruno Fernandes on 17 Jan 2018, 16:53 

Dear all,

I communicated today on the 13h meeting that the Trigger #16 was back to 10Hz; this is no longer the case, the trigger signal is back to 1Hz.

 

Entry   Rack 1.2 Timing Update, posted by Bruno Fernandes on 17 Jan 2018, 15:55 

Dear all, 

following up from the message #449, the MicroTCA Crate in rack 1.2 has been rebooted. Timing system hardware is now running firmware v1.24.0.

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 17 Jan 2018, 13:54 
SPB:
- one mfpga board was found malfunctioning and was replaced with the old one. Concerning the mc the new version can be used.
- Liquind jet test ongoing.
- Waiting for the Loop 5 to be updated by AE
- Old version of Karabo was sluggish as of yesterday.
- 2.2.1 Karabo verion being rolled out for SPB - test ongoing.

FXE:
not represented
Vacuum:
- SASE1 vacuum in the tunnels closed (CRL chamber closed).
- KB mirror chamber in D.02 (SPB optics hutch) will be opened at the beginning of February
- In SASE3 the gas supply is now decoupled from the vacuum loop
- Soft XRay mono vacuum to be closed today.
XPD:
not represented

Detectors:
not represented

AE:

-XTD 2 CRL to be tested tomorrow
- Update of loops ongoing
- Emergency off button test in FXE showed that the relative controlling PLC was not configured correctly. In addition, communication problems between TS and FXE made things more difficult. PSPO will talk to TS and decide how to proceed. In the meanwhile the test foreseen in SPB for next monday HAS BEEN CANCELLED. GWellenreuther has informed Torsten Schoen.



ITDM:
 - Meeting this week to decide whether to use or not the train builder for 
AGIPD and LPD detectors
 - in 3 racks in XTD10 some network connection added last year do not work 
properly. The responsible company solved the problem without bringing down the loops.

CAS:
- 2.2.1 Karabo was deployed in FXE experiment and tests are ongoing.

- 2.2.1. being rolled out in SPB exp and Laser

- SASE3 tunnels  tunnels will get the new Karabo version next week. SASE1 tunnels will follow (probably in the same week) 

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 15 Jan 2018, 13:56 
SPB:
- The exchange of the mc and mfpga boards has been done and some problems were found. The boards are now being debugged at CFEL.
- Sample enviroment's group is testing the liquid jet this week.
- Wait for the Loop 5 to be updated by AE

FXE:
not represented
Vacuum:
not represented
XPD:
not represented

Laser:
not represented

Detectors:
not represented

AE:

- Timing devices update done. One crate in XTD2 has a problem and cannot be operated remotely. Fixing ongoing.
- The clock, VETO and Start signals for the AGIPD could not be brought correctly from the utca in the rackroom to the patch panel in the hutch due to the excessive cable length. Workaround found using a signal replicator at the patch panel position. The problem seems to be solved.


ITDM:
 - LPD recabled with Infiniband connection. Test succesful.
 - Meeting this week to decide whether to use or not the train builder for 
AGIPD and LPD detectors
 - in 3 racks in XTD10 some network connection added last year do not work 
properly. The responsible company is comeing back next week to check the 
cabling. Interventions have to be planned accordingly since the Beckhoff 
loops are running! ==> no news.

CAS:
- not represented
Entry   Update Timing Firmware/Doocs Server, posted by Bruno Fernandes on 12 Jan 2018, 14:34 

Dear all,

with the exception of one board, all boards in SASE1, SASE3, FXE, SPB and PPL have been successfully updated. All Timing boards are now running firmware v1.24.0. The doocs-x2timer-server has also been updated in all CPUs; running version is 7.8.

The problem occur in the Timing System of rack 1.2 located at XTD2. The MCH board is not reachable via ssh/telnet/web interface; thus I am not able to power cycle the timing board, which would make the hardware load the latest version. The board is currently running (i.e. generating all the timing signals) but with an older hardware version. During the next week this problem will be tackle this problem with a quick visit to the rack.

Cheers.

Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 12 Jan 2018, 11:10 
SPB:
- AGIPD was tested with old mc board to verify that it was working fine
after the in-vacuum intervention in Dec 2017. The detector is working
and also the vacuum is ok.
- The exchange of the mc and mfpga boards is ongoing and will continue
next week (according to planning)

FXE:
- Diffraction Grating is being installed by JJ-XRay. End to end tests to 
follow.
- Karabo being updated to the 2.2.1. version.

Vacuum:
SASE1:
- CRL XTD2 closed yesterday, seems to be leak tight
- PLC VAC loop update done yesterday
SASE3:
- soft mono chamber still open, XRO is installing mirrors
- MCP connected to beamline again, pumped down yesterday
- VAC - GATT loop separation ongoing, loop restart next Monday

XPD:
SASE1:
- rebooted vacuum loop yesterday, XGM vacuum gymnastics
SASE3:
- MCP technical comm.:  motor tests, some rewiring & enabling control of HV
- Imagers: all imagers in motion Loop 1 and 2 - some small mistakes
- Photonic Science camera issue (16bit) is solved
SASE2:
- MCP transported into tunnel XTD6
- now ALL vacuum chambers of XPD are in the TUNNELS (few more for the hall)

Laser:
- the timing specification has been extended, 6 laser patterns available
for SASE1/2/3 and the laser lab. 4 others are reserver for SASE4/5. In
the next months desy will upgrade doocs servers and firmware.
- SASE1: pp-laser upgrade and remaining commissioning progress as per
plan (finish end of March). No commitments to experiments till then.
- SASE3 and 2: Plenums are being installed. Plans for laser table
installations: currently still for April.

Detectors:
- did not attend

AE:
SASE3
- Gas attenuator is in separate loop and loop running
- MOV loop 1 updated (incl. MCP related change)
- Plan to update EPS loop today
- VAC loop update planned for Monday
- MicroTCA crate for PES replaced - Timing back for this crate and also
for XGM and KMONO
General 
- Timing changes - Machine switched to 1Hz and they reset the train IDs to avoid soon issues with the machine DAQ system

ITDM:
 - LPD recabled with Infiniband connection. Test ongoing.
 - Meeting next week to decide whether to use or not the train builder for 
AGIPD and LPD detectors
 - in 3 racks in XTD10 some network connection added last year do not work 
properly. The responsible company is comeing back next week to check the 
cabling. Interventions have to be planned accordingly since the Beckhoff 
loops are running!

CAS:
- Karabo 2.2.1 has been created and its roll out for hw tests on real
field has been started
- We have started at FXE. Until now only a single problem has been found
with LPD FEM.
- Laser Laboratory has also been updated without any problem detected
until now
- Next Monday Lasers group's PPL installation will be upgraded
- Next week, SPB will be upgraded also step-by-step
- Finally, SASE1 will also be upgraded.

Entry   FXE/SPB/PPL Timing Update, posted by Bruno Fernandes on 11 Jan 2018, 15:17 

Hi everyone,

after talking with the responsabile people, here's the timetable for the Timing firmware/server update:

FXE/SPB/PPL x2timer update timetable
Machine Experiment # Devices Time
FXE-RR-SYS-UTC-1 FXE 2 12.01.2018 @ 13H00
FXE-RR-SYS-UTC-2 FXE 2 12.01.2018 @ 13H00
SPB-RR-SYS-UTC-1 SPB 2 12.01.2018 @ 08H30
SPB-RR-SYS-UTC-2 SPB 2 12.01.2018 @ 08H30
LA1-LAS-SYS-UTC-1 PPL 2 12.01.2018 @ 14H00
LA3-LAS-SYS-UTC-2 PPL 2 12.01.2018 @ 14H00

 

In the meantime, all of SASE1 and SASE3 machines have been updated (with exception of the MicroTCA in the SASE1 Balcony room) with no problems.

 

Entry   Update Timing Firmware/Doocs Server, posted by Bruno Fernandes on 11 Jan 2018, 11:04 

Dear all,

an update of the Timing boards firmware and doocs server is require. This operation should not take more than 10 minutes per device; during this time no timing signals will be generate (clocks/triggers/bunch patterns/etc.). Naturally, problems may occur during this update which will lead to increase down time.

I will perform this necessary update in the devices locates in SASE1 and SASE3 tunnels today at 11H30. If somebody sees a problem please contact me.

Concerning the devices in the Experiment Rack Rooms, I will contact a responsible person to schedule a time slot where this update can be perform. If are one of these people contact me.

Entry   MicroTCA in rack 3.4/XTD10, posted by Bruno Fernandes on 10 Jan 2018, 17:35 

The MicroTCA crate used in rack 3.4 (XTD10) has been replaced. The system is up and running. Timing information is properly distributed from this system to the MicroTCA system in rack 3.2 and XGMXTD10.

Entry   1Hz Triggers , posted by Bruno Fernandes on 10 Jan 2018, 17:20 

Hello everyone,

The main Timing System at DESY, which distributes all timing information to our systems, is right now configured to generate 1Hz trigger signals on Event #16. This is the trigger that is deliver to most detectors/cameras on our site.

DESY is testing a new Gun and wanted to use a slower trigger frequency during this evaluation.

We were not inform in advance about this reconfiguration. After a few colleagues from SPB approach us reporting this problem, we contacted DESY and got the update. We will take steps to make sure that future Timing changes done by DESY are communicated to XFEL ahead of time.

Entry   FXE Mono, posted by Dennis Goeries on 10 Jan 2018, 14:54 

Hi,

the FXE Mono's won't be available via Karabo from 15.30 onwards due to an update from CAS (karabo) and ITDM (server).

Best, Dennis

Entry   Status and plans after Readiness meeting, posted by Monica Aresté on 10 Jan 2018, 13:22 

PSPO:

- G.Wellenreuther inform that MKK is planning to test the Umschaltautomatik, this will affect XHE1, XHE3, XHPSC, XHEXP, XHVAC. Oleg Engelmann will send a mail with detailed information.

 

SPB:

- AGIPD is fully occupied again and restarted this morning as scheduled. Everything works well so far and it is expected to finish the test on time. Further test with new Microcontroller are scheduled for next week.

- Most of the loops that required modifications are updated or on going.

- Module BKF00128 will be modified this week, update of Loop 5 will folllow.

- Loop 12 is ready to be deployed, to confirm if modifications in the modules are finished and reorganization on rack UH2.12 is ready.

- It is necessary to correct an error in module BKF00220,  AE will agree with SPB  when this will be possible.

 

FXE:

- New Vacuum device in operation.

- Karabo 2.2.0 being deploy today for FXE.

 

AE:

- Replace one Micro-TC in SASE3, a cooling unit is failing and one module will be replaced by a new one today. This is providing timing for XGM and K-mono. AE will inform by the logbook before to start the replacement.

 

 

    Reply   Re: Status and plans after Readiness meeting, posted by Hugo Silva Santos on 10 Jan 2018, 14:53 

Dear Monica,

Just one small correction at "Karabo 2.2.0 being deploy today for FXE." The version is, actually, Karabo 2.2.1 that we released yesterday.

Hugo

Monica Aresté wrote:

PSPO:

- G.Wellenreuther inform that MKK is planning to test the Umschaltautomatik, this will affect XHE1, XHE3, XHPSC, XHEXP, XHVAC. Oleg Engelmann will send a mail with detailed information.

 

SPB:

- AGIPD is fully occupied again and restarted this morning as scheduled. Everything works well so far and it is expected to finish the test on time. Further test with new Microcontroller are scheduled for next week.

- Most of the loops that required modifications are updated or on going.

- Module BKF00128 will be modified this week, update of Loop 5 will folllow.

- Loop 12 is ready to be deployed, to confirm if modifications in the modules are finished and reorganization on rack UH2.12 is ready.

- It is necessary to correct an error in module BKF00220,  AE will agree with SPB  when this will be possible.

 

FXE:

- New Vacuum device in operation.

- Karabo 2.2.0 being deploy today for FXE.

 

AE:

- Replace one Micro-TC in SASE3, a cooling unit is failing and one module will be replaced by a new one today. This is providing timing for XGM and K-mono. AE will inform by the logbook before to start the replacement.

 

 

 

Entry   Shutdown of compressed air distribution in XTDs today, posted by Martin Dommach on 09 Jan 2018, 10:32 

Dear all,

we got the information from MKK, that they have to fix a leak in the main compressed air line. Therefore they will close the valves to the tunnels for approximately one hour starting today at 1 p.m.

Please do not use the compresed air system in the tunnels during that time with air driven tools or air guns, as the volume of the distribution systems acts as a buffer.

Regards,

Martin

 

Entry   Access to XTDs, posted by Gerd Wellenreuther on 09 Jan 2018, 10:14 

Dear all,

according to H. Sinn the closing of the XTDs 2, 4 and 10 will be delayed until the 30th of January.

Cheers, Gerd

Entry   Status and plans after Readiness Meeting, posted by Monica Aresté on 08 Jan 2018, 13:47 

PSPO:

- G. Wellenreuther inform that DESY is commissioning a new gun in the injector that could take longer than expected. Harald Sinn is in a meeting today to disccuss this issue, any change in the scheduled will be reported.

 

SPB:

- Lost motor positions in the tunnel, CRL in defined state. Good state in general no major problems expected.

- Detector was clabled again.

- Loop updates still pending, SPB request to have loops ready during this week.

 

FXE: No one attended

 

Vacuum:

- SASE1:

  • Some works in CRL for XTD1.
  • Working in FXE grating chamber, necessary to update Vacuum loop.

- SASE3:

  • M1 and M2 mirrors were installed before X-mas. Mirrors installation in K-mono to be finished next week.
  • Created new loop this affects Vacuum loop, update necessary.
  • XGM loop need to be updated.
  • Motion loop 1 is working, some works in MCP motors on going.

 

Diagnostics:

- Technical commissioning of MCP on going together with the Russian collegues.

- MCP SASE2 will be transported to XTD6 on Wednesday afternoon.

 

AE:

- Working to implement redundancy into FXE loops.

- To agree a date with FXE to work in the grating chamber at the end of XTD10.

- Motion loop for SASE1 will be interrupted this afternoon at 14:00 to add some terminals for mirror 2.

 

Software:

- Deployment of Karabo 2.2.0 will start this Wednesday in FXE.

- Next dates for Karabo deployment are: 15th January for the Tunnels,  22nd January for SPB.

 

TS:

- Torsten Schoen inform that it is necessary to carry out an 'Emergency off button' test during the Shutdown.

- SPB agreed to perfom the test the 22nd January in the morning.

- For FXE the proposal is to perfom the test the 17th January, to be confirmed with AE and FXE.

 

 

 

 

 

 

 

 

 

Entry   Reminder Readiness meeting today at 13:00, posted by Monica Aresté on 08 Jan 2018, 09:50 

Dear all,

This is a reminder to inform you that Readiness meeting will resume today at 13:00.

Best regards and Happy New Year !!

 

Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 18 Dec 2017, 10:48 

PSPO:

  • M. Areste presented a report about the progress so far achieved in the shutdown (see Indico for details).
  • Most tasks are ongoing, on schedule.
  • Few still have to be scheduled, mostly because support groups wait for feedback.
  • C. Youngman does detailed coordination of SASE3tasks.Will organize meeting on Tuesday 9:30 for SASE3 tunnel only
  • We will review the progress again in Mid-January!

 

SPB (M. Sikorski):

  • AGIPD was tested.
  • Roll back to crystallography configuration is ongoing.

 

FXE: No one attended.

 

Vacuum (M. Dommach): 

  • 1st mirror M1 in SASE3 installed, chamber closed, pumped down & leak tested
  • Preparations for 2nd mirror in SASE3 installation ongoing, to be installed next week.
  • MCP taken out of SASE3, put in parking position and pumped down again.
  • Grating chamber from FXE was installed by JJ X-ray, is to be pumped in CW 51.
  • SASE2 XS2 beam pipe behind shutter and lead wall installed, ready for TÜV inspection next week.

 

Diagnostics (A. Koch):

  • XGM in XTD1 is almost cabled, more cabling was done in XTD10.
  • Gas supply system in XTD1+6 was worked on.
  • Photonics Science camera was tested.
  • Trouble with the motion loop in XTD2 and XTD10, reported to AE.

 

AE (P. Gessler ):

  • MCP motion and k-monochromator were tested.
  • Motion loop was split in SASE1 tunnel.
  • Many tests, lots of work in progress, need to act quick as time is short.
  • T. Wilksen (DESY) is going to update the timing hardware è devices would have to switch to local timing, and switch back later to be operable.

 

Laser (M. Lederer):

  • Further commissioning of the PP-laser was started.
  • Upgraded Karabo and PLC firmwares. Works are on schedule.
  • Measurements on the dependence of humidity are ongoing.
  • DESY is working on the timing system, laser synchronization will be down until the 21.1.18.
  • PP-laser pattern selection with machine timing:DESY is now pushing for the originally planned implementation. DESY will have to do some software development in this context.

 

Detectors (J. )

  • Tested the AGIPD @ SPB, but 1 board was not working. Detector consortium could not provide a replacement board, so only half of the detector was tested before SPB/SFX had to close the detector vessel again.
  • LPD was tested with train builder, but only tests using 2 memory cells could be conducted (2 images per train), so train builder was not tested with all memory cells.
  • More tests with full load (i.e up to 510 images per train) still have to be performed.
  • Test with DSSC will take place in HERA South in CW 51.

 

ITDM (K. Wrona)

  • Monday til Wednesday there will be no DAQ due to extension of the Infini-band bandwidth, upgrades, firmware updates, recabling etc.
  • DAQ up again on Thursday

 

Software (S. Brockhauser)

  • CAS-People are currently working only in SASE3. In the future, they can either work on SASE3 or SASE2, but not both!
  • Slides with Project-plan provided by Hugo Santos (see Indico)
  • Release of Karabo 2.2.0 on the 18.12. (in the meantime shifted to the 20.12.)
  • Testing by ITDM and consecutive deployment in tunnels and at the instruments takes until 22nd of January
  • Karabo 2.2.1 to be expected mid of January
  • Further decisions will be taken mid of January
Entry   FXE Collimating CRL, posted by Lewis Batchelor on 14 Dec 2017, 09:12 

The LENS_3X limit switch (switched when driving towards the chamber center) is broken and must be replaced, hence further work is required on the next JJ visit 9/10 Jan (TBC)

The in vacuum components also need further work during the above visit. The lens that lost alignment during commissioning was also found to be more severley damaged than anticipated - the B4C guard is cracked and this deposited some fragments under the lens. All lens cassettes will be exchanged, rebuilt and realigned in Jan.

The patch panel has been removed for rework (to switch motor direction)

The Be lenses seem to be in exactly the same condition as 'new'

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 13 Dec 2017, 16:28 

General

  • Meeting on Friday will take place at 1300 due to overlap with XDAC
  • M. Areste shall ask for updates on task list on Thursday

Instruments

  • SPB
    • Work on AGIPD is ahead of schedule. Closing of detector should happen at the beginning of next week
    • Additional installations for roughing pump system is going on and will probably finish this year

Tunnels

  • Diagnostics group currently working in the Southern tunnels, cabling components and aligning imagers
  • Colleagues from Russia are coming 3 - 20 Jan to work on MCP in SASE3
  • KMono local tests in SASE3 should also happen in early Jan
  • Diagnostics requests scenes for XGM in XTD1

AE

  • Vacuum loop in SASE3 will be modified. Some components shall be moved to a separate loop, e. g. Soft Mono
  • SPB tunnel loop will be re-deployed to include the attenuator
  • The motion loop in SASE1 will also be split to allow more rapid updates for newly integrated components
  • Z-motion crate for detector in SPB will be done until next week or early next year

CAS

  • Currently working with AE and ITDM on refining release schedule for KARABO
  • Testing the version for release next week. This will then first be used by ITDM and is needed for the firmware upgrade of AGIPD
  • Work is going on on the XGM train ID problem
  • FXE will be moved to a separate topic (broker) to disentangle some dependencies at least temporarily
  • FEL imager performance problem was investigated. This runs on a server that is very busy and should be moved to a different server
Entry   Fire alarms in tunnels and shafts on 13 Dec 9 - 11, posted by Tobias Haas on 08 Dec 2017, 15:49 

FYI

Author: F. Saretzki

English version below

Ankündigung:

Aufgrund von Sachverständigenprüfungen wird es am folgenden Termin zu Auslösungen des Evakuierungsalarms kommen:

Gebäude: XHE2/XS2, XHE4/XS4, XSDU1, XTD1, 3, 5, 6, 7 und 8
Datum: 13.12.2017 ca. 09:00 Uhr – 11:00 Uhr


Sie brauchen bei ertönen der Sirene in diesen Zeiträumen das Gebäude nicht verlassen.

============================================================================
Announcement:

Due to expert testing there will be an evacuation alarm on the following date:

Building: XHE2/XS2, XHE4/XS4, XSDU1, XTD1, 3, 5, 6, 7 and 8
Date: 13th of December 2017 between 09:00 a.m. and 11:00 a.m.


You don’t need to exit the building while the alarm occurs.

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 08 Dec 2017, 11:35 

General

  • Starting from next week shutdown activities will be tracked using M. Aresté's list
  • Dispatch meeting on Monday and Wednesday at 13:00
  • Next Friday Readiness meeting also at 13:00 because of conflict with XDAC

Instruments

  • FXE:
    • Currently focussing of implementing all default parameters into the next firmware release
  • SPB:
    • Major detector work with AGIPD disassembly started

Tunnels

  • Currently testing firmware and software in SASE3
  • Installation of first mirror starts next week. Mirror installation takes about 1 wk/mirror
  • CRL in XTD2 will be vented to align internal mask and fix stuck arm
  • Drilling takes place at the end of XTD9 for the installation of the FXE diamond grating
  • Mirror cooling will not be installed this shutdown. It is not needed for the planned bunch rates and might introduce unwanted effects/vibrations
  • Activities of Diagnostics:
    • Photonics Science camera in SASE1 exchange.
    • Tests are being carried out in SASE3 together with J. Tolkiehn
    • Cabling is going on in XTD1 on the XGM
    • There is a noise problem on the Gotthardt detector in the HIREX. Need support from AE to find the origin

AE

  • Motion loop in SASE3 will be split into mov1 and mov2. This will allow to sort components into more and less stable sets and keep one of the loops up most of the time

Laser

  • Laser activities had to start late due to problems with AC and laser interlock (delays of 6 and 5 months respectively)
  • Availability of trigger pattern from the machine was also a problem
  • Specs could just be reached for the Nov user period
  • Eventually the PP laser was not used for any of the experiments
  • Work on the laser is far from finished and will require 3 more months to come to full funtionality
  • Currently, the Karabo version is being upgraded and the most up-to-date PLC firmware is being installed
  • These updates had intentionally been delayed until the end of the user period.

Detector

  • Detector group not present at the meeting
  • Information from SPB: major work is ongoing on AGIPD

AE

  • Train builder is being tested as it was not used so far. This required re-cabling
  • PLC motor loops are also being split in SASE1
  • Many activities in SPB
    • Remaining modifications of modules have started
    • Export of input for firmware generation for loop 8 has been provided by EETF
  • Waiting for go in FXE
    • Need to work on the interface for the EPS system
  • No tasks currently from laser group
  • New information available on SmarACT stages: The observed problems arise from a cable problem and can be solve by configuration
  • The problems with movers in the sample chamber in SPB (non-functioning encoders) arise from cable cross talk at the vacuum feed through. This require hardware re-design
  • In SASE2 there are tests coming up together with the diagnostics group

ITDM

  • Train builder tests are scheduled next week
  • Recabling of Infiniband network happens on 18/19/20 Dec. No DAQ and controls available on these days
  • A summary of DAQ statistics was shown (see slides on INDICO)

CAS

  • Release of KARABO 2.2 on 18 Dec
  • Freeze of functionality on 21 Jan
  • Discussion reveals that a discussion on specific deployment dates and needs of different groups is urgently needed (Instruments, Tunnels, DAQ)
Entry   Rack extinguishing system in SASE2, posted by Tobias Haas on 07 Dec 2017, 09:04 

Please note following info from DESY:

 

Author: F. Saretzki



Ab sofort werden die Rack-Löschanlagen in den südlichen Tunneln in Betrieb genommen. Die Anlagen bleiben danach scharf.



 

Entry   SASE1 MOV, posted by NEREA JARDON on 06 Dec 2017, 17:17 

The Motion loop in SASE1 is totally operated again.

Entry   Status report after dispatch meeting 13:00, posted by Adriano Violante on 06 Dec 2017, 13:46 

General:

  • Shutdown started.

Instruments

  • SPB:
    • AGIPD prepared for exchange modules intervention
    • AE is in contact with SPB for crates issues fixing
    • The schedule for next year, especially when the experiment has to be ready before the users run has to be known as soon as possible.
  • FXE
    • Starting loops update in the next days. Reason for the small delay is that FXE is checking all the default parameters to be able to restore them after the update.
    • In order to solve some DAQ issues, FXE requested to have their own topic. AE agrees, ITDM agrees, CAS is trying to find out how to do it and to do it before the next users run. Technical details have to be discussed offline with FXE.

ITDM

  • in KW 51 (18-22 Dec.) the DAQ and online cluster will not be available due to recabling works in the balcony rooms.
  • Update of the servers in the experiments has to be done. ITDM requested to know from CAS when the major update of Karabo is taking place to coordinate the effort and minimize the downtime. CAS will present a schedule concerning Karabo this Friday.
  • 700 Tb of data are stored on the online cluster. It has to be communicated by the experiments what can be moved from there, since there is almost no space left.

Diagnostics

  • Implementation of Gotthard detector in Karabo is still a problem. S.Hauf will invite the main groups involved for a meeting to find a solution.
  • The data correlation with time stamps when using the Karabo DAQ has to be done carefully and contacting WP74 since there are still issues present. 

AE

  • Activities on the Hirex in SASE1 will need the MOV loop to be brought down in the afternoon. An entry in the ELOG will be written.
  • SPB loop 8 prepared. 
  • Full list of new crates belonging to the motion loop in SASE3 tunnels has to be delivered to AE
  • Full list of new crates belonging to the IPS loop in SASE3 tunnels has to be delivered to AE in order to be able to close the loop.
  • Technosoft controller issues in SASE3 will be attacked once the SASE1 activities will allow it.

VAC

  • VAC testing ongoing.
  • 2 mirrors will be installed before Christmas
  • Motion crates for the motion lopps and test of the VAC interlock will happen this week.
Entry   Status after 0930 meeting, posted by Tobias Haas on 04 Dec 2017, 10:56 

General:

  • User operation with good beam conditions over the weekend
  • One interlock trip in the FXE branch in XTD9. Restored by CAS
  • Shutdown starts tomorrow at 08:00.
  • Next dispatch meeting takes place Wednesday at 13:00. A reminder will be sent.

Instruments

  • SPB:
    • Started with the actual sample during the night shift
    • Some DAQ issues
    • 108TB data was recorded
    • Problems appear to occur between 01:00 and 02:00  and between 13:00 and 14:00 
  • FXE
    • Running is ok. 
    • Temporal and spatial overlap with optical laser established
    • Currently taking pump-probe data
    • People on shift were uncertain about how to recover from interlock trip
      • Statement from Vacuum: Pumps can restarted/valves open if the respective button in KARABO can be clicked

CAS:

  • Delay between data taking and "online" analysis in the "Hummingbird" software is about 0.3s

ITDM

  • On Friday, there was a global network outage affecting the Office Network on the DESY site.
  • The transponder system in the experiment hall was down
  • SRP organised a guard at the hall entrance so that the hall had not to be evacuated
  • The control network (XDAC) was not affected
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 01 Dec 2017, 11:42 

General:

  • User Operation ongoing until Tuesday 5 Dec 8 AM
  • CAS shall present a release plan for KARABO 2.2 next week
  • Dispatch meetings shall move to a Mo/Wed 13:00 schedule starting next Wedneday 6 Dec

Instruments

  • FXE:
    • Scantool was successfully used to establish overlap with laser beam (Tangerine) 
    • Some problems with slow DAQ in particular also for tunnel components
    • Comment from ITDM: There are known issues with the slow data acquisiton. A new version exists that was intentionally not deployed before the end of UOP
  • SPB
    • Just finished first shift of laser user experiment
    • No big problems
    • All goals in the optimistic schedule were achieved

Tunnels

  • Currently preparing for the shutdown
  • Sticking condition of mirror bender could be reproduced in the lab
  • WP74 just installed the last missing pieces in XTD1

Laser

  • Running
  • temporal and spatial overlap with beam is achieved
  • But now instruments do not intend to use the PP laser for the last experiment

Detectors

  • Both detectors are working
  • The DAQ for slow data is crashing occasionally
  • Gotthard is fully operational but there problems getting the data out. Help from PSI is needed

AE

  • No problems

ITDM

  • No problems

CAS

  • CAS-XPD Running:
    • We will finish next Monday
    • We have been addressing issues related to MCP, Karabo-DAQ, Cameras, and K-Mono
    • Deploy K-mono today
    • Review DAQ Groups in Karabo: Cyril (interface to ITDM), Liubov, Koch
    • Gotthard we have to address in a separate and more systematic discussion: trigger, operation, calibration...
  • XGM memleak - we already have a fix to get it stable but have to check when we will be able to upgrade (only device).
  • Internal discussion about CAS/Karabo priorities for the winter shutdown
Entry   Status after 9.30 dispatch meeting, posted by Adriano Violante on 29 Nov 2017, 09:56 

General

  • Preparation for the user's run starting tomorrow (until 7:00 Tuesday morning)

 

Instruments

  • FXE:
    • On Monday night the DAQ seemed to be slow. This problem was caused by a misconfiguration in the DAQ which could be solved by ITDM once they were informed. In general both the Configuration understanding by the users and the communication with ITDM has to improve.
    • The Gotthard detector could not be used. The Greateyes detector is being used now and works properly.
    • PP laser is now synchronized but not commissioned yet. This is going on now (crucial point is the pulse width measure). It is not yet clear whether the PP laser will be used in the next users run. 
  • SPB
    • AGIPD was moved 5 m downstream for the next experiments. Vacuum is OK. Alignment checked with the ALAS, will be checked with beam probably today evening.
    • A change in the DAQ configuration has to be (is being) done today (CAS/ITDM)

 

ITDM

  • Upgrade switches today at 9:00 will be checked if there were problems right after this meeting.

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 24 Nov 2017, 13:15 

General

  • User operation ongoing in SPB/SFX and FXE

 

Instruments

  • FXE:
    • User operation started during the night
    • Some concerns over running LPD as the sample chamber is from diamond and direct reflections could cause damage
    • Generally instrument worked very well
    • Synchronization with PP laser is now in a state where it can be tested
  • SPB
    • Many data taken for detector calibration
    • Severe issues with KARABO
      • Response is very slow
      • Major crash this morning
      • Detector controls complex and instable
    • A failure of AGIPD related to FPGA not understood
    • Strange interlock issue: EPS interlocks appeared disabled

Tunnels

  • L. Samoylova spent many hours on Wednesday to set up the DAQ in the tunnel
  • With the help of many support people she managed to get the system to work
  • The system is instable and also seems to record many more parameters than are needed
  • Use of the system is very clumsy
  • Comment from ITDM (L. Maia): The data sources were specified by the users. It is acknowledged that the system needs a lot more work
  • Diagnostics is working with CAS in a squad to work down a list of open redmine tickets
  • The DOOCS - KARABO bridge is now working. The FEL imager is routinely available in DOOCS to the BKR crew
  • DESY set up a statistics server to help collect data about beam pointing instabilities

Laser

  • Local pattern generation synchronized to machine timing is working
  • Overlap finding together with FXE was done but has to be tested under real condition next week
  • A few suddent shutoffs of the front end occured. The origin might be understood
  • There are large timing drifts in the ADCs that are currently not understood (up to ms)

ITDM

  • Next Wednesday there will be a 1h shutdown of the load balancer in the DESY RZ. This should affect mostly the web services
  • It should be noted that the DAQ ran quite stably in SPB and FXE. More than 20 runs were collected in each case without a restart

CAS

  • Two hot fixes are out (2.1.18.4/5). These address  very specific issues
  • A major new release (2.2) is planned for the winter shutdown. This will be mandatory
  • Comment from instrument: It must happen early so that wrinkles can be ironed out!)
Entry   Status and Plans after 0930 meeting, posted by Tobias Haas on 22 Nov 2017, 10:57 

General

  • User experiments resume tomorrow morning
  • Beam should be coming back late this morning or early this afternoon
  • After the Operation Coordinaton Meeting H. Sinn, L. Samoylova and the instruments will align the mirrors
  • Beam to the instruments should be available directly after this

Instruments

  • SPB:
    • The last night with beam on Monday was used to take flat field calibrations with AGIPD
    • The timing for overlap with the optical laser was adjusted
    • 5 out of 6 SmarACT rotational stages are now operations. Some problems remain and AE is talking to the manufacturer
  • FXE
    • Request for use of the beam after 9 PM
    • Can be given to SPB starting at 5 AM tomorrow for final setup 

Detectors

  • Connection to the ONDA system was set up for the detectors
  • Significant latency develops quickly an saturates at approximately 2 mins

ITDM

  • Simultaneous use of the DAQ system by both instruments should be done carefullly

AE

  • no further comment

CAS

  • no further comment
Entry   Status after 0930 meeting, posted by Tobias Haas on 20 Nov 2017, 10:21 

General

  • Intensity and availability of beam was good over the weekend
  • Large drifts and jitter were observed that are significantly higher than previously
  • Beam has two horizontal lobes as if it is too large for the mirrors

Instruments

  • SPB:
    • Many tasks were achieved during the weekend, e. g. instrument alignment, detector calibration
    • Issue with encoders whose cables are close to motor cables persists. These encoders are being disabled
    • Rotational SmarACT stages still do not work and are needed for this week's user experiment
  • FXE
    • At shift start on Saturday after reloading beam parameters there was no beam in the hutch.
    • Beam had to be brought back by hand. This was a large effort
    • This situation did not repeat on Sunday
    • LPD detector had problems: Only one super module correctly recorded data. Comment from S. Hauf: FXE should have called the detector expert
    • PP laser synchronisation does not work properly yet: Increments when adjusting timing are too coarse. Scan range is limited to 18ns

Detector

  • Detector group was not informed about the LPD issues in FXE. 
  • AGIPD calibrations were successfully taken on Sunday

ITDM

  • Still work is needed for slow data DAQ
  • DAQ behaves differently in SPB and FXE. In FXE it appears overloaded and in SPB it works fine
  • Comment from CAS: 
    • Many changes were made in the KARABO framework to allow asynchronous operation
    • These changes have to be also pulled through to DAQ. This will only be done during the winter shutdown
    • Until then, DAQ is very vulnerable to any delay in the system

CAS

  • No further comments

AE

  • Currently working on problems with rotational stages in SPB

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 17 Nov 2017, 17:14 

General

  • Beam is back with good intensity (up to 1 mJ) 
  • Next user period starts on  23 Nov
  • Time between now and then should be used to optimize FEL, beam lines and Instruments

Instruments

  • FXE:
    • Measurements of pulse intensity were done using an XGM from DESY in the hutch
    • A  pulse intensity of ca 40 uJ was found. This is in rough agreement with the expectations
    • Spectrometer was aligned
    • GreatEyes and Gotthardt detectors are working fine
    • LPD still to be checked
  • SPB:
    • Using beam to do alignment
    • Not such a good focus (too big)
    • Plans are to continue with instrument commissioning today and Saturday
    • Work is currently being done by Mahadi on the SmarACT rotary stages
    • FXE points out that most likely SPB operated with the FXE CRLs inserted into the beam
    • Note: The standard "switching script" from Harald should be used to make sure parameters and devices are properly adjusted when beam is switched from one instrument to the other
    • Detector calibration on Sunday

Tunnels

  • Last Friday there was a Bender failure on mirror M2
  • The mirror was removed from the tunnel during the weekend and the SASE2 spare was inserted 
  • In the process one Beckhoff controller was found broken
  • In the removal process a further problem was caused in one of the Beckhoff loops
  • This problem could be fixed from outside the tunnel 
  • After this 20h were spent to redo Beam-Based Alignment in 7 iterations
  • The new orbit deviates from the old by up to 80 um.
  • After using the new orbit, the FEL lased quickly with good intensity
  • The replaced mirror M2 could be re-aligned 
  • On Thursday beam was available to FXE
  • Remark from J. Grünert: Instruments should make sure that most up-to-date DOOCS panel is loaded to see proper XGM info
  • Update of DAQ caused DAQ in tunnels to be broken. This is now fixed according to K. Wrona
  • HIREX commissiong is going in parallel 

Detectors

  • AGIPD:
    • Before the bender failure a few X-Rays could be taken on AGIPD
    • It looks like 30 X-Ray pulse can be taken now
    • Additional flat field calibration is needed now
    • On Sunday a full shift is foreseen for commissioning with beam
  • LPD:
    • One quadrant was disassembled to find the cooling leak.
    • Leak now appears to be fixed
    • No sign of dead spots on detector

Laser

  • We are operating in shifts:  early / late, although experiments have been cancelled, performing shift change and other excercises for commissioning.
  • Operating the laser with machine timing was so far hampered by the fact that the transmitted laser patterns from the machine were limited to the actual number of x-ray pulses, i. e. mostly non-deterministic 1 or 0. Optical alignment and characterization is not possible under those conditions. Therefore, on the weekend we have switched to local timing to give guys some power.
  • Following this experience, we have decided to attempt local generation of laser patterns under machine timing in order to be independent of the machine and not have to switch back and forth between local and machine timing. This has been implemented and is under test today and over night. We still observe spurious long term drifts, which are under investigation.  However, if finally successful, this can only be a make shift solution for the coming weeks. Mid to long term we need proper implementation by DESY, allowing pattern changes on short notice and independent of the machine. This is in preparation (time line ca. mid 2018).
  • Currently, beams are sent to FXE and SPB with 30 pulses each, 800nm broadband, should be compressible to 15fs. This is under machine timing but with locally generated patterns.
  • There are other curiosities concerning machine timing, which are related to the increased T0 arrival time jitter compared with our local timing. Debugging is ongoing. We are also testing various features under above conditions (machine timing, local pattern):  phase shifter, trigger shifter, shift change. Time line: depending on outcome, daily updates will be provided.

AE

  • When the breakdown of the interlock occured in conjunction with the broken Beckhoff terminal it became obvious that crucial emergency phone numbers are not available
  • Better emergency procedures are needed
  • The special EPS operation mentioned to align the mirrors should be written down so that it can be implemented an no override of the interlock system is needed
  • The list of shutdown activities compiled by PSPO contains a lot of work for AE. This is now being discussed. 

ITDM

  • Some problems occured this week with DAQ of slow data. This should have been fixed yesterday

CAS

  • Doing 24/7 OCD support 
  • During switch between instrument CAS comes in to provide support
  • The cancellation of user operation last weekend was not properly communicated so that people came in unnecessarily
  • Next week additional work for WP74 is being done
Entry   Status after 0930 meeting, posted by Tobias Haas on 15 Nov 2017, 11:51 

Instruments

  • SPB:
    • Waiting for beam to come in a usable condition (500 uJ and pointing within aperture of optical elements)
  • FXE
    • Similar

AE

  • There was an interrupt of the vacuum loop in XTD2 due to a faulty pump controller. This was fixed by ZZ
  • Rotational SmarACT stage and slits in the sample chamber for SPB are being worked on

CAS

  • Due to change of beam schedule, now working on implementing more devices in DOOCS-KARABO for Jan Grünert

ITDM

  • Will upgrade DAQ software today. Note: Still based on KARABO 2.1.16
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 14 Nov 2017, 11:05 

Dear all,

I received updates from DESY (M. Hüning) about how the access to the southern tunnels is being restricted in the next months, due to interlock tests etc., and included it in the TAS. Please check, if you have work to be done in these tunnels:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status after 9.30 dispatch meeting, posted by Adriano Violante on 13 Nov 2017, 09:45 

General

  • No user operation.
  • During the week end the accelerator was not able to deliver reliable and stable beam for the user operation.
  • The M2 mirror bender stopped working on Saturday morning and had to be replaced. The mirror and blender were replaced as a whole durig the week end. Normally it would have taker weeks but a "spare" system was already set up for SASE2 and could be used on a short notice. Pumping of the M2 section is ongoing and leak test be performed today.
  • The non working M2 does not show apparent problems so far, and the reason why was not working is not clear.
  • Some sections of the LINAC were warmed up due to some maintenance required for the cold compressors.
  • LINAC is being cooled down and ready for operation today afternoon.
  • The technical support groups were not informed about the problems until saturday afternoon. The communication channels in these cases have to be improved.

Instruments

  • SPB and FXE:
    • The goal is to be able to strat the secondo users run on Thursday (Day FXE, Night SPB).

Tunnels

  • XTD2,9 Ready to take beam in the afternoon (if no leak in M2 is discovered).

ITDM

  • A small bug was found in the DAQ that affects only slow devices  with certain train ids
  • It is proposed to fix this during the next break. Decide on Wednesday

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 10 Nov 2017, 11:46 

General

  • User operation is delayed by 48h due to rocky startup of FEL.
  • FEL still has not reached acceptable levels of stability and power

Instruments

  • SPB:
    • Instrument was brought back to a somewhat running state
    • There are still problems with motors in the sample chamber
    • Alignment with beam is ongoing at this time
  • FXE
    • New scan tool was tested
    • Currently working on user-specific alignment tasks
    • Laser was routed to the sample position
    • The beam is still drifting around

Tunnels

  • FEL had trouble to find lasing
  • There was a controled access on Wednesday to fix various problems. However, further problems appeared
  • It was decided to roll back the changes made for a new injector laser, but this did not improve the situation
  • At some point 400 uJ were reached and lost again
  • There are many problems with the undulator system
    • Incorrect values in lookup tables
    • Difficult operation of the entire system
  • FXE should be able to start up tonight
  • SPB would follow Saturday morning since time is needed for alignment during the day today
  • Shifts for photon diagnostics were largely cancelled due to FEL problems
  • KMONO gave some interesting results pointing to the problems in the undulator system
  • Next week FEL Imager and KMONO will be installed in SASE2

Laser

  • Both SASE1 instruments have laser beam with local timing. 
  • Tests with machine timing start today at lunchtime

Detectors

  • AGIPD is in best possible state. 
  • Firmware and DAQ were upgraded
  • Some commissioning time with beam is needed today
  • LPD had a cooling leak  and a power problem last night
  • At 6 pm yesterday, this was still not fixed

AE

  • Continuing small activities for user operation

ITDM

  • A small bug was found in the DAQ that affects only slow devices  with certain train ids
  • It is proposed to fix this during the next break. Decide on this Monday

CAS

  • Dedicated squads for the setups of SPB/FXE, DOOCS integration, Scan Tool closed now
  • Tools delivered but with significantly reduced scope
  • All necessary things for DOOCS Karabo integration were delivered. Now waiting for DESY
Entry   Status after 0930 meeting, posted by Tobias Haas on 09 Nov 2017, 13:21 

General

  • There is currently no beam less than 24h before user operation is supposed to start in SPB
  • The affects everybody (Instruments, Detector, Laser 
Entry   Status after 0930 meeting, posted by Tobias Haas on 06 Nov 2017, 14:13 

General

  • Recomissioning of the FEL has been bumpy and up to this point only very weak lasing could be achieved. 
  • So far SPB had only little beam and FXE had no beam at all. Both instruments state that the commissioning time for the up coming user run is insufficient

Instruments

  • FXE:
    • First SW and DAQ stress test on Friday went well.
    • Some problems appeared with the slow data that should be fixed by now
    • K. Wrona states that these problem originated from missing permissions due to change of userid
  • SPB 
    • Entire instruments needed re-alignment with beam since the CSS was moved during the shutdown
    • Very low intensity and not very stable beams were available on the Weekend. The beam could not be properly focussed
    • The bender for M2 cannot reach the flat condition. Is this the temperature problem again?
    • One pump was overheating
    • AGIPD tests with new bunch patterns started this morning
    • Significantly more time needed before user operation
    • There were some problems with the interlock system that trigger beam aborts

Tunnel

  • Commissioning program was very limited in the last few days
  • KMONO got some first interesting results
    • Rings and Kicks could be seen
    • Some wrong undulator settings were identified

Detectors

  • Firmware update was done to record all 30 bunches. However this still has problems
  • Need beam for calibrations
  • The planned update by ITDM of the DAQ was not yet done

Advanced Electronics

  • The mentioned interlock issues in SPB require an update to loop 7
  • In loop 4 need to reset the "all valves open" signal by hand if it trips
  • The SPB Master loop needs updating both for MPS and timing

Software

  • Tests of the scantool took place with hardware. These tests continue today
  • A new data model is being worked on for the scan tool but this is not available yet
  • SPB states that at this point they will not make use of the scan tool as they first have to consolidate the instrument
  • FXE is involved in the CAS tests

ITDM

  • As mentioned before the DAQ version is still old and needs an update. This contains many improvements
  • IBM discovered a bug in GPFS and published a patch. The bug could lead to data corruption
  • Decision: DAQ update and GPFS patch will be installed today in the morning.

 

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 06 Nov 2017, 13:58 

Dear all,

I updated the TAS to include the upcoming user runs up to and including the winter shutdown. As you can see, there will only be access to the XTDs in cases of urgency. In these cases, please contact Martin Dommach, Harald Sinn or Thomas Tschentscher.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

Entry   WP74 OCD plan until next shutdown, posted by Jan Grünert on 04 Nov 2017, 03:28 WP74_OCD_Plan.xlsx
 
Entry   WP74 OCD contacts for this weekend, posted by Jan Grünert on 04 Nov 2017, 03:26 

4.11. from 08:00 until 5.11. 08:00 - Jan Gruenert by email (work mobile defect)

5.11. from 08:00 until 6.11. 08:00 - Naresh Kujala 9-6840 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 03 Nov 2017, 15:06 

General

  • The rack layouts and rack placement were finalized during the PRR in August. The result is the basis of the network planning. The network is currently being installed and will most likely be finished by the end of the year. Changes to the layout that affect the network planning are no longer possible. 
  • The TC/XHEXP1 meetings shall be combined into one bi-weekly meeting starting on 9 Nov. A separater new invitation shall be sent

Instruments

  • SPB
    • Currently preparing for the next user period
    • A lot of work still needs to be done for bringing the laser to the interaction point. This mostly concerns the beam pipe
    • Apparently there was an interlock problem related to SPB components in XTD9. SPB components were taken out of the EPS loop without SPB being informed
      • Comment from T. Freyermuth: The condition of SPB devices was preventing beam operation and noone of SPB could be reached
  • FXE
    • A lot of progess was made together with CAS
    • This afternoon a DAQ stress test with several detectors is planned
    • The encoders on the CRL lens stack were disabled as this complicates the operation at the moment

Tunnels

  • XTD9 was closed yesterday. Beam could arrive this weekend
  • About one shift worth of work remains in XTD10 before readiness for lasing
  • KMONO measurements took place on Wed/Thurs from 3PM - 3AM
  • Some DAQ and KARABO issues surfaced
  • But it was possible to record donut radiation patterns
  • Now commissioning of HIREX is being prepared
  • XGM requires some minor re-commissioning

Laser

  • Beam is in the ILHs. 
  • Still problems dealing with the capricious AC system
  • The promised specs of the laser beam are met
  • Synchronization is still to local timing. Synchronization to the machine timing only comes next week and no time remains for testing before users

Detectors

  • LPD:
    • 15/16 super modules are operational
    • This week calibration data from charge injection were taken
    • The detector is ready for users
  • AGIPD:
    • Detector is fully working again after a big rearrangement of cables
    • It was found the the clocking-control cable is too long and needs to be re-routed during the winter shutdown. The detector will be fine for the next users
    • Work is ongoing on the firmware in order to allow 30 frames/train rather than only 15

Electronics

  • SPB:
    • Updated the tunnel loop for SPB
    • Loop 12 is up-to-date
    • Loop4: The mirror mounts were tested locally
    • The is no feed back on interlock behaviour in loop 5. If there should be problems individual conditions can be disabled
    • For loop 7 zoom and focus and mirror mounts to be tested
    • Same applies to loop 2
  • XTD9:
    • want to update EPS loop to include removed SPB components today
    • Vacuum loop to be updated next week
  • XTD10
    • Some ion pumps show an error condition in KARABO. J. Tolkiehn is investigating

ITDM

  • User handling for log books has changed. Please consult the help log book for details or consult J. Szuba
  • The meta data catalogue was updated so that instruments can now annotate with their own credentials
  • Folders for the next two user proposals are created, also in the online environment
  • A new version of the DAQ software needs to be deployed in order to fix a bug in slow data daq

CAS

  • A number of issues need to be resolved with Diagnostics as already mentioned earlier
  • The Gotthardt Detector is now working in FXE
  • The promised reduced scope for the scantool has been achieved. It will be made available to the users asap, most likely today
Entry   Automatic logbooks for beamtimes, posted by Janusz Szuba on 02 Nov 2017, 10:09 

Hi

Logbooks for the first two upcoming proposals in FXE and SPB instruments have been set up and all missing users in the past 6 proposal have been corrected. From now on, user registration is disabled, logbooks for next proposal will be set up automatically once the proposal info is migrated from UPEX to MdCnix. Any subsequent changes (like a new user added in MdCnix to a given proposal) has to be done on request either by admin of particular logbook or ITDM.

Standard setup of beamtime logbooks is the following

  • Admin list contains ITDM staff, instrument support group (as given by relevant instruments), PI and Main proposer as given in UPEX
  • User access is given ITDM staff, instrument support group and all participants of a given beamtime.

All subsequent customisation, including adding extra users, should be made by logbook admins.

Regarding logbooks for the past proposals in September, not all was corrected according to the above defaults, especially there may be wrong email addresses put at that time by users during registration -this can be fixed as well, taking info from UPEX.

Also HELP logbook was updated.

This change affects also XFEL internal usage of ELOG, as from now on, a new user has to be added by a relevant admin.

Cheers, 

Janusz
 

Entry   Status after 9.30 dispatch meeting, posted by Adriano Violante on 01 Nov 2017, 11:24 

Instruments

  • SPB:
    • When PLC loops are restarted, still many device parameters are not properly recovered. This generates a lot of work for the team. Recently an entire day was lost.
      • The procedure now foresees a notice to the relevant group before each loop update. In particular, CAS will be asked for the last version of the parameters export to be re-implemented. The relative script was also updated and some bugs were fixed.
    • Loop 4 (maybe also 3) - MKB system - needs to be updated. This will be done as soon as the last eplan export is available.  
    • XTD9 loop needs to be updated with proper encoder names. CAS takes care of the missing names.
    • AGIPD Interlock system (loop 5) shows some issues concerning valves. It is not clear whether this is due to real problems with the interlock definitions or just to the fact that the system is not yet in vacuum. Chember will be pumped today and then the final test will be done.
  • FXE:
    • Preparation for the users run ongoing. PP laser treatment test ongoing.

Tunnels

  • XTD10/SASE3
  • XTD9/SASE1
    • Si-Mono: work has been done during the week end. The idea is to have it running without tilt stages.

Laser

  • Delay control is available through KARABO but requires ca 2 days testing: ongoing.

Electronics

  • Currently the work that is still needed for SASE3 is being evaluated
  • Planning for the next shut down is going on

CAS

  • Working on DOOCS/KARABO integration together with DESY. Ongoing. General frame being built. Then priority on the FEL imager needed for first lasing.
  • A. Silenzi and S. Hauff worked on the AGIPD procedures: Cooling down procedure successfully tested.
  • Work continues on reading and writing data for the GreatEyes detector: The idea is now to test the parallel operation of LPD, Gotthard and Greateyes detector.

ITDM

  • The folders for the next user run are being set up next week. GPFS is now fixed.
  • SPB requested 18 new cameras. This effort needs to be carefully coordinated. CAS and ITDM are working on that.
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 27 Oct 2017, 11:38 

Instruments

  • SPB:
    • When PLC loops are restarted, still many device parameters are not properly recovered. This generates a lot of work for the team. Recently an entire day was lost.
      • Answer from AE: The parameters are extracted by CAS using KARABO. It is possible that not all necessary values are returned. AE is also investigating whether there are some bugs in the firmware procedure. It is pointed out that the change from 24V to 48V led to a huge amount of changes. 
    • Injector motion is now working along all three axes
    • AGIPD automatic power up procedure is now working. Tests continue
  • FXE:
    • The spurious data losses with the Gotthard Detector were further investigated. They are not resolved but they do not limit operation with 30 bunches

Tunnels

  • XTD10/SASE3
    • All vacuum sections are connected, locally tested and ready
    • Part of the interlock system is also ok. A global test of the entire integrated system still needs to be performed
    • The biggest challenge was the gas attenuator section with 7 turbo pumps. All pumps were locally test and integrated into the control system. The vacuum is very good (10-9) Now they are put into a  safe state.
    • R. Villanueva would like to be informed in case whenever the interlock in XTD10 is broken so he can inspect the system
    • XGM is connected to the overall vacuum and tested. The interlock is working and it is also connected to DOOCS
    • The two imagers requested for first lasing (SR/FEL) are available
    • Approximately one shift would be needed to take care of a few remaining tasks before first lasing
  • XTD9/SASE1
    • The HiRex is fully operational
    • The Si-Mono needs work but this was de-prioritized as it is not needed for the next users

Laser

  • Full specs were reached for both the SPB and FXE beams. The laser is in the respective instrument laser hutches
  • The laser was covered in order to reduce effects of any remaining air drafts
  • Differential mode compensation is available. Common mode compensation is not
  • Work still continues on the 4 agree-upon bunch patterns. Another meeting is set up for today
  • Delay control is available through KARABO but requires ca 2 days testing

Detectors

  • For AGIPD both  for turning on power and cooling automatic procedures were implemented and tested
  • LPD was moved to Karabo 2.18. 
  • One charge injection run was done and the system operated for 2 days without interruts

Electronics

  • Currently the work that is still needed for SASE3 is being evaluated
  • Planning for the next shut down is going on

CAS

  • Currently planning next OCD period
  • Very good progress was made in SASE3
  • Working on DOOCS/KARABO integration together with DESY
  • Work on the laser is progressing
  • A. Silenzi and S. Hauff worked on the AGIPD procedures
  • Work continues on reading and writing data for the GreatEyes detector
  • As reported by the detector group, the stability of the DAQ is much improved

ITDM

  • A major problem caused the Maxwell cluster to be down for 3 days. IBM Technicians had to be called
  • In this context it became clear that the communication with the users must be optimized
  • Now the system is ok
  • The folders for the next user run are being set up next week. This was delayed due to the technical problems
  • For the experiment log books the users will now be automatically set up
  • The update of the DAQ for AGIPD is somewhat delayed due to the long time taken for the recabling
  • SPB requested 18 new cameras. This effort needs to be carefully coordinated.
Entry   XTD10 closed and interlocked, posted by Tobias Haas on 26 Oct 2017, 17:34 

The SASE3 tunnel XTD10 was searched by Janni and her team and interlocked about one hour ago.

It is now almost ready for first lasing in SASE3:

  • The vacuum is completely connected and closed from V0 all the way to the end
  • All valves, pumps and gauges are included in the PLC loop and can be controlled from Karabo
  • The gas attenuator section was completely tested and is also under PLC control. The turbos are isolated from the rest of the vacuum and put into a safe state
  • All three DPS's are operational, tested and included
  • All imagers are operational
  • The XGM vacuum is part of the general vacuum and controlled and monitored from KARABO
  • The interlocks of the DPSs were succesfully tested

In order to allow beam, it is estimated that one access with approximately 8h would be needed to sort out some remaining smaller issues

I would like to thank the entire team from Vacuum, Optics, Diagnostics, AE and CAS for the big effort and in particular C. Youngman for coordinating.

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 25 Oct 2017, 15:20 

General

  • After discussion between XFEL Vacuum (J. Eidam) and DESY XFEL Run Coor (Matthias Scholz) it is agreed that XTD10 will only be closed on Thursday and that XFEL will search the tunnel between 15:00 and 17:00. (This information became available only after the meeting)
  • This gives some extra time to finish activities in XTD10

Instruments

  • FXE
    • Currently A. Parenti and FXE are hunting a spurious data loss in Gotthards
    • Otherwise the software is surprisingly stable
  • SPB
    • Slow progress towards getting the Detector going again
    • The task to ease the acquistion needs help from the DESY developers

Tunnels

  • XTD10:
    • A lot of progress was made by the team working in XTD10: Thank you very much!
    • The complete tunnel is under vacuum
    • Also the missing pieces between XGM/MCP and the rest were inserted 
    • Cleanup is done
    • Denis and Raul are still working on local tests of the gas attenuator system
    • Testing is somewhat slowed down because the GUI client no longer allows active manipulation of components at the moment. So the ikarabo interface is used
    • Work also continues on getting the mov1 loop going
    • Local tests are done on all imgers except on the exit slit imager
  • XTD9
    • The FXE Mono is not finished. It needs a restart of the motion loop
    • AE will check when this is possible, but there are a lot of constraints from users and from resources
    • Since there has been a change in the interlock system, SPB needs to be in place when the shutter to XTD9 is opened. There is a risk of triggering the interlock and shutting down the machine.

AE

  • Almost everything that was planned could be achieved in XTD10
  • Some of the remaining work can be finished when the tunnel is closed.
    • Work is going on to finish the controls
  • Even the interface to MPS that was originally not foreseen is now available

CAS

  • The workaround that allows to modify parameters even though the protection does not allow this, is now in place. This should help with the trouble observed by the Vacuum Group.
  • A new bug in the PLC was observed in this context. Changing a parameter whose name has changed leads to a crash. 

ITDM

  • Currently the MAXWELL cluster is unavailable.  This is a serious software/hardware issued. The manufacturer is actually on site to fix the issue today
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 23 Oct 2017, 16:54 

FXE:

  • Pump-probe beam is now in the instrument hutch
  • Currently working on setting up the remainder of beam steering and compression
  • Gotthardt is working. Tests are going on a and some issues with the DAQ still need to be solved
  • The sample stack needs to be moved up stream for the next user period

SPB

  • Still working on AGIPD. Many cables needed to be disconnected and are being re-connected now
  • AE finished all the scheduled modifications on the crates and are doing some more that were originally not scheduled
  • A few details with the interlock need fixing
  • The newest version of Beckhoff_Devices needs to be deployed
  • The previously observed slowness of the GUI is probably fixed but needs more real life exposure. Final test are being done
  • The full infrastructure should be back and operational Tuesday/Wednesday

Tunnels

  • Work is going on on the gas attenuator
  • Interlocks are ready for the WP74 DPS and the XGM
  • Detailed steps to completion in XTD10 were re-iterated by C. Youngman. Additional coordination off line after the meeting
  • L. Samoylova mentioned that the mirror encoders in XTD2 are currently in error. B. Baranasic will have a look

AE

  • In the new version of KARABO, the rights for reading and writing parameters from and to the PLC are now being observed, differently from before.
  • This causes problems. P. Gessler mentions that he is very concerned that such a major change is introduced so briefly before the next user period. This puts AE under great pressure and leaves almost no time for testing
  • All the SASE1 loops were updated because of the new "feature" in KARABO
  • A. Silenzi mentions that he can implement a workaround for this "feature" so that loops need no updating. However, this requires a new KARABO release

CAS

  • KARABO2DOOCS: Meeting today with the DESY control people at 1430 in BKR
  • ScanTool: Meeting foreseen Tuesday/Wednesday with the instruments
  • The GUI slowness necessiated a hotfix which was verified within CAS. Now waiting for feedback from instruments
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 20 Oct 2017, 15:42 

General

  • SASE1 Instruments are asked to comment on progress with KARABO 2.1.18
  • Tunnels XTD9/10 will be closed on 25 Oct at 1700

Instruments

  • FXE (A. Galler):
    • KARABO 2.1.18 appears to be working ok. The device instantiation problem reported earlier in the week is no longer there. However, not all equipment could be tested yet
    • Work currently focusses on preparing for the next User Run and in particular on preparing the sample environment
  • SPB (A. Mancuso)
    • A situation similar to the on in FXE is observed. Full proof of functionality of KARABO will only be possible once AGIPD is fully assembled again which is next week at the earliest
    • Currently, work is going on inserting the AGIPD cables into drag chains so that the detector can be moved on the CSS. This work should finish today

Tunnels (J. Eidam, R. Villanueva, T. Maltezopoulos)

  • Leaky vacuum pipes were successfully welded
  • Absorber section is closed and under vacuum
  • MCP detector is connected
  • DESY finished work on the upstream section in the dump
  • The gas attenuator has very good vacuum (10^-9)
  • Differential pumping is ready from the HW side
  • Cabling for the gas attenuator section is still going on
  • Alignment was done in view of the small apertures in the gas section
  • Local tests can start now (This is 3 days behind the schedule made at the beginning of the week)
  • PES is installed but will only act as a pipe.

Laser (M Lederer)

  • NOPA Beam is now going to FXE
  • Next week it will be brought to SPB
  • The KARABO version used is several versions back with respect to the one in the instruments and there are still a few minor problems
  • On Monday work on programming the laser burst patterns together with the respective people at DESY shall start
  • Continue testing
  • There appears to be a shortage of conversion crystals for the instruments. New ones have been ordered but are not there yet.

Detectors (P. Lang)

  • AGIPD HW work is on track and finishes thie week. Software work starts next week
  • LPD control system works ok with KARABO 2.1.18. 
  • Some small issues with LPD calibrations

ITDM (K. Wrona)

  • Two updates were done for the DAQ of LPD
  • Some issues were found with the RC
  • It was tried to install a new version. This was already done for AGIPD

AE (T. Freyermuth, B. Baranasic, J. Tolkiehn)

  • SASE1 Tunnel:
    • Vacuum loop was updated without problems
    • The motion loop was updated a few times because there were problems with some motors. The work continues today
    • EPS loop was updated
    • On Monday/Tuesday the SPB loop will be updated to account for the terminal changes from 24V -> 48V
  • SASE1 Instruments:
    • Loop 5 with the redundancy module is now ok
    • Loops 2, 4, 7 were updated
    • Next come loops 1 and 12
    • All modified modules (24V -> 48V) are installed but a few more might need to be changed
  • SASE3 Tunnel:
    • Tried to get the vacuum loop up
    • But there are still many mistakes and inconsistencies with names
    • A big amount of work is still needed for the gas attenuator

CAS (S. Brockhauser)

  • KARABO 2.1.18 was deployed
  • Good progress was made with the Gotthard and GreatEyes Detectors
  • For GreatEyes a specific driver on a specific computer will be used
  • The problem with extra delays in the GUI client was resolved
  • Scantool:
    • A plan of what to implement exists. This needs to be checked with the instruments
    • A first part of this tool is actually already implemented
    • A. Galler points out that he sees the problems predominantly in the integration with the rest of the environment
  • DOOCS2KARABO
    • An example for pipelined data was sent to DESY
    • There is no showstopper seen, but the work is progressing according to priorities which are 1 Laser, 2 Undulators, 3 DOOCS2KARABO
    • Diagnostics points out that the will need both the scantool and DOOCS2KARABO for their commissioning period from 1 - 7 Nov. CAS should please provide information so that the tools can be tried
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 16 Oct 2017, 17:11 

Dear all,

I updated the schedule for the tunnel access in the upcoming weeks based on the discussions in the PSO- and the Operation Board-meetings:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status and Plans after 01:30 meeting, posted by Tobias Haas on 16 Oct 2017, 15:22 

General

  • Closing of XTD2/4/9/10 foreseen for Oct 23. Possibly XTD9/10 can be re-opened afterwards and stay open until 28 October

Instruments

  • SPB:
    • A lot of cabling work was done. Cable drag chains were installed for AGIPD to move it to another posiiton
    • Roughing pipes were installed
    • Update of KARABO to 2.1.18 was not as smooth as expected. Currently it is not operational. An operational control system is needed soon
    • M. Messerschmidt sent another message with problems early today
  • FXE
    • Final testing ongoing of Gotthardt with KARABO
    • Cable management and cable re-routing was done last week

Tunnels

  • V0 valve was replaced
  • The first vacuum section down stream from V0 was successfully closed and leak tested
  • DESY Vacuum group is currently working on the respective section upstream of V0
  • Welders are here today to work on the two pipes with leaks. They spent all morning on safety trainings
  • The gas attenuator was leak tested on the "good" side (where vacuum section is currently ok/no leaks)
  • Pumping has started on the diff pumping section by Vac
  • Many small things (mostly cabling and electronics)_ remain to be done

Diagnostics

  • Group was not represented by some infos from J. Tolkiehn
  • More tests are needed for the Diff Pumping of the Diagnostics group.
  • Diff Pumping and PES require more crates to be connected

AE

  • SPB loop 5 was cycled.
  • The issues with the turbo pumps is being worked on today (Pumps do not turn on after loop is cycled)
  • Work is ongoing on the MKS gauge controller
  • In the SASE1 tunnel the motion loop will be updated tomorrow and the vacuum loop on Wednesday 
  • At this time the SPB loop in XTD9 will also be cycled
  • FXE is asked to provide information on what works need to be done
  • SASE3 Tunnel:
    • Interlock definitions arre prepared but need to be implemented
    • Many local tests still ongoing
    • There are still problems with inconsistent/wrong device names
    • Two motions loops (mov1/mov2) mov1 contains the most important components upstream
    • EPS not expected for some time

ITDM

  • GPFS upgrade today
  • redundancy data link might be done today
  • Tomorrow: DAQ SW upgrade for LPD (Is still at KARABO 2.1.16.4)

CAS

  • Long discussion happened on what the word "mandatory" means in conjunction with the most recent KARABO release
  • CAS will look into the specific problems in SPB and FXE that have been brought up
  • H. Santos discussed the scan tool with S. Brockhauser on Saturday
    Reply   Status and Plans after 01:30 meeting, posted by Tobias Haas on 16 Oct 2017, 15:54 

Dear Tobias,

Just to clarify that the last information that we got from SPB was the message below. From this information and the technical evaluation that we did the issue is not strong enough to classify Karabo 2.1.18 as "Currently it is not operational. An operational control system is needed soon". This statement is too strong and does not contain technical fundamental. 

Anyway, we already mentioned in the meeting that since Friday we have been working to solve the problem and we already have alternatives. We will publish a patch (Karabo 2.1.18.x) today or tomorrow.

Finally, I talked offline with Adrian and we agreed about some topics. Especially to review the "mandatory" word in the release process.

Hugo


From: "Marc Messerschmidt" <marc.messerschmidt@desy.de>
To: "Hugo Santos" <hugo.santos@xfel.eu>, "chen xu" <chen.xu@xfel.eu>, "cyril danilevski" <cyril.danilevski@xfel.eu>, "Marc Messerschmidt" <marc.messerschmidt@xfel.eu>, "Jolanta Sztuk-Dambietz" <jolanta.sztuk@xfel.eu>, "Britta Weinhausen" <britta.weinhausen@xfel.eu>, "Alessandro Silenzi" <alessandro.silenzi@xfel.eu>
Cc: "John Wiggins" <john.wiggins@xfel.eu>
Sent: Friday, 13 October, 2017 20:47:41
Subject: AW: GUI Responsiveness in SPB

I saw some issues today as well when instantiating devices, but nothing as bad as yesterday. The gui delay also seemed functional and went only up top around 30s.

Marc 

 

 

Tobias Haas wrote:

General

  • Closing of XTD2/4/9/10 foreseen for Oct 23. Possibly XTD9/10 can be re-opened afterwards and stay open until 28 October

Instruments

  • SPB:
    • A lot of cabling work was done. Cable drag chains were installed for AGIPD to move it to another posiiton
    • Roughing pipes were installed
    • Update of KARABO to 2.1.18 was not as smooth as expected. Currently it is not operational. An operational control system is needed soon
    • M. Messerschmidt sent another message with problems early today
  • FXE
    • Final testing ongoing of Gotthardt with KARABO
    • Cable management and cable re-routing was done last week

Tunnels

  • V0 valve was replaced
  • The first vacuum section down stream from V0 was successfully closed and leak tested
  • DESY Vacuum group is currently working on the respective section upstream of V0
  • Welders are here today to work on the two pipes with leaks. They spent all morning on safety trainings
  • The gas attenuator was leak tested on the "good" side (where vacuum section is currently ok/no leaks)
  • Pumping has started on the diff pumping section by Vac
  • Many small things (mostly cabling and electronics)_ remain to be done

Diagnostics

  • Group was not represented by some infos from J. Tolkiehn
  • More tests are needed for the Diff Pumping of the Diagnostics group.
  • Diff Pumping and PES require more crates to be connected

AE

  • SPB loop 5 was cycled.
  • The issues with the turbo pumps is being worked on today (Pumps do not turn on after loop is cycled)
  • Work is ongoing on the MKS gauge controller
  • In the SASE1 tunnel the motion loop will be updated tomorrow and the vacuum loop on Wednesday 
  • At this time the SPB loop in XTD9 will also be cycled
  • FXE is asked to provide information on what works need to be done
  • SASE3 Tunnel:
    • Interlock definitions arre prepared but need to be implemented
    • Many local tests still ongoing
    • There are still problems with inconsistent/wrong device names
    • Two motions loops (mov1/mov2) mov1 contains the most important components upstream
    • EPS not expected for some time

ITDM

  • GPFS upgrade today
  • redundancy data link might be done today
  • Tomorrow: DAQ SW upgrade for LPD (Is still at KARABO 2.1.16.4)

CAS

  • Long discussion happened on what the word "mandatory" means in conjunction with the most recent KARABO release
  • CAS will look into the specific problems in SPB and FXE that have been brought up
  • H. Santos discussed the scan tool with S. Brockhauser on Saturday

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 13 Oct 2017, 13:48 Zusammenstellung_Nivellement_Oktober_2017.pdf

General

  • A recent survey has shown that the experiment hall and the end of the tunnels XTD9 and XTDD10 have settled by as much as 6.5mm. If components need to be re-aligned a completely new network of points would need to be established. This is not foreseen before the end of the year. A plot is attached to these minutes

Instruments

  • SPB: 
    • Recabling of many components is currently going on
    • AGIPD has been opened and some electronics are being exchanged
    • Preparations are being made to move AGIPD also to a more downstream position
    • Laser table for bringing the PP laser to the sample has been set up
  • FXE:
    • Cables in the hutch have been re-routed and cleaned up
    • Preparations for the PP laser are well advanced as the Tangerine laser was already brought to the sample

Laser:

  • Work is going on under pressure as the time available until first laser beam is short
  • 3 Days were lost due to unannounced shut downs of the AC systems. 
  • Both the SPB and the FXE NOPAs are running
  • There are problems with triggering the ADC and hence the timing drift cannot be locked. The problem was reproduced in the lab and fixed. But the fix needs to be transferred to the laser hutch
  • Tests with the machine timing are still outstanding and it seems that there are some resource issues on the DESY side
  • Currently the optical sync system from DESY provides too little power and hence the laser cannot be synchronized by optical X-correlation. For the upcoming run period sync to the RF system will be used. This means that up to ps drifts are to be expected
  • The laser is very sensitive to changes in the humidity. This has been traced to the construction of the laser tables which involves wooden side panels. The problem has been discussed with Newport and the laser tables for SASE2/3 will be modified to avoid this

Tunnels:

  • Vacuum XTD10/SASE3:
    • There are currently two leaks in welded beam pipes. The welders are coming on Monday to fix this
    • After the leaks are fixed the MCP can be connected to the vacuum
    • And then finally this entire vacuum section can be closed
    • There are several leaks in the dump area. In particular the V0 valve is leaking and one flange. DESY will exchange V0 next week.
    • The pipe that hit in the vacuum incident in September appears not to be leaking
    • The absorber appears to have been damaged in the September incident and needs to be replaced. The SASE2 absorber could be used
    • Vacuum tests were done for the differential pumping downstream of the gas attenuator
    • Work is still being done one the differential pumping of the Diagnostics group
    • Interlock needs to be set up and tested
    • M. Petrich defined the interlock conditions and sent them to AE. This still needs  to be implemented
    • Cabling was done for the gas attenuator
  • Diagnostics
    • Inhibits for XGMs in in XTD2/9/10 was implemented
    • Loops were successfully rebooted in XTD9
    • A lot of work done on HIREX (camera exchanged, Gotthard connected to Beckhoff and tested)
    • Today repairs will be done on the MCP in XTD2
    • For both MCPs in SASE1/3 additional Beckhoff terminals will be installed
    • Next week focus will be to finish in XTD10 and get plc control of installed devices
    • All 10 imagers in SASE3 were tested. 3 needs fixes/repairs

AE

  • In order to close the loops in SASE3, focus should be given to the most relevant components
  • Component lists were circulated. Please check!
  • Work on KMONO is complete
  • What should happen to the CRL of FXE in XTD2? Statement from A. Galler: Nothing for now as it can be operated for the upcoming user run
  • Work on the instruments is ca 50% done
  • In SASE3 most local test are done
  • It will be tried to get the Vacuum and Motion 1 loop going next week
  • The EPS loop is not so critical

ITDM

  • The announced GPFS update was postponed several times but will now happen next Monday
  • The DAQ for AGIPD was upgraded (The SW used so far was dating back to May)
  • The time allocated was 3h. The upgrade was done after 1h, so the remaining 2h were used for tests.
  • Longer runs could be taken without major problems
  • People should be aware that during the first three days next week, the detectors cannot be operated due to the GPFS upgrade

Software

  • Planning is being aligned between CAS (H. Sanchez) and PSPO (M. Areste)
  • Progress was made for the laser. The software however will remain at version 2.13 since they do not need DAQ and the scan tool
  • Yesterday version 2.18 was released. It is already deployed for SASE1
  • Note that this version is not complatible with previous GUI clients
  • Next week: Work with AE for SASE3
  • There is no news on the scantool as S. Brockhauser was not present
  • FXE should be updated to 2.18 today
  • The DOOCS/KARABO interface is not considered a priority on the DESY side. They are working on the undulator controls

 

Entry   Status report after dispatch meeting 13:30, posted by Adriano Violante on 09 Oct 2017, 14:00 

Tunnels (J. Eidam, J. Gruenert)

  • SASE3:
    • ​1st section is not recovered yet, ongoing.
    • Diff. pumping XGM is being installed
    • Leak tests ongoing
    • MCP manipulator XTD2: company got the training - repair ongoing 
    • Absorber was moved ==> has to be realigned by MEA
    • A. Koch is commissioning the imagers. Some bugs were found and will be solved with the new release of Karabo.
    • MCP, FEL-Imager: Crates are there, AE still has to understand and define the priorities of their work
    • No access to the tunnels with visitor cards! (Access to tunnels requires rebreather training, knowledge about procedures, warnings, dosimetry etc.)
    • Exchange of gotthard detector in XTD 9 ongoing.
  • SASE1:
    • ​XGM Inihbit system will be brought up tomorrow. VAC loop needs to be brought down . Will be notified with a message in the logbook.

 

Electronics (P. Gessler)

  • Responsibles
    • SASE1: Bernard Baranasic
    • SASE3: Jan Tolkiehn
    • Instruments SASE1: Tobias Freyermuth
  • Fast valve terminals exchanged today. 
  • Documentation by WP74 + Vacuum is not consistent ==> AE will provide an Excel-sheet to be used, which should give a consistent picture of all terminals, connections etc. Ongoing

ITDM (K. Wrona)

  • Both online & offline-filesystems have to be updated. Postponed to TOMORROW (16.10.): Online-FS will be down, offline-FS will be worked on continuously, should not be down, but at reduced performance, since update will be server by server.
  • DAQ-Upgrade: still running Karabo 2.1.12 on detectors, which requires lots of restarts. UPGRADE: TOMORROW 13==>16 to Karabo v.2.1.16

Software (H. Santos, A. SIlenzi):

  • Karabo 2.1.18 being tested. Test to continue for a couple of days before deployment.
  • S. Brockhauser will report on the status of the scan tool this Friday.

 

Entry   Online storage update on Monday 9th Oct, posted by Janusz Szuba on 04 Oct 2017, 10:31 

We would like to take the oportunity of the shutdown period and update the online storage next week on Monday 9th Oct. This will take approx. half a day. During that time the online storage will not be available on the online computing cluster as well as on pclayer servers used for DAQ. In the same way, the nfs export for data logger is also affected.

Regarding data collected on the online cluster, although it should not have any influence, but as a precautionary measures, please make sure that all relevant data from all past proposals  are migrated to offline storage, which in practice means requesting migration via metadata catalog web interface. If there are still issues with particular runs not being able to be migrated, please contact ITDM.

regards,

Janusz 

    Reply   Online storage update on Monday 9th Oct, posted by Janusz Szuba on 06 Oct 2017, 14:42 

After today's discussion with WP75 group, we decided to postpone the update of the online storage to the next Monday 16th October.

Janusz Szuba wrote:

We would like to take the oportunity of the shutdown period and update the online storage next week on Monday 9th Oct. This will take approx. half a day. During that time the online storage will not be available on the online computing cluster as well as on pclayer servers used for DAQ. In the same way, the nfs export for data logger is also affected.

Regarding data collected on the online cluster, although it should not have any influence, but as a precautionary measures, please make sure that all relevant data from all past proposals  are migrated to offline storage, which in practice means requesting migration via metadata catalog web interface. If there are still issues with particular runs not being able to be migrated, please contact ITDM.

regards,

Janusz 

 

Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 06 Oct 2017, 11:15 

SPB (B. Weinhausen): 

  • Users took good data
  • Problems occured with the DAQ / control system
  • Working on diamond @ beamstop
  • Preparation for several updates / activities regarding AGIPD

FXE (A. Galler):

  • User took good data, analysis is ongoing
  • Will rework cable routing/connections
  • Chiller was moved to the rackroom, redo the connections etc.

Tunnels (M. Dommach, H. Sinn, J. Gruenert)

  • SASE3:
    • ​1st section is not recovered yet, DESY Vacuum has to replace the last valve here, works have not started yet
    • 2nd section with K-Mono, which was vented, is now pumped again.
    • Diff. pumping in gas section has been tested, upcoming are interlock tests
    • Gas attenuator still needs a lot of cabling, cooling water and compressed air
    • Leak test starts
    • MCP has to be connected next week
    • Leak @ absorber: has to be reweld by Trinos, or a blind flange has to put right after the absorber ==> should not hinder the 1st lasing attempt.
    • Absorber was moved ==> has to be realigned by MEA
    • A. Koch is ready to commission several imagers as soon as the motion loop is up&running
    • Next Monday AE, WP74, Vacuum etc. will finalize which components will be implemented in the motion loop during the October shutdown
    • MCP, FEL-Imager: Crates are there, AE still has to understand and define the priorities of their work
    • Repair of MCP: Access to XTD required, WP74 to clarify with SRP.
    • No access to the tunnels with visitor cards! (Access to tunnels requires rebreather training, knowledge about procedures, warnings, dosimetry etc.)
    • Hirex was calibrated @ 9keV, is ready to measure the bandwidth, was determined to be 20eV FWHM

Laser (M. Lederer)

  • NOPA-Alignment progressing
  • Some setbacks due to shutdown activities by MKK, which affected the humidity stability ==> tables bend
  • Laser synchronization has to be implemented by WP18, is questionable, the responsible expert is going on vacation next Friday.
  • Motors seem to move reliably now
  • No process yet to let the users easily change the laser burst pattern via software. Currently, BKR is being informed about our needs, and they "drive" the laser through timing signals from BKR.
  • Laser group will operate in a shift pattern:
    • 8-16h morning shift
    • 15-23h late shift

Detectors (M. Kuster)

  • AGIPD:
    • Decided not to modify the vacuum
    • Working on internal calibration
    • Working on increase of the bias voltage to improve the performance
    • Electronics are being replaced partly
  • LPD:
    • Upgraded the chiller
    • A leak occured due to the increased pressure, since the chiller was put into the rack room ==> pressure reducer is used now
    • Will exchange faulty super-modules
    • Working on the internal calibration
  • Planning next beamtime & shift schedule as laser group has setup
  • There still exists a risk to collide AGIPD-modules, meeting with the AGIPD-consortium to agree on changes for the next detectors
  • Problem with additional frames which had to be taken during data acquisition: pattern upgrade / firmware upgrade required, will not come in October.

Electronics (P. Gessler)

  • Responsibles
    • SASE1: Bernard Baranasic
    • SASE3: Jan Tolkiehn
    • Instruments SASE1: Tobias Freyermuth
  • Lots of updates are required, could all be done in short succession ==> can the beamline be put in an insensitive state, to allow quick series of updates?
  • Documentation by WP74 + Vacuum is not consistent ==> AE will provide an Excel-sheet to be used, which should give a consistent picture of all terminals, connections etc.

ITDM (K. Wrona)

  • Both online & offline-filesystems have to be updated. Monday: Online-FS will be down, offline-FS will be worked on continuously, should not be down, but at reduced performance, since update will be server by server.
  • How should ITDM communicate this to the user? Suggestion: Setup an email-list for users to subscribe to, so those individuals who actually work on the data get the updates, and not every user.
  • Capacity of the offline FS has to be increased
  • DAQ-Upgrade: still running Karabo 2.1.12 on detectors, which requires lots of restarts. Will upgrade to .13 first.
  • Still there is no proper commissioning of the Gotthard. Testing would be appreciated to improve reliability ==> time required from Detector and Instrument

Software (S. Brockhauser):

  • Karabo 2.1.18 to be released today, but not immediately to be installed. To be deployed after PLC upgrades.
  • Karabo + DOOCS: A meeting took place with T. Wilksen (responsible for DOOCS). ==> interface for slow data / digits exists, but not for pipelined data / cameras / images
  • Highest priority of the DOOCS-Team are the SASE3 undulators, which is not in line with the XFEL priorities (improving the stability / reliability of the SASE1 operation)
  • C. Youngman to work on the master equipment list for SASE3
  • A. Galler: Is the current situation really bearable for the instruments, can we actually call this upcoming beamtime "user time"? ==> S.Brockhauser: Lots of problems have been solved, new will arise...
  • A. Galler: Will we be able to do a simple blade scan through a laser beam and get a plot?
    ==> S. Brockhauser: We are working on this. You can have plots showing motor positions, intensity, and then correlate this.
  • H. Sinn: Basically, we still to not have a working scan tool, which is a big drawback. This is one of the very basic functionality every user will expect!

Priorities & Schedule (G. Wellenreuther, H.Sinn):

  • Operation board should decide about updated schedule next week
  • Users & instruments request time to with beam to set up before user time!
  • OCD-contacts for TS were provided (again?)
  • In general, interface to OCD should be harmonized for all groups (e.g. always have a fixed cellphone number)
  • Activities for the shutdown have been gathered by PSPO, and are being provided to the support groups for crosschecking.
  • No major collisions/ bottlenecks appeared apart from the high workload / demand for support by AE and CAS.
  • AE and CAS will crosscheck and provide feedback to PSPO regarding resources & priorities if required.
Entry   Status and plans after Readiness Meeting, posted by Monica Aresté on 04 Oct 2017, 12:10 Shut_down_task_list.xlsx

General:

Reminder to all the groups to provide the shutdown task list today afternoon to PSPO. Find template attached.

SPB:

  • In general was a succesful weekend. On Sunday there were some problems with control and DAQ already reported to CAS.
  • To check if there were additional problems on Monday and report to CAS if necessary.
  • To provide the shutdown task list to PSPO.

FXE :

  • Was not present, so nothing was reported.

Tunnels:

  • Nothing particular.
  • List with the shutdown tasks to be provided to PSPO.

Laser:

  • Motors were not working, this issue was partially solved in a couple of motors. Detected that the problem was a configuration issue in the PLC. WP-78 will test the solution in other motors of the same kind.
  • Laser was running during thre weekend, data will be reviewed today to analyse laser behaviour.

Detectors:

  • To investigate a problem with AGIPD, this will require the support from CAS.

Electronics

  • Preparing for Oct. shutdown.

ITDM

  • DAQ problems on Monday and Tuesday due to detector configuration, still working to find out the causes of the problem.

Software

  • Working in the problems reported during the weekend.

 

 

 

Entry   WP74 - OCD contacts for this weekend, posted by Andreas Koch on 29 Sep 2017, 14:46 

30.09. from 08:00 until 01.10. 08:00 - Andreas Koch 9-6443

01.10. from 08:00 until 02.10. 08:00 - Joakim Laksman 9-5630  

Entry   SASE1/SASE3 Readiness meeting on Monday cancelled , posted by Monica Aresté on 29 Sep 2017, 11:03 

The SASE1/SASE3 Readiness meeting next Monday is cancelled we will meet again on Wednesday the 3rd of October.

    Reply   SASE1/SASE3 Readiness meeting on Monday cancelled , posted by Monica Aresté on 29 Sep 2017, 11:09 

Correction: We will meet again on Wednesday the 4th of October.

Monica Aresté wrote:

The SASE1/SASE3 Readiness meeting next Monday is cancelled we will meet again on Wednesday the 3rd of October.

 

Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 29 Sep 2017, 10:43 

SPB (A. Mancuso): 

 

  • Users are in good shape
  • Beam operation with ca. 600 microJ, but beam seems to be ring-shaped after M2?
  • Preparing for first pump&probe experiments in November.
  • Start of the focussing mirror controls should start after the user run

FXE ():

  • Was not present at the beginning of the meeting, so nothing was reported.

Tunnels (M. Dommach):

  • SASE1:
    • Nothing particular.
  • SASE3:
    • ​Preparing for the works in XTD10 during the Oct. shutdown are ongoing.
    • PES: Will just be connected to vacuum & pumped, not functional.

Laser (M. Lederer)

  • Sustained small damage during set-up
  • Not much time left until user run requires PP-laser
  • Issue regarding motors not coming back to their position reliably still persists / is not solved. ==> To be tackled by Gabriele (CAS) + Nerea / Nicola / Janna (AE)

Detectors (P. Lang)

  • Detectors are in operation
  • Works in Oct. shutdown mostly indepenent from other groups
  • LPD & Gotthard run together, but Gotthard has not yet detected X-rays?

Electronics (P. Gessler)

  • Preparing for Oct. shutdown
  • Train-builder should be tested in the Winter shutdown, because the contract only runs until March.

ITDM (K. Wrona)

  •  There are some issues with run-control, being investigated.

Software (S. Brockhauser):

  • Daily meetings with FXE & SPB.
  • C. Youngman is working on the Master Equipment List for SASE3. The basic assumption is to copy any configurations/parameters from SASE1 to SASE3.
  • Focussing now more on the SASE1-issues (e.g. Karabo-DOOCS-Interface ==> will mirror devices from Karabo into DOOCS.)

Priorities & Schedule (T. Tschentscher, G. Wellenreuther):

  • Performance of SASE1 has to be improved, in particular the performance of the accelerator. This has higher priority than continuing building up SASE3 or SASE2.
  • For example, the measurement of gain curves requires the MCP, consequently its completion has highest priority.
  • The control room also needs fast & direct access to more devices than just the XGM to properly tune lasing, consequently the Karabo-DOOCS interface has highest priority.
  • For the overall planning of the next ca. 5 weeks all groups are expected to report back to T. Tschentscher & PSPO until Wednesday next week. PSPO will produce a Gantt-chart of all activities. Template for the feedback will be sent around still today.
  • PSPO is tracking ALL major activities associated in all SASEs in the presentation shown. Missing items to be reported to G. Wellenreuther. Will be revisited on a ca. monthly timescale
  • Planning for the next shutdown in December should commence in early November (= after the upcoming shutdown), to allow for proper planning and preparations.
  • Despite the priority on SASE1, activities in SASE3 and SASE2 should progress. We still would like to attempt to do first lasing in SASE3 before the November user run!
Entry   Status and plans after SASE1/SASE3 Readiness meeting, posted by Monica Aresté on 27 Sep 2017, 10:11 

General

  • T. Tschentscher inform about Management Board priorities for the October shut down:
    • Management Board Priority 1 after the Oct shutdown will be the characterization for SASE1 performance. Any still necessary development for this (MCP, HIrex operation; two-way functional DOOCS-Karabo interface and data exchange; etc.) should get highest priority during the shutdown period. It would be good to achieve substantial progress with the DOOCS-Karabo interface before the MAC meeting to avoid general bashing of our controls. The instruments will provide a detailed list to permit support groups (ITDM, CAS, AE) to plan resources.
    • Priority 2: SASE3 completion. It is expected that the machine will anyway be able to reach lasing at SASE3, but this has lower priority at present.

SASE1 Instruments

  • SPB : 
    • No major issues to report
  • FXE:
    • In the next days FXE will work in the commissioning of Gothard & LPD in parallel operation to be ready to test with beam on Saturday.

Electronics

  • MPS Interlock for SPB already switched on.
  • No further issues to report.

ITDM

  • Users have no access to on-line DAQ. They can use off-line cluster, the transfer is 5 min. after the end of the run.
  • Out of the shift scientist should work with off-line cluster.

Safety

  • There is  a new procedure for tunnel access. Accelerator areas will have to be measured by Safety group before tunnel access release.
Entry   Status and plans after SASE1/SASE3 Readiness meeting, posted by Monica Aresté on 25 Sep 2017, 12:58 

General

  • Beam was lost due to incident with electron beam hitting & damaging components downstream of the northern dump.
  • Goal is to stablish proper conditions for the beam again, last week seemed much better. On Wednesday this week it is expected to have stable beam conditions and sufficient pulse energy for next experiments. 

SASE1 Instruments

  • SPB : 
    • Several persistant problems with Karabo that affect DAQ and Detector. Detector failed on Saturday triggered by the Karabo issues, it took long to recover since a complete power cycle of the Detector was required (30 minutes).
    • CAS is working to fix the problems.

Tunnels

  • SASE1:
    • Beam shutter closed during FXE shift, the reasons are not clear. M. Dommach and L. Samoylova to investigate to solve this issue.

Electronics

  • MPS Interlock for SPB tested but not switched on. Agreed to switch on this Tuesday.

ITDM

  • ITDM report that FXE experienced some problems with the DAQ but they did not inform ITDM . The Experiment team decided to continue and try to figure out by themselves. ITDM and FXE to discuss how to improve the communication for next time.
  • Next experiments require Gotthard & LPD in parallel operation ==> to merge Gotthard & LPD to same run control ITDM needs some time to test. Agreed to carry out the tests Tuesday and Wednesday this week, also fine for SPB.

 

Entry   Status and plans after SASE1/SASE3 Readiness Meeting, posted by Monica ArestĂŠ on 25 Sep 2017, 10:25 

General

To stablish proper conditions for the beam as it was before. On Wednesday to have the mirrors in the correct configuration and machine back to the old conditions at the end of the week.

SASE 1 Instruments

  • ​SPB (M. Messerschmidts): 
    • Reported several persistant problems with Karabo that affectd the DAQ and Detector. On Saturday detector falled over and took long time to recover. CAS wokring to fix this issue.
  • FXE:
    •  

Tunnels (M. Dommach):

  • SASE1:
    • Beam shutters closed during FXE shift. It is not clear the reasons why this happened, to investigate.

Electronics (P. Gessler)

  • MPS Interlock tested but not swichted on. SPB agreed to switch on the MPS tomorrow.

ITDM (K. Wrona)

  • FXE was runnig  experiments with problems in DAQ, the experiment this was not reported to ITDM
  • Next experiments require Gotthard & LPD in parallel operation ==> to merge Gotthard & LPD to same run control ITDM needs some time to test, agreed to perform these tests Tuesday and Wednesday this week.

Software

  • FXE:
    • Still daily meetings, prepare LPD & Gotthard
    • Working on GreatEyes, too
  • SPB
    • Configure slow-data cameras
    • Laser project is running in CAS
  • SASE3:
    • C. Youngman is the CAS-responsible, should collect requirements to compile master equipment list for SASE3 ==> to be compared against MEL SASE1 to identify additional work required.
  • SASE1:
    • Loops & Karabo will be updated together.

 

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Gerd Wellenreuther on 22 Sep 2017, 16:06 

General

  • First users have done experiments - despite the current problems it appears as if everybody was able to take some data for future publications.

Short Report from SASE1 Instruments

  • ​SPB (A. Mancuso): 
    • Beam was lost due to incident with electron beam hitting & damaging components downstream of the northern dump.
    • Currently only single bunch operation
    • Lots of work to be done in Oct. shutdown, Adrian will provide a list to Thomas Tschentscher
  • FXE (T. Tschentscher):
    • Problem with the Tangerine-laser affects PP-experiment ==> to be fixed on Tuesday
    • Consider to switch to oscillator only until then ==> lower repetition rate, lower OL pulse energy
    • Next experiments require Gotthard & LPD in parallel operation ==> merge Gotthard & LPD to same run control next week before user run.
    • Today, test with DAQ and Gotthard was successful, but Gotthard has never seen XFEL X-rays so far. ==> Test with beam could happen potentially Monday night (instead of user experiment)

Tunnels (M. Dommach, J. Grünert):

  • SASE1:
    • Few issues with XGM, have been or are being solved.
    • It was suggested to put the Hirex-grating into the beam while FXE is taking beam to measure / commission parasitically. But it appears next week neither Naresh nor Jan will be available.
  • SASE3:
    • ​Due to the electron beam incident the first vacuum sections have been vented, there is most probably a hole in the V0, but only Rad. Safety to access the tunnels right now. ZZ/Access by anyone else only after clearance through SRP - working there is probably only possible in Octorb
    • Beam did hit the beam pipe apparently just upstream of the transmissive imager. Imager and further (vacuum) electronics seems to have been damaged in the upstream part of XTD10.
    • Due to this incident, it should be reconsidered if dosimeters are required in XTD10, too. SRP did unfortunately not participate, and thus was not able to comment.

Laser

  • Working still on improving the laser
  • Issue regarding motors coming back to their position is most probably a firmware/options issue

Detectors

  • AGIPD:
    • According to Yolanta "operates better than expected"
  • LPD
    • Also operates better than expected
    • Configuration of LPD is getting messed up by people working in parallel / unclear status of the detectors Gotthard & LPD ==> There should be a responsible for the detector, who is present in the control room and can allow remote access to work with the detectors / run configuration. ==> These steps should be well-documented in the FXE-Logbook.
    • K. Wrona: Next week will be better with just one run controller.

Electronics (P. Gessler)

  • There is an issue with some motors & encoder @ SPB.
  • AE will finish the work on the last loops in SASE1.
  • WP79 needed & got support by AE.

ITDM (K. Wrona)

  • DAQ for the tunnels is setup. ==> XGM-run control for the tunnel is to be tried.
  • Slow data: It is an issue how and how fast to store slow data (lots of properties which do not change).

Software

  • FXE:
    • Still daily meetings, prepare LPD & Gotthard
    • Working on GreatEyes, too
  • SPB
    • Configure slow-data cameras
    • Laser project is running in CAS
  • SASE3:
    • C. Youngman is the CAS-responsible, should collect requirements to compile master equipment list for SASE3 ==> to be compared against MEL SASE1 to identify additional work required.
  • SASE1:
    • Loops & Karabo will be updated together.

October Shutdown:

  • SASE1
    • No major items here currently, focus is on SASE3 / XTD10.
  • SASE3
    • First priority is to get all items required for first lasing up & running ==> Vacuum system including anything up to the absorber.
    • CAS is starting to set up Karabo and all controls.
    • ITDM will also start to work, but does not require access to the tunnel.
    • C. Youngman to generate MEL from input from the groups ==> invites to a meeting if necessary.
    • Eplan for PES will not be available on time ==> has to be pumped in a provisional fashion.
Entry   Status and plans after 09:30 meeting, posted by Tobias Haas on 20 Sep 2017, 11:15 

General

  • First user experiments ended on Monday evening/Tuesday morning
  • They are considered a great success and overall the instruments worked better than expected
  • The S1S/S3R meeting on Friday happens at 13:00 this week due to SAC

SPB

  • Karabo is freezing up much less frequently than previously
  • The latency of data being available for online analysis seems to be increasing
  • Todos:
    • Update the laser loop (11) today
  • Please keep in mind that updating the PLC loops requires a lot of hand work from the instrument afterwards and should not be done during beam time

FXE

  • FXE was not represented
  • The parallel operation of Gotthard and LPD was discussed. This is currently not possible. But this restriction was put deliberatly in order not to compromise LPD operation. It can be lifted whenever requested. However, the incoming user group will only need LPD. Hence this should be postponed for one week

AE

  • Preparations are ongoing for work on SASE3 tunnel during October shutdown
  • Prepartions are on done to connect the EPS in SPB to the DESY MPS system

CAS

  • The second stage of the SPB-CAS and SPB-FXE projects has been started
  • They include additional functionality that is required for user operation in November and also for the operation with the optical laser
  • The next Karabo release is being prepared
  • Next thing on the list is to implement the slow data acquisition for the tunnels
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 18 Sep 2017, 17:39 

Dear all,

XTD9 will be accessible tomorrow until the afternoon, but access should be communicated to M. Dommach, H. Sinn and T. Tschentscher. Martin will organize a search team for the afternoon.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 15 Sep 2017, 11:58 

General

  • User run is currently going well. Thanks to everybody!
  • Preparations need to be made for the October shutdown. Information will be collected by PSPO and T. Tschentscher. Care must be taken that the relevant people are available. Priority will be given to XTD10!

Short Report from SASE1 Instruments

  • ​SPB: 
    • First user shift last night
    • No hickup from accelerator
    • Focus is still too large (12 - 15 um) and beam pointing and beam position are unstable
    • Calibrations were done with AGIPD using powder. 
    • DAQ ran stably
  • FXE:
    • No report as FXE is currently on shift

Tunnels

  • Optics:
    • ​Reminder: The last two metal valves in the FXE and SPB beam lines are currently not in the interlock. Hence the beam could hit them if no attention is paid. This has been fixed in the firmware but will only become active after the next reboot. This will not happen before October
    • Switching between instruments is done using a macro by Harald. It worked without hickups so far. Nevertheless, one should attenuate the beam before moving the mirrors
    • It is important to put relevant info into the operations log book. In particular since all the user log books are closed
  • Diagnostics:
    • XGM data is now available both via DOOCS and Karabo and can be put into the DAQ stream. However, this data needs to be included. This has not been done so far
    • The XGM data should also be stored for the purpose of optimizing the facility. However, if stored with the user data, access will be difficult
    • Parallel storing of XGM and user data is not possilble currently

Laser

  • Work is still progressing in line with laser delivery in November. However, the time is getting tight and overtime requests have been filed for the whole group
  • Drifts of the laser beam are being observed that do not correlate with temperature and humidity. A feed back is being worked on
  • A fix has been prepared by CAS for the motor problem reported earlier. However, due to the high work load from user operation this could not be tested yet. It is scheduled for next week
  • DOOCSGATE was updated to allow adjustment of synchronisation

Detectors

  • AGIPD:
    • DAQ ran stably 
    • Users took calibration data last night that allows to calibrate the different gain stages
    • A. Mancuso showed nice data on his laptop with very clean rings from the glas in the beam
  • LPD
    • Not used yesterday
    • Should take data today
    • The calibration pipeline on the Maxwell Cluster is now enabled allowing calibrations to be calculated for both detectors

Electronics

  • All instruments loops were updated before the user experiments for DAQ and for failsafe operation with train id injection
  • Additional signals were prepared for the MPS system (Vacuum ok, end switches, pulse picker beam pattern). This is not yet integrated
  • ZZ happened last Tuesday in XTD2 for CRL and MCP. On CRL significant problems with the cabling were identified (wrong connections, sparks in connectors). The sparks are probably the reason for the broken Beckhoff terminals. Fix can only be done in October
  • In October the remaining tunnel loops with also be updated

Software

  • 90% of personnel is currently working supporting the user operation in SASE1
  • A hot fix for the data logger was deployed. 
  • Instrument user shifts will be supported by 2 CAS people at least until end of next week. 
  • Remaining personnel will work on the backlog, e. g. fixing the motor problems in the laser
  • FXE:
    • DAQ for Gotthardt was deployed yesterday
    • Scantool was updated
    • Work continues on the GreatEyes detector. Currently it only works in Win7 and not in LINUX
  • SPB
    • Doocs bridge is operational and slow data can be recorded, e. g. e-beam energy, K param
    • Users also made first use of the ZeroMQ tool 
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 15 Sep 2017, 10:12 

General

  • User run is currently going well. Thanks to everybody!
  • Preparations need to be made for the October shutdown. Information will be collected by PSPO and T. Tschentscher. Care must be taken that the relevant people are available. Priority will be given to XTD10!

Short Report from SASE1 Instruments

  • ​SPB: 
    • First user shift last night
    • No hickup from accelerator
    • Focus is still too large (12 - 15 um) and beam pointing and beam position are unstable
    • Calibrations were done with AGIPD using powder. 
    • DAQ ran stably
  • FXE:
    • No report as FXE is currently on shift

Tunnels

  • Optics:
    • ​Reminder: The last two metal valves in the FXE and SPB beam lines are currently not in the interlock. Hence the beam could hit them if no attention is paid. This has been fixed in the firmware but will only become active after the next reboot. This will not happen before October
    • Switching between instruments is done using a macro by Harald. It worked without hickups so far. Nevertheless, one should attenuate the beam before moving the mirrors
    • It is important to put relevant info into the operations log book. In particular since all the user log books are closed
  • Diagnostics:
    • XGM data is now available both via DOOCS and Karabo and can be put into the DAQ stream. However, this data needs to be included. This has not been done so far
    • The XGM data should also be stored for the purpose of optimizing the facility. However, if stored with the user data, access will be difficult
    • Parallel storing of XGM and user data is not possilble currently

Laser

  • Work is still progressing in line with laser delivery in November. However, the time is getting tight and overtime requests have been filed for the whole group
  • Drifts of the laser beam are being observed that do not correlate with temperature and humidity. A feed back is being worked on
  • A fix has been prepared by CAS for the motor problem reported earlier. However, due to the high work load from user operation this could not be tested yet. It is scheduled for next week
  • DOOCSGATE was updated to allow adjustment of synchronisation

Detectors

  • AGIPD:
    • DAQ ran stably 
    • Users took calibration data last night that allows to calibrate the different gain stages
    • A. Mancuso showed nice data on his laptop with very clean rings from the glas in the beam
  • LPD
    • Not used yesterday
    • Should take data today
    • The calibration pipeline on the Maxwell Cluster is now enabled allowing calibrations to be calculated for both detectors

Electronics

  • All instruments loops were updated before the user experiments for DAQ and for failsafe operation with train id injection
  • Additional signals were prepared for the MPS system (Vacuum ok, end switches, pulse picker beam pattern). This is not yet integrated
  • ZZ happened last Tuesday in XTD2 for CRL and MCP. On CRL significant problems with the cabling were identified (wrong connections, sparks in connectors). The sparks are probably the reason for the broken Beckhoff terminals. Fix can only be done in October
  • In October the remaining tunnel loops with also be updated

Software

  • 90% of personnel is currently working supporting the user operation in SASE1
  • A hot fix for the data logger was deployed. 
  • Instrument user shifts will be supported by 2 CAS people at least until end of next week. 
  • Remaining personnel will work on the backlog, e. g. fixing the motor problems in the laser
  • FXE:
    • DAQ for Gotthardt was deployed yesterday
    • Scantool was updated
    • Work continues on the GreatEyes detector. Currently it only works in Win7 and not in LINUX
  • SPB
    • Doocs bridge is operational and slow data can be recorded, e. g. e-beam energy, K param
    • Users also made first use of the ZeroMQ tool 
Entry   TAS updated, posted by Gerd Wellenreuther on 11 Sep 2017, 14:04 

Dear all,

I updated the tunnel access schedule to reflect the access to the XTDs tomorrow.

Cheers, Gerd

Entry   TAS updated, posted by Gerd Wellenreuther on 11 Sep 2017, 14:03 

Dear all,

I updated the tunnel access schedule to reflect the access to the XTDs tomorrow.

Cheers, Gerd

Entry   Status and plans after 09:30 meeting, posted by Tobias Haas on 11 Sep 2017, 10:32 

General

  • ​More or less continuous beam delivery over the weekend
  • Beam was lost 2 times. Took almost 2h to recover in the second case
  • The stability of the machine was poor. 
  • SPB cannot achieve a good focus and FXE reports sync problems as the timining jumps by 220ns (1 bucket) from train to train

SPB

  • Liquid jet could be operated with water for an entire shift
  • Images were acquired both with powder samples as well as with the water jet
  • A lot of flat field data was taken for AGIPD calibration
  • One camera had a problem and CAS was called in
  • There is unexpected behaviour with limit switches. Suspicion from CAS: A SW flag might be incorrectly set. A. Silenzi and B. Weinhausen will investigate)

FXE

  • As stated above, the timing jumps in machine operation render pump-probe experiments impossible. A way out might be 4.5MHz operation which has other issues
  • Need a lot more experience with the new scan tool
  • Request is made for training on the configurator tool: ITDM reports that they have set up a script to set the many parameters from stored values
  • There is a fundamental problem that the scan tools does not see some parameters available in DOOCs. Hence scanning is not really possible right now.

AE

  • There are at least two arms in the XTD2 CRL in error. This requires access. Possibly bundle with the ZZ request of W. Freund
  • Two loops in SPB still require update (loops5/12)
  • It is not clear why many configuration parameters have to be put back by hand after a loop update. N. Jardon and B. Weinhausen will check

ITDM

  • Many tests over the weekend for DAQ of slow data with SPB
  • Problems were observed because train IDs were zero
  • Also time stamps showed values of many hundred hours ago
  • CAS suspects that this might be due to wrong configuration of some devices (use_timeserver flag)
Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 08 Sep 2017, 13:47 

General

  • User operation starts on Thursday 14 September 08:00 in FXE
  • Instruments alternate every 12h switching at 0800 and 2000
  • A common SASE1 operations log book has been set up here. It is accessible for all inside XFEL
  • The PIs of the first 6 user groups have been informed that the scope of their experiments will be rather "user-assisted commissioning". In compensation they will get more beam time in March 2018 if the objectives of their proposals could not be reached

SPB

  • An effort was made with ACC to achieve good conditions for focussing. So far this has not been successful
  • At 2200 on thursday these efforts were abandoned as there were no more ideas to try
  • Also the power level in the beam was rather low
  • Negative effects of running the detector on KARABO responsiveness are much reduced now
  • This night KARABO froze up completely (no detector running) and no support from CAS was available (No response from calling the OCD mobile)

FXE

  • Cross calibration effort for the beam energy was performed with HIREX. This succeeded after some efforts.
  • The absolute energy scale could be established to within 70 eV. The fluctuations (averaged over several seconds) are around 20 eV
  • Effort to synchronize the tangerine laser beam and to bring it to the sample continues. The quality of the sync signal is not very good. There are big signal losses in the fiber

Laser

  • Still two problems with KARABO: Cannot reliably read date from wave guides and the python to doocs interfaces does not implement essential data types
  • Currently working on aligning the NOPA
  • The fact that the synch signal will not be available until end Sept puts a strain on the planned dates for beam delivery
  • The full SYNC hutch will not be available until end Dec

Detectors

  • The new GUI version gives good response while detector is running
  • SPB was instructed on how to use the offline calibration
  • LPD was brought into  the SASE1 broker topic
  • Coolant leak in LPD was fixed but 1 super module had to be removed

Electronics

  • A failsafe mechanism has been implemented in the firmware framework that allows the PLCs to continue running even if train ids should not be available from the timing system
  • This requires an upgrade of all loops. 
  • One encoder problem in SPB was identified as a problem with the cable
  • One motor problem in SPB (injector y motion) is suspected to be a faulty terminal. The motor was moved to a test crate where it works fine. This can stay like this for the moment

CAS

  • KARABO 2.1.16 was released. This release is not mandatory but recommended
  • Work is ongoing on the DOOCS bridge
  • XGM data is availalble now but requires a check by J. Grünert
  • Work continues on the Gotthardt and GreatEyes detectors
  • In the case of GreatEyes the vendor has been contacted and the reply is being awaited
  • Good progress was made with data analysis on the ONDA cluster

ITDM

  • Accounts for users are prepared. 
  • Maxwell cluster is ready for offline analysis. Example files and programs are available
  • Several PCs in XHQ have been set up that have direct access to the control network
  • These PCs are only for monitoring experiment activities. They are not for general use and are not connected to the internet.

 

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 08 Sep 2017, 11:55 

Dear all,

I updated the TAS to incorporate the newest dates for the October shutdown (currently 4.10.-23.10.):

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status after 0930 meeting, posted by Tobias Haas on 06 Sep 2017, 11:04 

FXE

  • Still working on getting the laser on the sample
  • Commissioning the recently received intensity monitor
  • Work is also ongoing on the Gotthardt detector
  • LPD is still in its own "Topic" but will be moved to the SASE1 "Topic" today

SPB

  • Problem developed with one ELMO motor. It was moved to a test crate where it worked
  • All loops were updated to allow slow data integration into DAQ
  • AGIPD running improved significantly in stability after implementing the latest nightly build of KARABO
  • ITDM team has various testing tools operational on the different channels of the detector
  • Charge injection scan was possible for the first time without significant degradation of KARABO response

ITDM

  • Slow data is now integrated for SPB
  • Request is made for the list of data sources to integrate with FXE

AE

  • PG points out that it was always foreseen that the timestamp/train ID integration would be done in software
  • A HW solution was implemented during his absence to generate train IDs in a  PLC. He considers this to add significant risks.
  • The HW solution will not be implemented in the tunnels to avoid unexpected behaviour during the user run
  • Hence a work around solution needs to be found how to uniquely identify slow tunnel data with train IDs

Discussion about time stamps and train ID

  • The summary of a longer discussion about the subject leads to the following conclusions:
  • Slow tunnel data could be logged via a python script that also stores time stamps and train ids. An integration of this data with the fast data would have to be done offline post mortem
  • Different opinions exist whether the association between time stamps and train ids in the KARABO data logger is unique and compatible with the train ids used in DAQ
  • It is decided that this will be checked now and the result reported during the Friday S1R meeting

Announcement by ITDM

  • The elog will be upgraded this afternoon
  • The online cluster servers will be rebooted this afternoon
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 04 Sep 2017, 17:33 

Dear all,

I have updated the TAS with the most recent information about Tuesday and Wednesday this week:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status after 0930 meeting, posted by Tobias Haas on 04 Sep 2017, 10:39 

SPB

  • Demo experiment done last week
  • Flat fields taken with AGIPD over the weekend
  • Focus was re-characterised. This required modifications to several beam parameters and then led to a controversial discussion with the RunCoor
  • The sluggish behaviour of the GUI remains an issue and might pose a real risk if the injector freezes up and direct reflections into the detector occur
    • Kerstin and Gero looked at it last week
    • John is back from holidays and will also look
    • One observation is that the same information may update quickly on one server but not on another
  • One motor is stuck in XTD9. A temporary access is requested
  • On Sunday at beam hand over the CRL in XTD2 was not fully retracted. This was then done unannounced. Nothing bad happened this time but  this might cause real damage. 

FXE

  • on shift and not represented at the meeting
  • Harald mentions that 2 motors in the XTD2 CRL are stuck/in error. This should be fixed during this week's repair period
  • Info by CB after the meeting: Scanned K_\beta and established machine energy scale within 40 eV

Tunnels

  • Motion loop and SPB loop to be updated by AE tomorrow
  • Tunnels and instruments are in different KARABO "Topics". K. Wrona states that this is a problem for DAQ
  • SPB states that they have all information required already in their "Topic"
  • It is unclear whether this might be an issue for FXE

CAS

  • No specific issue
    Reply   Status after 0930 meeting, posted by Tobias Haas on 04 Sep 2017, 12:03 

Just to clarify:

  • Tunnel and SPB are in different Karabo Topics. It should not be a problem since we agreed that SPB does not need XTD2 slow data (from devices)
  • Tunnel and FXE are in the same Karabo Topic
  • We will keep prioritizing the configuration and deploy of Karabo-DAQ in SPB and FXE. Before going for Tunnel updates (we are mitigating risks of broadcast unknown issues just before the 1st User Experiments).  
Tobias Haas wrote:

SPB

  • Demo experiment done last week
  • Flat fields taken with AGIPD over the weekend
  • Focus was re-characterised. This required modifications to several beam parameters and then led to a controversial discussion with the RunCoor
  • The sluggish behaviour of the GUI remains an issue and might pose a real risk if the injector freezes up and direct reflections into the detector occur
    • Kerstin and Gero looked at it last week
    • John is back from holidays and will also look
    • One observation is that the same information may update quickly on one server but not on another
  • One motor is stuck in XTD9. A temporary access is requested
  • On Sunday at beam hand over the CRL in XTD2 was not fully retracted. This was then done unannounced. Nothing bad happened this time but  this might cause real damage. 

FXE

  • on shift and not represented at the meeting
  • Harald mentions that 2 motors in the XTD2 CRL are stuck/in error. This should be fixed during this week's repair period
  • Info by CB after the meeting: Scanned K_\beta and established machine energy scale within 40 eV

Tunnels

  • Motion loop and SPB loop to be updated by AE tomorrow
  • Tunnels and instruments are in different KARABO "Topics". K. Wrona states that this is a problem for DAQ
  • SPB states that they have all information required already in their "Topic"
  • It is unclear whether this might be an issue for FXE

CAS

  • No specific issue

 

Entry   WP74 - OCD contacts for this weekend, posted by Jan Grünert on 01 Sep 2017, 20:14 

02.09. from 08:00 until 03.09. 08:00 - Wolfgang Freund 9-5630  

03.09. from 08:00 until 04.09. 08:00 - Florian Dietrich 9-6968

Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 01 Sep 2017, 10:34 

General:

  • The length of the shut down in October is still under discussion. Currently it appears that it is shortenend to 8 working days
  • The management reviewed the readiness of the instruments for first users on 14 September:
    • Very good progress was made over the last weeks
    • Data was taken with both large pixel detectors
    • A few "red lights" remain
    • In spite of the remaining difficulties, the first users will be invited
    • However, the Management shall inform the first users that they will get another beam time in March in case the experiment objectives cannot be reached
  • The second  call for proposal will only cover 5 weeks in May/June
  • The third call will start on 6 September for all 6 instruments

FXE

  • van Hamos was aligned for the Cu K_\beta line (required for the 3rd exp)
  • XRay emission was observed on the GreatEyes detector
  • Work is still urgently needed to get the Gotthardt Detector working 
  • The laser is synchronised to 100fs. It is currently up to the shutter in the instrument hutch

SPB

  • On Monday AGIPD took first data  with 30 frames 
  • The sample jet is working with sufficient vacuum to operate the detector
  • Yesterday, everything was ready to take data with liquid jet and AGIPD. Unfortunately, there was a major software/electronics failure that lasted for 6.5h
    • A fuse was blown in one crate needed for the train IDs (single point of failure)
    • This affected all crates and KARABO
    • A fallback is currently being implemented
  • The door interlock could not be operated because there was a problem with the operator password

Tunnel

  • SASE3 tunnel installation will not be reviewed because there is no work on it
  • SASE2 tunnel installations will be reviewed once AE and CAS get involved.
  • Network installations may take up to 4 months (info by K. Wrona)
  • First signals were seen from HIREX last week
  • Currently this integrates over 30 bunches as Gotthardt is not available

Laser

  • Differently from what was reported earlier, the AC system works at the required lower flow rates
  • Progress on laser installation and commissioning is progressing as planned
  • There are a few problems with motor operations from KARABO

Detectors

  • Both AGIPD and LPD are taking uncalibrated data
  • A cooling leak was detected in LPD. Experts from RAL are going to look at this today
  • Calibration may just be achieved for AGIPD. Probably not for LPD due tot the HW problems

AE

  • All SPB loops were updated to accommodate the train ids
  • Almost all FXE loops were updated too
  • The tunnel loops were not updated yet. 
  • For the tunnel, the motion loop needs to be updated. EPS and Vacuum loops should remain unchanged
  • There remains one open issue with an encoder on the sample injector. X and Y encoders will be exchanged today to isolate the problem

CAS

  • Work this week concentrated on GUI issues (achieve faster feedback)
  • One patch was released to fix GUI problems
  • Good progress was made with data analysis tests together with people from CFEL
  • Next important topic on the list is to get the XGM data into the KARABO DAQ stream. This requires the DOOCS interface
  • KARABO 2.1.16 needs to be closed
  • For FXE there is good progress with Gotthardt. This now needs testing in the hutch. The same applies to the digitizers.
  • W. Wrona points out that independent KARABO installations exist for SPB, FXE and tunnels. This needs to be fixed to allow DAQ integration.

 

Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Monica Aresté on 30 Aug 2017, 09:53 

Electronics

  • Currently work continues on the SPB SmarACT stages, this issue progress slowly since right now it is not possible to reproduce the error.
  • SPB loops 1/2/3/4/12 already updated, they will continue with the update of loops 5/7/13 today.
  • Update on FXE loops will be the next.
  • It is suggested to update also the loops in XTD9.
  • AE report a request from J. Grunert to work in the HYREX. So far first priority is to work in the Experiments, this issue will be on hold.

CAS

  • CAS has been working in the last days to solve the problems with the DAQ integration. Main showstopper now is the update of the Beckhoff loops.
  • Still working to fix some minor issues for SPB.

Tunnels

  • There is a problem in the HYREX photonic camera, CAS has been investigating but is not a KARABO issue.
Entry   TAS updated, posted by Gerd Wellenreuther on 28 Aug 2017, 16:00 

Dear all,

I updated the tunnel access schedule - as you can see there will be no access tomorrow. Any access requests regarding next weeks Tuesday as usual to M. Dommach, cc to Harald Sinn and T. Tschentscher.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 25 Aug 2017, 13:42 

General

  • T. Haas conveys the congratulations of the management
    • for the achievements in installing and commissioning the AGIPD in SPB
    • for the progress made with installations in XTD10/SASE3
  • There will be a meeting next week in order to determine whether we are ready for "Early User Experiments" in SASE1.  
  • A discussion on what needs to be prepared for this meeting followed with the following conclusions
    • The term "Early User Experiments" needs further qualification in order to establish a well defined scope
    • Instruments and support groups (SPB, FXE, AE, CAS, ITDM, Detectors) should prepare a table with their list of deliverables and the corresponding status, following the model presented by CAS in the talk by H. Santos last week
    • In the wake of the meeting it needs to be communicated to the first scheduled groups what boundary conditions they will most likely encounter

FXE

  • The optical signal for laser synchronisation is still missing and not likely to arrive before next week
  • Hence a pump-probe experiment cannot happen before the scheduled "Readiness Meeting" as there will also be no beam on Tuesday and Wednesday
  • It will be difficult to answer the question whether a pump-probe experiment is possible
  • JJ was here this week and installed the intensity monitor

SPB

  • Big gate valve between AGIPD and sample chamber was opened for the first time 10 mins ago
  • The liquid jet is running and the differential pumping is working so that proper vacuuum can be maintained
  • Issues remain with the SmarACT stages. Resets are needed at short invervals
  • Availability of "slow" data in the DAQ chain remains the hot topic

Tunnel Installations

  • Work in XTD10 continued through Monday morning
  • Ion pumps and valves are now connected to the PLC. 
  • KARABO control has to wait for CAS resources

Laser

  • Issues remain with AC system.
  • The flow rates are way to high and it appears that the system was designed for much higher flows than needed
  • Weiss Klimatechnik is coming on Monday for a discussion
  • Otherwise, installation proceeds and is still on track for laser beam delivery in October

Detectors

  • A lot of progress was made with the detectors
  • However, time is still needed to take calibration data. This is estimated as one day without beam per detector
  • A reduced rates both detectors can run in parallel for tests. This is not possible for the calibration

Electronics

  • The encoder bug reported on Wednesday was found and consequently all loops were updated
  • Currently work continues on the SPB SmarACT stages
  • The interface to the MPS system still needs to be set up. This requires an interrupt and testing

CAS

  • Several unexpected issues were found in the most recent KARABO release, e. g. there are problems with the time server that still prevent DAQ integration of the slow data
  • This takes a lot of additional time
  • A plan review has now been agreed with both instruments once per week
  • A survey was made on the need for specific DOOCS devices
Entry   Status and Schedule after 09:30 meeting, posted by Tobias Haas on 23 Aug 2017, 10:20 

CAS

  • Finishing tests for KARABO 2.1.15. Deployment should start today during the middle of the day for SPB
  • SPB asks for additional slow data to be included in the DAQ. This requires tests after 2.1.15 is deployed
  • For the moment 2.1.15 will only be deployed for SPB. Once it is installed on all control servers, switch from 2.1.13 can take place
  • The switch can be reversed in case of problems
  • AGIPD control server will remain on current software version for the moment

FXE

  • FXE was unfortunately not represented
  • AE needs to perform updates on loops 9 and 7 

Tunnels

  • Beam should be coming back today
  • XTD9 will be searched today at 1400
  • In XTD10 7/10 imagers were succefully tested and integrated. The rest will have to be done in October

AE

  • Need to test one motor for SPB/CSS
  • Yesterday 4 encoders in SPB were fixed but one additional problem was identified with the microscope stage in the sample chamber`
  • N. Jardon needs to do further updates of PLC loops for SPB. This will be done after KARABO has been upgraded, probably tomorrow

CAS

  • KARABO 2.1.15 should contain crucial fixes to associate data from tunnel devices with detector images
  • Initially this will be possible train-by-train
  • Pulse-by-pulse association, e. g. as needed for XGM, will require further work
Entry   Karabo 2.1.15 in Test , posted by Hugo Silva Santos on 22 Aug 2017, 10:53 

Dear All,

I would like to report that we started today to test (internally in CAS) the Karabo 2.1.15 version.

We got delayed to prioritise and solve a showstopper issue related to GUI Client. If our tests succeed, we are foreseeing to finish the tests and release tomorrow.

Best,

Hugo

Entry   Karabo down in tunnel, posted by Hugo Silva Santos on 22 Aug 2017, 09:48 

Dear All,

We have a issue on the control servers and we are already working on it...

Best,

Hugo

    Reply   Karabo down in tunnel, posted by Hugo Silva Santos on 22 Aug 2017, 10:24 

Dear All,

We solved the incident and the services are running normally. We are still try to investigate, as far as we know we have some "zumbies" process running in the GUI servers and it was not consuming the HEATBEATs.

Hugo Silva Santos wrote:

Dear All,

We have a issue on the control servers and we are already working on it...

Best,

Hugo

 

Entry   Status and Schedule after 09:30 meeting, posted by Tobias Haas on 21 Aug 2017, 16:26 

General

  • Access to tunnel XTD10 ends today around midday and beam is expected back for the instruments on Thursday

SPB

  • Good progress was made over the weekend with AGIPD. On Saturday first dark images were recorded
  • Today the detector hybrids are being exchanged (1.0 -> 1.1)
  • The injector motion system was taken into operation
  • The SmarACT stages can currently not be tested since some parts are disassembled for final AGIPD installation

FXE

  • Some loose ends were tied up for LPD
  • JJXray was here last week and did some more installations, e. g. I0 monitors and alignment of the sample stack
  • This week Gotthard integration will proceed

Tunnels

  • The vacuum loop is now running for XTD10 with the full design firmware
  • Approximately 40 ion pumps were locally test and are no under PLC control
  • Almost all valves were locally tested and are also under PLC control
  • XGM is connected to its own PLC currently (integrating Vacuum and gas supply)

CAS

  • A disucssion on the details of Gotthard integration will happen with FXE after this meeting
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Aug 2017, 16:13 

Dear all,

I updated the tunnel access schedule with the most recent information provided by M. Dommach and H. Sinn. If you plan any works in the tunnels please check their availability on

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 18 Aug 2017, 11:23 Readiness.pdf

Software:

  • CAS meets with SPB and FXE on a daily basis to fine tune progression towards user operation
  • A list of required deliverables for user operation has been agreed between CAS and SPB/FXE (see slide 5 in presentation by H. Santos attached to these minutes)
  • The list has been associated with Karabo releases and dates
  • These dates and respective progress needs to be monitored continuously as the schedule is very tight

SPB

  • AGIPD installation is progressing according to plan. 
  • Next steps are data taking and then the exchange of the detector modules by the consortium
  • SmarACT stages in the sample chamber started working yesterday but it is not understood why they are working now while they were not working before

FXE

  • Work continues on van Hamos integrations
  • Next step is integration with the Tangerine laser

Tunnel Installations

  • This week the focus was on SASE3 installation in XTD10
  • The vacuum group closed almost all gaps
  • A lot of cabling was completed
  • Local tests together with AE are being carried out on the vacuum components
  • MCP was delivered with too short bellows so this could not be connected
  • XGM is connected on one side only
  • The Diagnostics group brought PES into the tunnel
  • 5/10 imagers are operational. 2 more are almost done

Laser

  • Work is back on track after the cooling water incident 10 days ago
  • AC controls are ok but the air flow is too high for laser operation

Electronics

  • A lot of progress was made in the course of AGIPD integration in SPB (Chiller working, Gate Valve working. interlocks working and tested)
  • A smaller effort was done for FXE (Some support for LPD and re-integration of van Hamos)
  • Tests of the vacuum components in XTD10 are still ongoing and continue through Monday morning
  • A new email with associated ticketing has been set up: ae-support@xfel.eu

 

Entry   Office network in XTD10, posted by Krzysztof Wrona on 17 Aug 2017, 07:59 

Dear All,

In XTD10 there are now office network ports available in each rack. These can be used to connect your regular laptops with a network cable without special configuration and registration of your laptop.

The list of racks and corresponding port numbers is listed below. Please, note that in lead racks (3.4, 3.7, and 3.13) you need to plug the cable directly to the office switch port 24. This port is located in the bottom row, most to the right.

Rack3.1        

116.732

Rack3.2        

116.741

Rack3.3        

116.755

Rack3.4        

switch: SW-HH-AL-285 port: 24(last, bottom row)

Rack3.5        

116.762

Rack3.6        

116.877

Rack3.7

switch: SW-HH-AL-286 port 24 (last, bottom row)

Rack3.8        

116.885

Rack3.9        

116.891

Rack3.10

116.895

Rack3.11

116.903

Rack3.12

116.909

Rack3.13

Switch SW-HH-AL-287 port 24 (last, bottom row)

Rack3.14

117.021

Rack3.15

117.032

 

Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 11 Aug 2017, 10:07 

General

  • The focus of activities next week for the AE and vacuum groups is on getting as much done in XTD10 as possible. There is a conflict with the aim to bring AGIPD to SPB and start commissioning. A lot of preparatory work was done for the latter this week already. Nevertheless this conflict needs to be monitored carefully. There will be a daily stand up meeting at 11:30 in front of the MCR to monitor the ongoing work. The SASE1 displatch meetings on Monday and Wednesday at 09:30 are correspondingly cancelled

FXE

  • Philipp Lang reported on the status of the LPD commissioning. The detector is essentially ready to take data with 14 out of 16 super modules on the weekend. A few software issues remain but should not stop the activities.
  • FXE is working on commissioning their greateyes camera 
  • Loop 7 needed to be re-worked for the van Hamos spectrometer
  • Work is stil required for the Alio stage in the monochromater in XTD9. This will probably not be ready for first user operation.
  • During the shutdown week work will focus on getting the instrument laser hutch going with the Tangerine laser. After the XFEL beam is back, first pump-probe experiments should be possible
  • This afternoon radiation safety tests with 30 bunches and different materials shall take place

SPB

  • One SmarACT motor is now running. The problem was identified as a combination of a connection and a Karabo issue
  • The next step is to reconnect the remaining motors correctly and then all SmarACT motors should be operational (The firmware is set up for all)
  • Updates need to be done for loop 5 (AGIPD chiller) and loop 7 (interlock). Since this can only be done after 1500 once the sample chamber is vented, this work was postponed to Monday
  • SPB also provided an updated priority list to AE in order to fine tune the remaining work until user operation 

Detectors

  • Moving AGIPD will start early on Monday and the detector shall arrive in SPB around lunch time
  • Immediate works shall be mechanical, connection of vacuum, chillers, power and cooling. 
  • A. Sztuk points out that the integration plan from SPB is very optimistic

Tunnels

  • The goal of next week is to get the vacuum and the imagers into the PLC and eventually KARABO controls
  • Detailed schedule planning was unfortunately stopped yesterday due to the fire next door but will be done today
  • There is a scheduled power outage next week in the tunnels. Here is the respective email with information.
  • The problem with the fast valves in SASE1 (spurious trips of the interlock) has not re-occured after the controllers were exchanged. They have been sent to the manufacturer

Laser

  • Progress was set back last week due to un-announced work on the 11 C cooling circuit. This necessitated a re-alignment of the lasers
  • Otherwise commissioning work in SASE1 is progressing

Electronics

  • The points discussed are included with the affected groups

Software

  • The storage for images from the cameras in the tunnels was changed due to a disk space crisis. Currently 150TB are available. This should be enough for some time
  • CAS support for XTD10 work is need only after Thursday next week once the PLC work is done
  • Karabo 2.1.14 was released. Currently 2.1.13 is deployed.
  • Currently the data from LPD cannot be archived. Work on this topic was stopped yesterday due to the fire. Should happend today
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 09 Aug 2017, 10:23 

General

  • Main focus for Vacuum Group and AE next week will be to get as much done in XTD10/SASE3 as possible. Conflicts with activities in SASE1 need to be carefully monitored

SPB

  • SMARAGD motors are still not working even though one of them worked once. Mahadi/AE is focussing on this problem. It should be solved asap
  • Focus should be on loops 11 and 13. Loop 8 has lower priority at the moment. Loop 11 is urgently needed for the laser

  • A vacuum event occured last night. Currently some parts of the instrument vacuum are at 10-3 mbar.

Tunnels

  • There is an issue with disk quotas for storing camera images. This is due to the fact that the DAQ system is not implemented for the tunnel components and an interim solution is being used.
  • The focus of the DAQ activities is on AGIPD and LPD

DAQ Tests

  • Tests with LPD achieved recording 10000 trains. Performance is still limited when many images (>300) are being stored per train. 
  • Currently data is not yet stored on gpfs but recorded on disks locally
Entry   KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 15:25 

The system is up and running.

Regards,

Wajid 

Entry   KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 13:10 

As previously announced we will deploy KARABO 2.1.13 in tunnel under topic SA1. The system will go down in 10 mins. I will announce it again as soon the system is up again.

Regards,

Wajid Ehsan

Entry   Radiaiton Measurements Complete for SASE 1, posted by Eric Boyd on 07 Aug 2017, 18:30 

Radiaiton Measurements are complete for SASE 1 Normal access is restored.

 

Entry   Status after 9:30 disptach meeting, posted by Monica Aresté on 07 Aug 2017, 12:45 

General

  • The Radiation measurement test will be postponed until the beam reach the 30 bunches.

 

SPB

  • Problem with Smaract motors has been identified. Loop 12 updated and working fine.

  • SPB working to focus the CRL, it works but beam is not stable.

  • Vacuum interlock for Loop 5 (AGIPD) is being implemented. Interlock definitions for AGIPD under discussion with AE, this is still on going.

  • Export for Loop13 updated due to a reorganizattion of the modules into the rack. Firmware will follow.

  • Export for Loop 8 still missing.

Tunnels

  • Images are displayed later, this issue was discussed off-line with CAS. This issue has been fixed for one camera and it works, now will be deployed for the rest. Will be necessary 15min. of downtime to deploy, CAS to coordinate with Control room.

AE

  • SPB Loop 5 thre are some issues with Julabo Chiller, AE contacted the manufacturer for information, still working on this.

  • SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. Change request submitted  to swap module positions. 

  • Loop 8 should be the next, EET  to clarify if the export is done and provide to AE.

  • AE ask to define priorities for next week since they will have to work in SASE3 tunnels but threre are still many issues form SASE1 on going (Firmware, AGIPD..).

CAS

  • 2.1.13 Karabo version update is being agreed with the interested parties. Implementation will be next Tuesday 8.08.2017 in the afernoon. It takes approx. 3 hrs. 

Entry   Time Schedule change in Radiation Measurements for Monday, posted by Eric Boyd on 04 Aug 2017, 15:24 

Dear All,

We have just changed the time that the Radiation Protection Measurements will take place on Monday. This will now begin at 15:00. The time has been pushed back so that the DESY Radiation Protection group will be able to also be there.

I will inform you if anything changes.

Entry   Radiation Measurements of FXE Monday 07.08, posted by Eric Boyd on 04 Aug 2017, 13:41 Restricted_areas_for_FXE_EXP_measurments.pptx

The control room thinks that they will be able to very easily provide us the desired parameters for commissioning  the FXE EXP Hutch this coming Monday. If that is the case we will be restricting access in SASE 1 in accordance to the attached presentation from 8:00 am until completion of the radiation measurements. A SASE 1 log book entry will be made when restrictions go into effect and are lifted.

We should find out Sunday evening from the control room if they don't think they can provide us with the proper parameters. If this happens I will send out an email informing you that the measurements have been canceled.  If you don't receive an email from me Sunday evening, assume that the measurements will be taking place beginning at 8:00 on Monday morning and will be in effect for most of the day.

Sorry for the short notice.

Entry   No Radiation Measurements in SASE 1 This week, posted by Eric Boyd on 03 Aug 2017, 10:52 

Do to repairs that need to be made with the cold compressor. We will be unable to perform Radiation Hutch Commissioning for SASE 1 this week. We will attempt to reschedule the Measurments for Thursday or Friday (10.08 or 11.08) of next week, depending on if it can be coordinated with all involved parties.

There is no restricted access to SASE 1 until then.

Entry   Status after 9:30 dispatch Meeting, posted by Monica Aresté on 02 Aug 2017, 10:17 

General

  • This Thursday the radiation test in D.05 (FXE) will be performed (from approximately 0900 to 1500), access to all areas adjacent to the hutch is only allowed by those that are assisting with the measurements.

  • Meeting on Friday is cancelled. We will meet again on Monday 7-08-2017.

FXE

  • Gotthard detectors to be tested in Karabo. On going.
  • Finished commissioning of OGT2_CRL and OGT1_ATT. The laser to be used in September installed and connected to electronics.

SPB

  • Problem with Smaract motors has been identified. Loop 12 updated, full test still on going.

  • Cameras trigger for the sample environment is now working. Software issues, CAS is addressing that. 

  • Vacuum interlock for Loop 5 (AGIPD) is being implemented. Interlock definitions for AGIPD under discussion with AE to continue work on this loop.

  • Working in the commissioning of Loop13.

Tunnels

  • In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.

  • Two issues with photonic cameras already solved by CAS.

  • Images are displayed later, this issue will be discussed off-line with CAS.

AE

  • FXE Interlock definitions have been changed and this reflects in the update of loop 1 and 2. Done.

  • Working on Alio Stages integration for Mono in the tunnel. Developing. 

  • SPB Loop 12 – Smaract motors and ELMO controllers implementation done.

  • SPB Loop 5 thre are some issues with Julabo Chiller, AE contacted the manufacturer for information.

  • SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. Change request submitted  to swap module postions. 

  • Cables for interface to Person Interlock laid. Connections to the MPS system to be done this week.

  • Loop 8 should be the next, EET  to clarify if the export is done and provide to AE.

DET

  • LPD – Synchronization is still showing problems, this is delaying the tests.

  • AGIPD – Detector being tested in Hera south. KWrona started the tests of DAQ, some minor issues arised but in general it works.

CAS

  • 2.1.13 Karabo version update is being agreed with the interested parties. Implementation will be next Tuesday 8.08.2017 in the afernoon. It takes approx. 3 hrs. 

  • CAS will send around a list with the tasks foreseen to be solved during the next weeks.

Entry   Status after 9.30 dispatch Meeting, posted by Adriano Violante on 31 Jul 2017, 11:58 

General

  • SRP was not able to measure any radiation even inside D.09 and D.02. This Thursday the radiation test in D.05 (FXE) will be performed. 

  • Tomorrow XTD9 open 7:00 ==>14:00

FXE

  • Gotthard detectors to be tested in Karabo

SPB

  • Problem with Smaract motors has been identified. Loop to be updated. 

  • Cameras trigger for the sample environment is now working. Software issues.  CAS is addressing that. 

  • Vacuum interlock for Loop 5 (AGIPD) is being implemented. There will be a meeting soon (today?) with AE to check the interlock definitions for AGIPD and continue work on this loop.

  • Focus characterization with CRLs ongoing. Beam size reached: <10 um

 

  • Tunnels

  • Fast valve fake triggering has not been reported in the last week end. 

  • In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.

  • Some problems with the cameras that stopped working have been reported by A. Koch. That could be just a matter of restarting the GUI. To be checked.

AE

  • FXE Interlock definitions have been changed and this reflects in the update of loop 1 and 2. Ongoing.

  • Working on Alio Stages integration for Mono in the tunnel. To start this week. 

  • SPB Loop 12 – Smaract motors and ELMO controllers implementation ongoing

  • SPB Loop 5 is up including the AGIPD related systems. AGIPD interlock will be added once low level tests done

  • SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. SPB wants to leave it and rather swap module positions and hand in a change request.

  • Cables for interface to Person Interlock laid. Connections to the MPS system to be done this week.

  • DET

  • LPD – Time server was set up. Images collected from 1 quadrant. Firmware upgrade for the other quadrants ongoing. 

  • AGIPD – Detector being tested in Hera south. KWrona will start the tests of DAQ in Hera today or tomorrow.

     

    CAS

  • 2.1.13 Karabo version update is being agreed with the interested parties. It takes approx. 1-3 hrs. 

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 30 Jul 2017, 23:04 

Dear all,

on Tuesday, XTD9 will be accessible from 7:00 - 14:00, due to requests by Naresh and Konrad. I updated the TAS:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 28 Jul 2017, 11:50 

General

  • The radiation test in SASE1 could not take place yesterday since the machine was not able to deliver proper light intensity with 30 bunches. Another tentative is happening now.

  • Instrument commissioning during the weekend

  • Monday - Wednesday next week will be machine development time. XTD 9 will be accessible on request. Please contact M. Dommach. XTD 10 is foreseen to be close.

     

    SPB

  • After tests Smaragd motors are not working. Under investigation with AE/CAS

  • Cameras trigger for the sample environment is not working. AE has been made aware of that during the meeting. Ongoing checks.

  • Vacuum interlock for Loop 5 (AGIPD) is being implemented. This has to be done before the detector installation (foreseen beginning of August).

  • Freezing and delays of the GUI are being experienced. CAS ticket has been sent. This has to be addressed as soon as possible in view of the instrument commissioning time during the week end.

     

    Tunnels

  • Fast valve fake triggering has not been solved. After tests the suspect was on the controller side. Controller has been replaced but the issue has not been completely fixed. Investigation ongoing. Valves are ACTIVE regardless.

  • In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.

  • XTD10 – progress in the last 2 days have been achieved concerning closing of vacuum gaps and leaks testing

  • XTD6 – Vacuum connections ongoing.

     

    AE

  • FXE Interlock deployed and under tests.

  • Working on Alio Stages integration for Mono in the tunnel. The goal is to have it ready by the end of August.

  • SPB Loop 12 – Smaragd motors and ELMO controllers implementation ongoing

  • SPB Loop 5 is up including the AGIPD related systems. AGIPD interlock will be added once low level tests done

  • SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. SPB wants to leave it and rather swap module positions and hand in a change request.

  • Cables for interface to Person Interlock laid. Connections to the MPS system to be done next week.

  • SASE3 Tunnel - Work started on PLC projects. There is the need for accurate schematics and a list of priorities in order to plan and prepare the shutdown week.

  • SASE3 Instruments – AE will start the installation of components ion the racks soon (Mid Aug. after network cables are finished in the PLC related racks).

  • General remark  - Do not leave cables in tunnels disconnected after having worked!

     

    DET

  • LPD – Trigger problems solved. DAQ tests to continue

  • AGIPD – Detector being tested in Hera south. As soon as the important issues concerning DAQ have been solved in Hera south (time allocated next week for that). The decision to move it to the SPB hutch can be taken. Schedule may be slightly affected, depending of the test results in HERA.

     

    CAS

  • 2.1.13 Karabo version has been presented yesterday

  • Scan tool measurement presentation today at the Mock-up control room

 

Next week NO SASE1/3 Readiness meeting!

Entry   No Restricted Areas for Radiation Commissioning, posted by Eric Boyd on 28 Jul 2017, 11:10 

Desired parameters where reached for radiation measurments of the SPB OPT and SPB EXP hutches. Radiaiton could not be detected inside the hutch with the beam shutters open and beam verified hitting the target, therefore it was not deemed necessary to take radiation measurments outside the hutches. As a result there are no additional access restrictions in SASE 1.

 

Entry   Restricted areas Durring Radiation Measurements of SASE 1, Friday 28.07, posted by Eric Boyd on 27 Jul 2017, 15:42 Restricted_areas_for_measurments.pptx

No radiation measurements have taken place today (27.07) due to insufficent energy of the machine. We think we can achive the desired energy by tomorrow morning at which time the SRP group will attemtp to commission both the SPB OPT and SPB EXP hutch. The attached presentation shows the new expected time schedule.

A log book entry will be made when area restriction goes into affect and when it is lifted.

Entry   Fast valves in XTD9, posted by Martin Dommach on 26 Jul 2017, 18:04 

Dear all,

the problem with the fast valves XTD9 tripping randomly is still not fully understood but we exchanged the controllers for both valves and they now seem to be stable. The valves are set back to active mode again with 1*10^-6 mbar trigger level while vacuum pressure at the sensors is around 1*10^-8 mbar.

In case one of the valves closes again in the next time you can do the following:
1. check the ion pump pressure in the beamline to make sure that it’s not a real event (they should be in 10^-8 mbar range or better)
2. If it’s not a real vacuum inrush you can open the valve by pressing “Open" button followed by the “Reset” button (SPB: Karabo scene SA1_XTD2_VAC/V11030F or for FXE: SA1_XTD2_VAC/V12030F )
3. Open the adjacent gate valves which were triggered by the vacuum interlock and continue with beam operation
4. Please inform the vacuum group (vacuum@xfel.eu)
 
If opening the valve again does not help because it trips to often, the fast valve can be disabled:
1. Open the valve by pressing “Open” button
2. When the valve is open again, switch off the high voltage of both sensors
3. Please inform the vacuum group (vacuum@xfel.eu)
 
Best regards,
Martin
Entry   SPB - Loop 5 is back online, posted by Bernard Baranasic on 26 Jul 2017, 14:10 

SPB Loop 5 is back online:

- but without crate BKF00095-SPB_IRU_CHL (there is missmatch of hardware and documentation (investigation is ongoin)),

- pumps: PUMP_TURBO4, PUMP_TURBO5, PUMP_TURBO8, PUMP_ROOT_1, PUMP_ROOT_2 ,PUMP_ROOT_3 and IRU_VAC/PUMP_ROOT_1  are without serial connection

Interlock is inlcuded and ready for testing.

 

Best Regards,

Bernard

Entry   Status after 9.30 Meeting, posted by Adriano Violante on 26 Jul 2017, 10:35 

General

  • Today the machine is being prepared to lase with 30 bunches in order to allow the radiation measurements in SASE1 Exp. Hall on Thursday and Friday.
  • Today GUI will be down for a couple of minutes at 11.30 to allow modifications of the servers for bugs fixing.
  • Specific SASE1 areas will be off limits during the test, scheduled for    SPB OPT 27.07.17   12:00-16:00 ,  SPB EXP 28.07.17 9:00-15:00   and  FXE 03.08.17  9:00-15:00.  Please address Eric Boyd's presentation for details. A mail reminder will be also sent to notify the beginning and ending of the tests.
  • The machine will be running with 30 bunches during the test and with 1 bunch during the night. Since no EPS is implemented, screens and sensitive components need to be taken out during the 30 bunches operation.
  • New version of Karabo ready to be deployed. The time slot when this will happen will be discussed on Friday,
  • Screens controlled by Karabo cannot be read from DOOCS. The Karabo/DOOCS interface problems will be be addressed with high priority by CAS.

XTDs

  • Fast valve in XTD9 still has issues with noise. Issue will be addressed tomorrow with AE support.

FXE

  • The detector group is updating the firmware for the LPD to fix the trigger signal problems. A test on just 1 quadrant will be done today together with ITDM
  • Interlock implementation in Loop 1 ongoing.

SPB

  • Integration of the turbo pumps in  the VAC loop ongoing. Interlock possible.
  • Chiller control being included in Loop 5 - Crate has been modified this morning. Loop will be updated checking that this will not stop the turbo pumps.
  • SMARACT motors being implemented. First motor is ready to be tested today after hardware problems have been fixed.
  • Work on in vacuum interlock in SPB ongoing.
  • The ELMO controllers for the motors of the liquid jet manipulator in Loop 13 should be brought and ready by CW 32. AE working on that. 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 25 Jul 2017, 13:26 

Dear all,

I had some minor updates of the TAS during the last days, please check again.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Be reminded that there will be virtually no access to XTD2, XTD4 and XTD10 before the 14.8. shutdown, so plan your work accordingly. Access requests please to M. Dommach, cc T. Tschentscher.

Cheers, Gerd

Entry   Status after 9.30 Meeting, posted by Adriano Violante on 24 Jul 2017, 10:38 

General

  • The latency observed by SPB in the GUI client has been almost completely fixed. Still some "freezing" from time to time remains.
  • DAQ tests in FXE with LPD worked for 12/16 of the detector. Trigger's signal stability issue being addressed by AE.
  • XTD 9 and 10 will remain open from 25.07. at 7:00 to 26.07. at 14:00  
  • On Wednesday afternoon the machine will be prepare to lase with 30 bunches in order to allow the radiation measurements in SASE1 Exp. Hall on Thursday and Friday.

XTDs

  • Fast valve in XTD9 still has issues with noise. Issue will be addressed tomorrow with AE support.

SPB

  • Integration of the turbo pumps in  the VAC loop ongoing.
  • Chiller control being included in Loop 5
  • Firmware for the AGIPD hv power supply was updated. The spikes during ramping are gone
  • SMARACT motors being implemented. (depend on Loop 13)
  • Work on in vacuum interlock in SPB will probably start this week.
  • Some problems with Karabo (While measuring profiles the level scaling does not work, Region of interest values wrong) have been reported to CAS.
Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 24 Jul 2017, 10:07 

General (T. Tschentscher/G. Wellenreuther)

  • Further tuning of the machine might require some time which was initially dedicated to photon/experiment commissioning.
  • Since Harald Sinn will be on vacation: If you need any kind of access please address T. Tschentscher or M. Dommach. TT will organize coordination of groups requiring access to the tunnels vs. requirements of the machine vs. the demand of the instruments for commissioning.
  • Lasing with 30 bunches was achieved this week. Consequently the radiation protection measurements have to be undertaken as soon as possible.

FXE (C. Bressler)

  • yesterday no beam at all
  • attenuators are being tested
  • all hardware installed

SPB (R. Bean/A. Mancuso)

  • Implementation of loops required for focal characterization — mainly loops 12 and 13. Also loops required for vacuum interlock.
  • Still more loops required to be brought up—working with AE down a clear priority list.
  • Clear plan for AGIPD to come to SPB/SFX instrument. Requires DAQ and more.
  • CAS reacted quickly to undesirable behavior (freezing) in Karabo, which is now largely solved.

Tunnel Installations SASE3 (J. Eidam, L. Samoylova, N. Kujala)

  • SASE3: No access – no progress
  • SASE2: work as planned is ongoing
  • SASE1: There are still issues with the fast valve.
  • During this and last week maintenance days, the Newton PICO motors of FXE monochromator were successfully tested in the tunnel together with Nicola. All four motors for crystal roll and pitch can be moved in vacuum. However a slow motion, necessary for fine tuning, seems still not available. Further motor parameters adjustment is needed, which will be done in the lab with test environment.
  • To fulfill the technical commissioning and make the FXE mono available for photon commissioning and operation, the firmware for Alio linear stage should be created. The work is on-going. May be available for tests before mid-August, but the schedule and priorities should be clarified.
  • Status of HIREX spectrometer in XTD9 tunnel: The HIREX saw FEL beam for the first time yesterday. All motors were commissioned with Karabo software and ready for commissioning with FEL beam. It is in discussion with SPB and FXE to have parasitic beam for commissioning in the coming week.

Laser (Daniel Kane)

  • The pump-probe laser group reported that, with the stabilization of the AC system, we are now continuing with production of the laser system. We are still missing the functionality some components of our control system, but we have enough at the moment that it is not an impediment to us building the laser for now, however it is something that needs keeping an eye on.

Detectors (J. Sztuk-Dambietz)

  • LPD: K. Wrona reported that they could observe on all channels but they are still working on storing the data. Loss of device settings induced by glitches in Karabo cost a lot of time to overcome.
  • AGIPD: ten out of 16 modules have been successfully tested but there is still a lot of work to do; still testing procedures and electronics, etc. before AGIPD is moving  in to SPB in August

AE (P. Gessler)

  • Focus is on loop 12 this week, continued to get remaining parts for loop 12 running
  • The firmware based interlock for FXE was implemented, certain conditions are disabled but otherwise it is running.
  • Plans for shut down week of SASE3 in tunnel in August are currently being made

CAS (S. Brockhauser)

  • As reported previously, a release candidate for 2.1.13 has been prepared last Friday
  • During the last week-end CAS could systematically reproduce the GUI delay problem SPB was reporting
  • In the beginning of the week CAS could identify the source of the GUI delay issue (which was in an old code of the GUI client and got triggered only under special circumstances) and fix it.
  • Solution was patched into the new 2.1.13 release resulting in a new release candidate which CAS finished testing now.
  • Note that the new release will also fix most of the annoying issues (especially the configuration persistence problems) experienced recently during LDP integration to FXE
  • As soon as the new release becomes finalized its deployment in the different production systems will be done under CAS coordination after consulting with all relevant WPs involved.
  • The newly introduced quick release cycles with the attached deployment process (as shown on the meeting last week) will help provide access to improved releases while guaranteeing that no surprises and irreversible regressions apply.
  • On the ScanTool thread opened by Christian: CAS has started to design a ScanTool around the SRD from SPB which is now being crosschecked against requirements coming from others, too, like FXE, before starting its implementation.
  • Thomas, Gerd, and Harald suggested to disseminate its design, so others can also give feedback. Hence, we agreed, that Sandor Brockhauser provide this information and organize a meeting next week.
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 24 Jul 2017, 10:03 

Dear all,

access to XTD9 and XTD10 will be available from tomorrow Tuesday the 25.7. 7:00 (Vacuum group will make sure the interlock is broken), until Wednesday 26.7. 14:00:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Please send any additional access requests to M. Dommach and T. Tschentscher.

Cheers, Gerd

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 20 Jul 2017, 15:19 

Dear all,

according to the current planning on next Tuesday (25.7.) both XTD9 and XTD10 will be accessible from 7-14:00:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

Entry   Status and Schedule after 09:30 meeting, posted by Tobias Haas on 19 Jul 2017, 10:11 

General

  • The latency observed by SPB in the GUI client could be reproduced by CAS. Also a  potential reason was identified. As soon as this has been sufficiently tested it will be released
  • DAQ tests in FXE with LPD worked for the first time yesterday for 1/16 of the detector
  • FXE and SPB will show 1-2 slides about progress and ongoing work during the TC meeting on Friday morning

XTDs

  • Fast valve in XTD9 still has issues with noise and will probably need to remain disabled

FXE

  • Interlock for loop 1 was deployed. Still need to do loop 2. Work per loop requires ca. 3-4 h.

SPB

  • Firmware for the AGIPD hv power supply was updated. The spikes during ramping are gone
  • Next items to get going are the SMARAGD motors
  • Loop 7 needs to be brought back. Crate 51 has been fixed.
  • Work on in vacuum interlock in SPB will need to be carefully timed and coordinated after finishing FXE. Due to impending beam probably not before next week
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 18 Jul 2017, 10:57 

Dear all,

an updated TAS is provided: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

There is potential access to the XTDs on next Tuesday + Wednesday (25+26.7.), as well as on Monday - Wednesday (31.7.-2.8.). Access will be organized by M. Dommach, since H. Sinn will be on vacation - so please send Martin your access request in time.

Cheers, Gerd

Entry   Information AE OCD July 14--17 (till Monday 8:00), posted by Nicola Coppola on 14 Jul 2017, 18:46 

AE on call service:

    Contact person:

        Nicola Coppola

    Phone

        9 - 8040

Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 14 Jul 2017, 13:17 

General

  • From now on progress with the SASE3 tunnel will be monitored in this meeting

FXE (A. Galler)

  • Work is going on to be ready for the start of instrument commissioning of Sunday
  • Currently the LPD movement is being tested
  • Today the firmware for the vacuum interlock system is being deployed

SPB (M. Messerschmidt)

  • All inputs needed for the vacuum interlocks can now be read out
  • Karabo was migrated to version 2.1.12. This appears to have some fixes for reading out cameras, but the GUI becomes unusable after ca. 10 min. Hence the version had to be rolled back to 2.1.11. This generated a lot of extra work
  • The test of the emergency off system was done this week. In preparation the PLCs were shut down to avoid damage. Bringing the system back was a significant effort. This should be getting less as more and more parameters are migrated to the firmware
  • A partial test of the MPOD power supplies was done in preparation for the AGIPD commissioning. Unfortunately some Wiener power supplies still have an older firmware that appears to produce voltage spikes when ramping up. This could damage the detector. Hence a firmware upgrade is needed. But no Windows PC was available on the controls network. The respective card was dismounted and taken to the lab for upgrading by K.-E. Ballack

Tunnel Installations SASE3 (M. Dommach)

  • A lot of installation work was carried out during the service period last week
    • All Day 1 devices are in place
    • A lot of missing connections were made (water, pressurized air)
    • Calbing was done for the imagers
    • The Solid Attenuator was assembled
    • There are still two vacuum leaks, one of them is on top of the dump. This may have to wait for the next service period in August
  • Focus during the next service period in August:
    • Install missing connection pieces and bellows in order to close the entire vacuum
    • Start bringing up Beckhoff loops with support from AE
    • Bring up as many components as possible 
  • For the comments made by WP74/J. Grünert, see the respective log book entry today

Laser

  • After a number of fixes and adjustments the AC parameters (Humidity/Temperature) are now according to specs

LPD

  • LPD is now fully installed in FXE
  • Work on the DAQ system starts next week
  • Next step for AGIPD in HERA-S is to get the DAQ system working. After this the detector will be brought to SPB
  • K. Wrona would like to cross check the configuration in HERA-S before this happens

AE

  • Work focussed this week on getting the remaining SPB loops up, in particular loops 12 and 5
  • For loop 12 a number of modules had to be taken out, modified and brought back. This relates to the operation of so-called SMARAGD motors
  • Originally it was planned to test the vacuum interlock system in SPB first. This requires inter-loop communication and there are still unused loops in SPB
  • Due to the problems with loop 12, it was decided to do the tests in FXE.
  • The firmware for the FXE interlock should be deplyed today
  • A meeting was held with MPS to clarify the interface between XFEL and MPS sind the MPS system cannot distinguish between the branch beam lines. This can now be handled by logic inside the PLC
  • AE is preparing for the support of SASE3 during the next service period

CAS

  • For more details see the detailed slides presented by S. Brockhauser during the meeting
Entry   Fast Valves in XTD9, posted by Martin Dommach on 14 Jul 2017, 12:44 

Dear all,

the fast valves in XTD9 were causing some trouble. From time to time they collect some electrical noise what triggers the valve. The pressure reading on the valve controller then shows oscillations of up to 10^-5 mbar, while the pressure around the fast valve gauges in the beamline is in the 10^-9 mbar range.
To operate the beamline in the meantime I have opened and disabled both fast valves. 

This needs further investigation on the service day next wednesday.

Best regards,
Martin

Entry   TAS updated, posted by Gerd Wellenreuther on 14 Jul 2017, 10:50 

Dear all,

the Tunnel Access Schedule has been update - potential access has been shifted from Wednesday the 19.7. to Tuesday the 18.7. Should you need this access, please inform Harald Sinn!

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

Entry   WP74 SASE1/3 readiness status and outlook, posted by Jan Grünert on 14 Jul 2017, 09:31 

SASE1 / SASE3 readiness --- WP74

2017-07-14

SASE1: 

  • commissioning of Kmono started yesterday at 10h for some hours
  • Kmono will be used for undulator commissioning as soon as Kmono is commissioned itself, and machine is ready for this
  • Support to SASE tuning given to machine (ongoing)
  • Maybe today: support during SASE gain studies
  • During last week (service week) : GLT-Anbindung XTD2 established

SASE3:

  • During last week shutdown : 
    • progress on DP installation, XGM cabling almost done, much imager and timing cabling done
  • When XTD10 is closed (as now) we currently cannot do much because there is no PLC loop in SASE3.
  • Non-Beckhoff technical commissioning started (e.g. some progress on MPOD HV-power supply)
  • WP74 must do a lot of technical commissioning in XTD10. Our work is by far not done when all our vacuum screws are tightened. There are different WP74 components in XTD10 than in SASE1 (not just a simple copy). WP74 requires the Beckhoff loops for tech. commissioning.
  • Alignment of DP „islands“ to be done in next shutdown.
  • Planned for next shutdown: installation of PES in XTD10, finishing of cabling
Entry   Information AE OCD July 13, posted by Nicola Coppola on 13 Jul 2017, 18:15 

AE on call service:

    Contact person:

        Nicola Coppola

    Phone

        9 - 8040

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 13 Jul 2017, 15:45 

Dear all,

I updated and extended the tunnel access schedule (TAS) until the 24th of July. According to Harald, there will be an opportunity to access XTD next Wednesday. Please keep him informed should you require access.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

Entry   Vacuum Loop in XTD9, posted by NEREA JARDON on 13 Jul 2017, 10:27 

Dear all,

One power supply needs to be changed in SASE1 XTD9 rack 1.12 tomorrow and it's related to the Vacuum loop. Denis Finze will do this change tomorrow morning, but we have to make sure before that we have all the equipments after this rack 1.12 in safe state (most concerning part, XGM in XTD9). Please, could you make sure that everything it's ok tomorrow at 10am? However I will send an email now to the involved people.

Thank you and best regards,

Entry   Motion loop update, posted by NEREA JARDON on 12 Jul 2017, 15:15 

Dear all,

Tomorrow morning we will do an update in the Motion loop due to some hardware changes requested in Rack number 1.18. You might will not have communication with this rack during whole day, because they will be doing local test after changing the hardware..

Thank you and bests,

    Reply   Motion loop update, posted by NEREA JARDON on 13 Jul 2017, 07:46 

Motion loop is up and running again, as I have said, you will not have communicatin with equipments of Racks 1.18 till Denis finishes with hardware changes.

Thank you,

NEREA JARDON wrote:

Dear all,

Tomorrow morning we will do an update in the Motion loop due to some hardware changes requested in Rack number 1.18. You might will not have communication with this rack during whole day, because they will be doing local test after changing the hardware..

Thank you and bests,

 

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 12 Jul 2017, 10:45 

XTDs

  • Mechanical operation of KMONO is prepared. Work is now ongoing on optimizing the scenes in KARABO
  • Data from the SR imager that is needed for scanning the undulator gaps needs to be available in DOOCS. This is prepared.
  • Once the machine can provide beam, one hour for KMONO first commissioning has already been agreed

SPB

  • Test of the Emergency Power Off should take place this afternoon. PLCs will be shut down and hence parameters have to be put badk
  • N. Jardon will put as much information as she can into the firmware do reduce the work of putting back the parameters
  • However, in FXE it was found that the Emergency Off buttons only act on the interlock and not on the electrical systems. The situation in SPB is probably similar
  • Work is ongoing on technical commissioning but there are still key components physically missing (e.g. CSS and Sample Environment)
  • Vacuum interlock is not yet implemented as it is still waiting for a number of components  in loops 12 and 5

FXE

  • JJ XRay worked last week and now the vacuum has to be re-established. Pump down should start soon but there was still one leak.
  • Vacuum interlock definition is ready and it will be implemented by AE today
  • LPD was installed. Currently 2 out of 4 super modules are installed. The other two should come early next week

DAQ

  • Cabling and preparations are ongoing
  • Tests should start early next week

AE

  • Currently working on changes in loop 12 for SPB

CAS

  • Currently working on bug fixes. Some of these bugs are probably responsible for the system not updating vacuum info for 30 minutes
  • Deployment should happen this or next week
  • There appears to be some confusion/communication issue as to what version of KARABO is installed where.
  • It needs to be ensured that the startup of the next photon commissioning period goes smoothly
Entry   Motion loop update, posted by NEREA JARDON on 10 Jul 2017, 15:23 

Dear all,

We will do an update of the Motion Loop in the next 15minutes in order to fix one analog signal related to the KMONO.

Thank you

Entry   K-Mono control, posted by Wolfgang Freund on 10 Jul 2017, 14:35 

During the first K-Mono test with Karabo on Friday the first goniometer THETA1 (Elmo controller) moved beyond the CW limit switch and stopped  at the CCW switch. So the goniometer was trapped between both switches with a movement range of a few degrees. Movement of encoder and motor were opposite. This behaviour is not understood and under investigation.

Now the goniometer is back within the nominal range and movement of motor and encoder reading is consistent. CCW limit switch at 117.5° / CW limit switch at ~182°.

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 10 Jul 2017, 10:31 

General

  • Interlock was set in the injector last Friday
  • All shifts were cancelled for the weekend
  • Startup today and interlocks set in XTD10
  • It is still the aim to have photons by Wednesday (info from XFEL runn coor at 10:30)
  • XTD9 remains open until Friday afternoon
  • Tests of the emergency off buttons by TS (Thorsten Schön/TS) need to be performed in the instrument hutches. This is currently scheduled for Wednesday and should be done this week but requires careful coordination in order not to break equipment and disrupt commissioning

XTDs

  • Progress on KMONO was unfortunately not reported as W. Freund was involved in tunnel search during the meeting. A. Koch shall ask W. Freund to put an update in the log book
  • A lot of work was done on XTD10 installations last week, e. g. cooling water connections, gas attenuator installation
  • Unfortunately, there is still a vacuum leak on top of the XSDU2 dump
  • Work shall continue during the next break week in August and during individual service day if the opportunity is given

 

SPB

  • Loops 5 & 12 are needed for the vacuum interlock. Hence cross-loop communication is needed. This requires additional testing
  • Loop 5 is deployed but misses 2 modules that are being modified
  • Loop 12 is not deployed and also requires that a few modules be modified
  • The goal is to get the interlock up during this week

FXE

  • The vacuum interlook will be deployed once the inter-loop communicationn has been tested in FXE
  • JJ worked all of last week to 
    • Fix a leak in a bellow
    • Exchange one pump controller
    • Rewire motors to conform to XFEL standards
    • Install diamond screens in the imagers
  • LPD was installed
  • There is still confusion about the CRL alignment: Are individual lenses misaligned or the whole stack? This information is needed to obtain the next security level clearance from D3

AE

  • AE will not attend the next meeting on Wednesday since there is a parallel event with MPS on the details of the interlock connections, in particular how to deal with the fast valves in the instrument hutches

CAS/ITDM

  • ITDM is currently working with highest priority on DAQ for LPD. Once this is integrated, DAQ for the tunnels will follow
  • Work on LPD DAQ is done in a separate KARABO "Topic" in order not to disrupt other work
  • There are ocnfusing statements of whether DAQ can deal with more than one topic per SASE in the long run...

Important topics for this week

  • Perform emergency off tests
  • Get LPD DAQ going
  • Integrate vacuum interlocks
  • Make KMONO available for SASE tuning
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 10 Jul 2017, 10:26 
 
Entry   EPS loop, posted by NEREA JARDON on 07 Jul 2017, 13:24 

Dear all,

We need to update EPS SASE1 loop in order to finish the interlock communication for the experiments. I will do the update around 14h.

Thank you!

Entry   Karabo K-Mono-scenes, posted by Wolfgang Freund on 07 Jul 2017, 08:24 

I am working this morning on following projects:

SA1_KMONO_SYSTEM
SA1_XTD2_KMONO
SA1_XTD2_IMGSR
SA1_XTD2_FLT

Please don't save these projects !

Entry   Vacuum Loop, posted by NEREA JARDON on 06 Jul 2017, 12:49 

Dear all,

Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.

Thank you,

    Reply   Vacuum Loop, posted by NEREA JARDON on 06 Jul 2017, 15:03 

Vacuum Loop is running again.

Thank you!

NEREA JARDON wrote:

Dear all,

Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.

Thank you,

 

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 06 Jul 2017, 08:51 

Dear all,

access to XTD9 has been extended until the Friday the 14.7. 14:00. Tunnel access schedule has been updated:

TAS

Cheers, Gerd

Entry   Motion loop update, posted by NEREA JARDON on 05 Jul 2017, 17:48 

Dear all,

In order to finish the configuration of part of Hirex devices, we need to make an update of the Motion loop tomorrow morning at 10am. Please drive your devices to safe position before this hour.

Thank you

Entry   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 10:12 

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

    Reply   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 11:23 

We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14

NEREA JARDON wrote:

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

 

       Reply   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 11:47 

It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.

NEREA JARDON wrote:

We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14

NEREA JARDON wrote:

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

 

 

          Reply   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 14:07 

The encoder terminal in rack 1.5 has been replaced.

NEREA JARDON wrote:

It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.

NEREA JARDON wrote:

We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14

NEREA JARDON wrote:

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

 

 

 

Entry   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 09:41 

Dear all,

Today we are planning to integrate part of Hirex motors into the Motion loop of SASE1. Therefore, the loop will be break, so you will loose communication with whole XTD9 Motion part. I will back again to you when we are done,

Thank you

Entry   Karabo for SASE1 topic restarted, posted by Alessandro Silenzi on 03 Jul 2017, 20:53 07.png

Here attached the main SASE1 panel

Entry   control servers maintenance, posted by Janusz Szuba on 03 Jul 2017, 18:22 

All control servers, brokers, dl and finally gateway were updated and restarted.

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 03 Jul 2017, 16:03 

Dear all,

based on the information from todays BKR-meeting and communication with Harald Sinn, I updated the TAS: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Basically, Harald is trying to keep XTD9 open until middle of next week, he still has to talk to DESY...

Cheers, Gerd

Entry   Motion loop update, posted by NEREA JARDON on 03 Jul 2017, 11:01 

Dear all,

We will be working in the Motion loop till this afternoon. So as I said in the morning meeting, I will let you know when we have finished.

Thank you

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 03 Jul 2017, 10:26 

General

  • Accelerator was down all weekend due to cold compressors that were damaged in conjunction with the power outage on Friday
  • Since 0700 all interlocks are broken and tunnels are open.
  • Tunnels except XTD9 stay open until Thurday.
  • XTD9 can remain open longer

Availability of Networks

  • Network mainentenance that was requested last Friday for Tuesday has to happen today together with the rest of the facility. It was scheduled for 0700 - 0900 and is already almost done
  • Following the network maintenance, N. Jardon will bring down the motion loop for KMONO integration. This only affects the tunnels and instruments can work during this time
  • After the work by N. Jardon, IT needs to replace kernels on server machines. This will result in KARABO being down until early afternoon
  • Afterwards CAS needs to bring back KARABO
  • All measures will be announced on this log book

Instruments

  • Implementation of vacuum interlock should be implemented this week. 
  • SPB requires several adjacent loops to be included. Some of them are not up or complete. Maybe a simplified version should be installed first
  • SPB requests loop 12 from AE. However this will take until mid July as it contains new motors (SMARAGD) that have not been tested so far

AE

  • Work is currently ongoing on preparing to connect instrument interlocks to the DESY MPS system
  • Work is also required to fix problems for the laser group that are most likely due to faulty wiring or a broken terminal

IT

  • The dual power supply for switches saved a lot of work for IT after the power cut on Friday
  • Unfortunately, the PLC CPUs in SASE1 are not on dual power. This should be upgraded as it is now also planned for SASE2/3.
  • Dual power should also be put for the uTCA systems
Entry   Network upgrade /information and problem, posted by Krzysztof Wrona on 03 Jul 2017, 10:13 

The upgrade of the switches is finished to the extend that it allows Advanced Electronic group to work on KMono (Nerea is informed)

However, during the upgrade of the network one switch got stuck and this is the switch in XTD2 tunnel. The IP network in the XTD2 tunnel is not reachable at the moment (Beckhoff loops are fine) and we are going top the tunnel soon.

 

 

Entry   Network and servers maintenance, posted by Janusz Szuba on 30 Jun 2017, 15:33 

As discussed offline with NOC, Monday schedule was already fixed and not movable to Tuesday. Therefore, the network maintenance will take place on Monday 7:00 - 9:00.

During that time, no stable network is guaranteed.

After the network maintenance, the foreseen update and restart of all control server will take place, which take approx. ~2 hours. The exceptions are sase1 control servers and plc gateways as well as data logger and brokers and probably most importantly, exflgateway. These will be done after the work in sase1 (KMONO integration) is finished.  

Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 30 Jun 2017, 11:33 

Data Acquisition and Data Archiving

  • K. Wrona summarised the basic ingredients of the system.
  • All components are ready and tested individually
  • Integration in the instrument environment is needed and will be done first in the context of commissioning LPD in FXE starting from 5 July
  • DAQ and archiving for the tunnels was originally not foreseen but is being worked on now
  • The split up of the KARABO environment into several "Topics"  was done on purpose to allow development with minimal interference
  • The separate topics have to be re-integrated now
  • The sildes from Krzysztof can be found here

XTDs

  • KMONO integration should happen next week starting on Monday
  • The planned work on the network switches should only start on Tuesday as it interferes with KMONO integration

FXE

  • Topics to be worked on next:
    • Vacuum interlock integration
    • LPD integration
    • uTCA digitizer (was already working in Karabo 1.4.7)
    • Great Eyes Detector has a rate limitation that was not there before
  • Longer term topics
    • Gotthard detector

SPB

  • Loops 12 and 5 are prepared and uploaded but need to be commissioned now
  • Firware for loop 13 is needed next
  • Many motors seem to be getting 24V, but should be ruuning with 48V. What is wrong? This needs to be checked in the EPLAN and CRDs
  • Loops appear to be missing components

Detectors

  • LPD goes to FXE on 5 July. Integration work in the hutch starts immediately after
  • AGIPD then goes into the X-Ray test stand in HERA-S
  • Note that the DAQ infrastructure can only support one detector at full rate at a time. 
  • In principle this should not be an issue at 30 bunches but it requires the veto system to work which needs testing

Electronics

  • Work this week concentrated on preparing everying for deploying the instrument vacuum interlocks next week
  • The problem with wrong names in the PP laser was identified as a wiring issue in one crate 
  • Work also concentrates on timing and train builder to support detector integration from next week

 

 

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 27 Jun 2017, 10:26 

Dear all,

according to Dirk Nölle access to XTD4 during the shutdown will be extended until Thursday.

Link to Tunnel Access Schedule

Cheers, Gerd

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 26 Jun 2017, 15:52 

Dear all,

I tried to update the TAS to include the times for each XTD during the shutdown-week at the beginning of July. It is currently not entirely clear when XTD9 and XTD10 will be searched, and as always this is subject to change...

Link to Tunnel Access Schedule

Cheers, Gerd

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 26 Jun 2017, 10:57 

General:

  • ​Beam was brought to all SASE1 hutches on Friday. Beam was available to both instruments splitting it with M3 until Sunday morning. Afterwards SASE tuning was done and the beam should be back in the hutches some time today. Beam operation will continue this week with very low intensity. Split beam operation to both instruments.
  • Rules as follows:
    • Only one bunch and very low intensity (< 100uJ)
    • Mechanical manipulation on vacuum parts only when shutter and all-metal gate valve are closed
    • Shutter and gate valve closed when instrument people are not in attendance
  • CAS appears to be in a 2 day workshop from 9 - 5. This is a problem as some urgent work is needed. 

XTDs

  • No access for KMONO commissioning this week
  • All preparations that can be done for KMONO operation should be done however
  • M. Messerschmitt prepares interface for the FEL imager to DOOCS so that KMONO can be used for tuning

SPB

  • A list with essential components has been prepared
  • It appears that some of the previously brought up loops contain only vacuum components. This should be fixed
  • Loops 5 and 12 are needed most urgently now. 
  • 5 additional servers are needed from CAS

FXE

  • No remarks from FXE
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 23 Jun 2017, 11:11 

General

  • A low intensity beam is being put into the SASE1 intrument hutches in this order: SPB Optics, FXE Instrument, SPB Instrument
  • No special precautions outside the hutches are needed due to the low intensity. 
  • The work will most likely not finish today. If necessary ti will continue next week Monday
  • From now on, access to the SPB Optics, SPB Instrument and FXE Instrument hutches requires these three safety trainings
    • General Safety (AllgSi)
    • XFEL Safety (SiXfel)
    • General Radiation Safety (StraSchu)
  • Check with SRP if you are not sure about yout status

XTDs

  • W. Freund and the AE colleagues successfully tested their firmware on the the KMONO in HERA-s. This will be integrated in the motion loop and a controlled access will be requested on Tuesday to try this out in XTD2

FXE, SPB:

  • Working in the hall to bring the beam into the hutches

Laser:

  • 90% of the hardware is installed on the tables
  • Humidity in the laser hutch still varies wildly, even after the humidity in XHEXP1 is below 60%
  • Humidity variations translate into a pointing instability of the seed laser which cannot go into the amplifier
  • There is a discrepancy between KARABO names and motor terminal names that needs to be cleaned up

Detectors

  • Interlock tests on AGIPD were successfull
  • The train builder is integrated
  • LPD is about to finish the tests in the X-ray chamber
  • Afterward the KARABO version needs to be updated 
  • Transport ot FXE is scheduled for week 27

Electronics:

  • Getting SPB and FXE ready for today's beam exercise required quite some short term effort
    • Mahadi had to get the cameras ready
    • Bruno had to set up the trigger timing
  • Implementation of the interlock conditions were delayed for the exercise of bringing the beam in. This should happen immediately afterwards together with the connection to the MPS system which is currently not present
  • The remaining problems with vacuum in SPB and FXE were solved (Some had to do with hw problems and wrongly wired controllers)
  • Work continues on bringing up more SPB loops. Most recently loop 4 was brought up and the firmware for loop 7 is prepared for tests
  • Implementation of the interlock conditions were delayed for the exercise of bringing the beam in. This should happen immediately afterwards
  • The work on KMONO delays some of the instrument work

Software:

  • CAS is currently working with high priority together with ITDM to get the DAQ system and archiving up 
  • There was a dedicated SQUAD for this purpose
  • The functionality has already been tested successfully on the LPD detector.
  • The interface needs work to become usable
  • Tests of full scalabiity are still outstanding
  • The system needs to be deployed in the real environment
  • It is estimated that the remaining work should take ca 3 - 4 weeks

 

Entry   Schedule for first beam SASE1 hutches, posted by Tobias Haas on 22 Jun 2017, 15:15 

It was just decided to put a very low intensity beam into the SASE1 hutches starting tomorrow morning at 8 AM. Both instruments declared that they are ready to accept it. Due to the very low intensity no special measures need to be taken outside the hutches. SRP and D3 shall be in the experiment hall. Harald Sinn shall coordinate beam activities from the BKR. Please note that the TC and S1R meetings take place as announced.

Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Jun 2017, 14:13 

Dear all,

I extended the tunnel access schedule up to the beginning of the shutdown (3.7.). As always, you can find it under https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Access request to Harald Sinn. Works during the shutdown have to be reported to Harald Sinn and Dirk Nölle for scheduling.

Cheers, Gerd

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 21 Jun 2017, 10:21 

XTDs:

  • DESY requests the KMONO to be commissioned since the K Values of the undulators appear not to be as accurately calibrated as originally advertised. Management decided to put KMONO at the top of the priority list for this reason. W. Freund should work together with Mahadi and Nerea on getting the two goniometer motors (ELMO controller) working. When software is ready a ZZ access should be requested
  • Latency of FEL imager is ~ 5s which is a problem for tuning and scans. M. Messerschmitt is looking into this. A. Silenzi was not aware of the problem up to now.

Radiation Safety Tests:

  • Radidation safety tests are scheduled for 26 - 28 June. Proposed order is SPB Optics, FXE instrument, SPB instrument. Detailed plans to be discussed in a dedicate meeting on Thursday and plans to be presented in the Friday TC meeting
  • Vacuum interlocks will not be implemented before the rad safety tests and vacuum will be operated completely in manual mode
  • Open topic: Can the instruments use the beam after the rad safety test are done and how is the procedure?
  • SRP needs to make precise statements about where people can/should be during the rad safety tests

FXE:

  • Ready for radiation safety tests.

SPB:

  • Tested motors in loop3
  • Tested valves in loops 2&3

Electronics:

  • Concentrating on getting KMONO going in the next days

Software:

  • No special topic
Entry   Access to tunnels updated, posted by Gerd Wellenreuther on 19 Jun 2017, 16:55 

Tunnel access schedule has been updated, access for XTD9 on Wednesday from 7-14:00 is now for granted.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 19 Jun 2017, 10:17 

XTDs:

  • There are no major issues, commissioning works smoothly this weekend.

FXE:

  • Radiation safety measures done last Wednesday.
  • Tests with CRL are on going but there are some problems with motors since are moving only in one direction. CAS is working on that issue.
  • Loop1 need an update, support from AE necessary.
  • Interlock conditions meeting to be held today, to carry out  the test end this week.

SPB:

  • Test with loop2 continue.
  • Cables for Loop3 will be repaired today and tomorrow. Firmware already available.
  • Export for loop 7 is done, AE is working to generate the firmware. EET has two persons working in the exports for loops 4 and 12.
  • Interlock conditions already defined by SPB sometime ago.

Diagnostics:

  • External trigger for Basler cameras still not always working, CAS keep working on that.

 

Electronics:

  • Today and tomorrow working for the AGIPD, required an additional interlock part for the Vacuum.
  • First priority is is to have the Vacuum system for FXE and SPB operational at the end of June. Next two weeks AE will be mainly focus in the loops that are still missing (SPB 4, 5, 7,12) or still not running (SPB 2, 3)

 

Software:

  • Karabo version installed in a different domain, CAS is still testing ths version to ensure a smooth transition from one version to other.
Entry   WP74 OCD plan update, posted by Jan Grünert on 16 Jun 2017, 18:12 WP74-OCD-plan-6-8-2017.xlsx
The WP74 OCD plan is also published in WP74-Alfresco and sent by email to HR/WoCo/STGL.
Please note that this plan could be subject to changes depending on the needs of the involved colleagues (e.g. if they want to swap OCD assignments).
The actually performed OCD-times are reported to HR at the start of each following month.

Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 16 Jun 2017, 10:18 Radiation_Measurments_for_Commissioning.pptx20170615-Components-Detectors.xlsx

General:

  • E. Boyd update the status about the tasks for radiation measurements the 26th June. See presentation attached.
  • J. Gruenert suggest to use similar interface as is being use for the machine and will send the link to G. Wellenreuther.

XTDs

  • Images for Photo commissioning on the tunnel are stored by a temporary solution. J. Grunert request when the DAS routines will work, CAS will prepare a short presentation for the meeting next Friday to show the progress on that issue.
  • This weekend is scheduled to commissioning with a WL of 1,5Å and 30 bunches into the dump for first time.

FXE

  • Radiation safety measures done last Wednesday.
  • Leaks in the Vacuum system already fixed.
  • Cables for motors already repaired by JOWO this week. Reparations will continue next week after urgent cables for SPB are done.
  • In general loops are working but there are still some minor issues, AE working in some loops updates.
  • Meting on Monday between FXE and AE to define Interlock to deploy.

SPB

  • Loop 1 is working, AE to fix some mismatchs in loops 2 and 3.
  • Export for loop 7 is done, AE is working to generate the firmware. EET has two persons working in the exports for loops 4 and 12.
  • Ion pump cables repaired and tests on going.
  • All connector reparations in the OPT-hutch are done and the test of the motors are on going.
  • JOWO will keep working in 20 urgent cables for SPB and then move back to FXE.

Detector

  • AGIPD is fully powered, there are still some issues for the Intelock that needs AE support.
  • More details see attached file provided by Detector Group.

Laser

  • The humidity in the hutch still oscillates, this shoud be fixed urgently since it is preventing further commissioning.
  • Image processor not working since each 2-3 hours stops, CAS to fix that issue.
  • There are motors not working, CAS to investigate.

Electronics

  • First priority is is to have the Vacuum system for FXE and SPB operational at the end of June. Next two weeks AE will be mainly focus in the loops that are still missing (SPB 4, 5, 7,12) or still not running (SPB 2, 3)
  • Elmo controllers not integrated, AE will test a solution in SPB on next week. If it works will be deployed also for the tunnels but this is not first priority and will be done in July.

Software

  • CAS is working to have a more robust system, S. Brockhauser point out that new request from instruments should we send to CAS to define priorities.
  • To prepare a short presentation for next Friday about the issue of the tunnel DAS to store images (see point in XTDs)
Entry   Access to tunnels updated, posted by Gerd Wellenreuther on 15 Jun 2017, 12:18 

XTD9 will be open until Friday this week 13:30. Check https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 14 Jun 2017, 10:57 

General:

  • G. Wellenreuther has created a link to the first version of a central schedule of "our" tunnels: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
  • Any changes of schedules should be put in there first, and THEN a short message can be sent using the e-log pinpointing people always to this page. Please check correctnesss, and feel free to provide Gerd with any feedback.

 

XTDs

  • Minor problem with Ion pump controllers, AE working on it. 
  • Vacuum loop needs an update but it is not urgent.

FXE

  • Ion pumps controller issue already fixed.
  • Test of CRL with PLC is on going. There are some issues with encoders, could be a cable mismatch problem in PP, JJ to check. The cables for CRL have been already measured and are correct. 
  • Radiation safety measurements being doing today.

SPB

  • EET is working to generate the exports for loops 7 and 12. Export for loop7 will be ready this week and EET will continue with loop 12.
  • Tests with loop2 on going.
  • Firmware for Loop 3 is available, but cables have to be repaired.
  • Modules BKF00056, 00057 affected by Ion pumps issue already modified.To double check with N. Coppola if more modules are also affected by this problem.
  • Cameras are not in Karabo, this is a requirement before cameras can be connected. A. Silenzi to work on that.

Laser

  • After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need some additional information from Laser group.
  • There is a mismatch beween the motors and the control, AE will check if it ia a firmware or hardware problem.

Diagnostics

  • External trigger not always working, CAS working to find the cause and provide a solution.

Software

 

  • Karabo version installed in a different domain, this will permit to fix errors. When this version will be ready, CAS will need 2 hours of downtime to implement.
Entry   Tunnel's schedule updated, posted by Monica Aresté on 12 Jun 2017, 13:21 

Last information is that tomorrow Fire brigade will come to inspect the tunnels, therefore all tunnels will be open from 7:00 to 15:00.

H. Sinn inform that XTD9 will not be searched until Wednesday morning.

Tunnel's schedule:

  • Monday 12th June:  XTD10 closed, XTD9 open
  • Tuesday 13th June: from 7:00 to 15:00 all open

 

Entry   Tunnel's schedule, posted by Monica Aresté on 12 Jun 2017, 11:17 

Tunnel's schedule clarification:

  • Monday 12th June:  XTD10 closed, XTD9 open
  • Tuesday 13th June: from 7:00 to 15:00 all XTD9 and XTD10 open (all is incorrect, I mean XTD9 and XTD10).

Someone pointed out that XTD2 maintenance for tomorrow is cancelled and XTD2 wil be closed.

 

 

 

Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 12 Jun 2017, 10:55 

Tunnel's schedule:

  • Monday 12th June:  XTD10 closed, XTD9 open
  • Tuesday 13th June: from 7:00 to 15:00 all open.
  • There is a request to have a unique place with updated information when the tunnels are open/closed, PSPO is working to set a place in the intranet and will inform as soon as this will be agreed.

General

  • Cable reparations on OPT hutch on going, FXE will follow.
  • WLAN access at the end of XTD9 is not very good and not sufficient for testing cameras, e. g. in PBLMs. ITDM re-cabled some ports and provided office network port in rack 1.17 that could be used to commission the cameras. According to Liuba it worked well.
  • From 08/06/2017 the ITDM group provides the OCD service. The general principle is that the 1st level support is provided by CAS group and in case they cannot solve the ITDM related issue they call us. The phone number for ITDM OCD is: 98070 or directly +49 175 9814494. There is a single number for 3 mobile phones so the number is valid independent on the person providing OCD.

XTDs

  • Motion loop updated twice during last week, but there is still a feature to be fixed.
  • There has been a modification of the interlock conditions by RAUL for the gas section. Already implemented and working.

FXE

  • There is a mistake in the channel assignment of the Ion pump controllers, modules BKF00074 and BKF00096 modified. Bug with the ion pump controllers still not corrected, AE and CAS are working on that.
  • Acceptance test for CRL is done, final parameters settled down, next step is to test CRL with PLC.
  • Loop 8 already deployed but still not working. This loop is low priority.
  • Radiation safety measurements are the first priority for this wwek in FXE.

SPB

  • Currently there is no working version of Karabo for SPB (Fixes were implemented that broke base functionality)
  • EET is working to generate the exports for loops 7 and 12. Export for loop 7 will take longer than expected acc. to last info from EET.
  • All motors in loop 1 are working.
  • In loop2 one module is being reworked by AE, still on going.
  • Firmware for Loop 3 is available.
  • SPB is also affected by the problem with the Ion pumps, modules BKF00056, 00057 affected. AE working to solve this issue.

Laser

  • After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need some additional information from Laser group.
  • There is a mismatch beween the motors and the control, AE will check if it ia a firmware or hardware problem.

Software

  • Deployment of KARABO version 2.1.12 was deployed to FXE on Friday. The new version is deployed but not activated since there are some issues to fix.
Entry   Motor in error, posted by Gabriele Giovanetti on 09 Jun 2017, 21:40 

Called at 21.18 for SASE1_XTD2_IMGSR/MOTOR/Y being in error.

Solved by pressing 'Reset' button in Karabo GUI

Entry   Information AE OCD June 9 -- 12, posted by Nicola Coppola on 09 Jun 2017, 19:09 

 AE/PLC on call service:

     Contact Person:

              Nicola Coppolla

    Phone:

   9 - 8040

Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 09 Jun 2017, 12:41 

General

  • E. Boyd presents a summary of the next tasks for the radiation measurements for hutch commissioning. There are some dates (13th and 20th June) that safety needs exclusively access to the hutches. Safety will be in close contact with Instruments to agree the dates.
  • Tests are finished in SPB Optics (40 connectors to be replaced) and continue now in FXE.
  • There is an interference of connector replacement and tests of the interlock. If Instruments grant exclusively access for the Interlock works, this has to communicate to PSPO to inform company JOWO that is working in the cable reparations.
  • Starting this week, new messages in the elog appear not to be sent to all registered user. The system unsuscribed automatically from one elog when you suscribe to a new one. IT has already fixed this problem.
  • WLAN access at the end of XTD9 is not very good and not sufficient for testing cameras, e. g. in PBLMs

XTDs

  • Motion loop updated twice during this week, but there is still an issue with Elmo limits. AE will first test a solution and decide if a new update is necessary.
  • PBLM tests with Mahadi and Natalia shall start after motion loop update.
  • There has been a modification of the interlock conditions by RAUL for the gas section. This needs to be carefully checked.
  • There is a request to improve the information when the tunnels are open/close, now it takes too much time to find the information in the elog. Suggested to have a unique place with the information up-to-date.

FXE

  • There is a mistake in the channel assignment of the Ion pump controllers, modules BKF00074 and BKF00096 will be modified today. Moreover firmware for loops 1 and 2 have to be updated.
  • JJ XRay is here this week, acceptance test for CRL is done. Work will continue with von Hamos Spectrometer
  • The LPD 2-tile system brought into the hutch to test the controls.
  • Loop 8 already deployed.
  • Interlock defintion for FXE is done.

SPB

  • Currently there is no working version of Karabo for SPB (Fixes were implemented that broke base functionality)
  • EET is working to generate the exports for loops 7 and 12.
  • There are still some mismatches in the connectors of 11 cables, A. Legrand working with Actemium to fix the problems.
  • In loop2 one module is being reworked by AE.
  • SPB is also affected by the problem with the Ion pumps, AE to figure out which modules have to be reworked.

Laser

  • The humidity in the hutch is down to 50%, but still oscillates
  • AE is fixing connectors with water problems
  • After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need soe additional information.
  • There is a mismatch beween the motors and trthe control, AE will check if it a firmware or hardware problem.

Detector

  • LPD test working succesfully, waiting when FXE hutch will be ready to move the LPD. Radiation protection has to be finished before to move the detector.

Software

  • Deployment of KARABO version 2.1.12 will be deployed today to FXE. D. Goeries shows a presentation with a description of improvements in the new version.

Entry   XTD10 and XTD9 tunnel opening and closings, posted by Harald Sinn on 08 Jun 2017, 08:24 

Dear all, 

according to the DESY logbook XTD10 will be opened today again: See DESY logbook entry:

'due to the cryogenic failure we will open XTD10 from 9am for working.
at XTL and XTD2/4 ZZ is possible for repairs/work.'

I don't know hoe severe the cryo failure is, but otherwise the agreement is that XTD9 will be closed Friday morning around 9am.

(I assume that they may close Friday morning also XTD10 again).

Best regards

Harald  

 

Entry   XTD10 open , posted by Tobias Haas on 08 Jun 2017, 08:24 
 Author: limberg, tischhauser
due to the cryogenic failure we will open XTD10 from 9am for working.
at XTL and XTD2/4 ZZ is possible for repairs/work.
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 14:19 

Dear all,

Motion loop is up and running again, now with all the PBLMs configured.

Thank you,

Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 12:00 

Dear all,

Due to some hardware changes needed in Motion loop, we will last a little bit more in the Motion update. You will loose communication but I will come back when it is running again.

Thank you and sorry for inconvenience.

 

Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 07 Jun 2017, 11:43 

 General

  • Technicians from Actemium/JOWO arrived and found that a lot more connectors than originally estimated need to be replaced
  • Tests are finished in SPB Optics (40 connectors to be replaced) and continue now in FXE 
  • Replacing connectors starts tomorrow with 3 technicians and should take 45 minutes per connector 
  • There is an interference of connector replacement and tests of the interlock. This needs to be resolved.
  • Starting this week, new messages in the elog appear not to be sent to all registered users. (Info from J. Szuba: Some users intentionally or unintentionally un-subscribed)
  • WLAN access at the end of XTD9 is not very good and not sufficient for testing cameras, e. g. in PBLMs

XTDs

  • On the weekend the broker queue filled up. This was fixed using "extreme measures". This led to V0 closing and  BKR crew was not aware of the state of V0. It is the opinion of the experts that the BKR crew could have known but were not fully informed where to look
  • The motion loop was updated yesterday for PBLM tests. But the update was not complete and will be redone today before 12:00
  • PBLM tests with Mahadi and Natalia shall start after motion loop update
  • XTD9 will be closed on Thursday (not confirmed)
  • There has been a modification of the interlock conditions by RAUL for the gas section. This needs to be carefully checked.

FXE

  • Communication is now possible with the ion pump controllers but there is still an error message from the controller that cannot be interpreted. The manufacturer of the ion pumps (AGILENT) has been contacted
  • JJ XRay is here this week. They work on the patch boxes for the CRLs and the von Hamos Spectrometer
  • The LPD 2-tile system will be brought into the hutch today to test the controls
  • Commissioning on motors continues

SPB

  • Currently there is no working version of Karabo for SPB (Fixes were implemented that broke base functionality)
  • Loops 7 & 12 have not connectors affected by water and could be commissioned. AE was informed to provide firmware

Laser

  • The humidity in the hutch is down to 50%, but still oscillates
  • AE is fixing connectors with water problems
  • After PLC cycling the Beckhoff terminals loose the proper parameter set. This issue needs attention.

Software

  • Deployment of next KARABO version is postponed until the new version switching method is sufficiently tests. H. Sinn points out that this version (2.1.12) contains many urgent fixes and is needed asap.
  • The incident on the weekend showed again the need for the consolidated list of mandatory devices. This is being worked on 
  • The bug where the gui server looses track of the state of the system is still not fixed! If it occurs inform CAS immediately

 

Entry   Motion loop update, posted by NEREA JARDON on 06 Jun 2017, 17:39 

Dear all,

The Motion loop is running again. We have included today the Mc2motor devices that were already before configured (FXE PBLMs and MCP), tomorrow we will include the rest of the PBLMs.

Right now is also into the loop the Hirex hardware in Rack 1.8 and the new crate of the Rack 1.18 for the temperature measurements.

Thank you,

Entry   Motion loop update, posted by NEREA JARDON on 06 Jun 2017, 13:46 

Dear all,

We will start with the Motion loop update. Will take us a little bit, around 3 hours, but I will let you know when it has finished.

Thank you,

Entry   SOLVED BROKER Problem , posted by Alessandro Silenzi on 03 Jun 2017, 22:39 

A pile up in the BrokerQueue was detected by CAS monitoring system and

a response action from the On-Call personnel was triggered.

Regrettably, the following device servers have been shutdown and will be re-instantiated.

- Dataloggers
- alarm server
- camera servers
- Motion Loop and Vacuum Loop beckhoff servers

Sorry for the inconvenience

Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 02 Jun 2017, 13:01 

General

  • Due to the water incident in the hall commissioning activities are somewhat delayed
  • Next week 2 technicians from Actemium/Jovo arrive and shall fix damaged connectors, disassemble a subset of connectors and test all cables
  • Detailed planning for the repair and testing will be made once Jovo is on site. But the work should go in this order: SPB Optics, FXE Instrument, SPB Instrument
  • A few cables are also affected in the tunnels but the Vacuum group can shorten the cables and reconfection them
  • Update of the motion loop in the tunnels should happen early on Tuesday
  • SRP should present the detailed plans for the radiation safety tests asap so a respective road map can be worked out
  • It was noted that the newly installed laser chicanes appear not to be radiation tight

XTDs

  • The bug that leads to the GUI not updating is annoying and has led to a loss of at least 2 h of beam time
  • One arm of the MCP got stuck since the end switch was not handled properly. For the moment this arm cannot be moved safely. The problem is understood but requires an update of the motion loop.
  • The update on Tuesday also contains code for HIREX, updates for PBLMs and imagers

FXE

  • Gate valves can be operated
  • Problems persist with ion pumps and pressure gauges
  • For radiation safety tests also the Fast Valve and the interlocks need to be working. This is not yet the case
  • JJ XRay is coming again next week. It is not currently clear how much they can do in view of the cable problems

SPB

  • The list of cables affected by the water were given to A. Violante
  • Testing activities should progress in parallel with cable testing if possible. This requires the respective module to remain in the crates. It needs to be clarified whether this is possible

Laser

  • The humidity in the hutch is still too high (>75%)
  • Humidity regulation is not ok and oscillates by +- 5%
  • The optical glue was found to be very sensitive to humidity and needs to be exchanged
  • A few connectors were damaged in the flood. They will be exchanged by AE

Detectors

  • AGIPD is currently open to fix problems with readout of temperature sensors and other controls
  • Next week the detector will be closed again and then PLC tests will be carried out
  • The modifications of the electronics took 1.5 weeks. Only 2 days were estimated
  • The LPD detector is currently already controlled with KARABO
  • DAQ is working and calibration runs with the internal source are being carried out
  • Next week the detector will be moved into the X-Ray chamber and calibrations with X-Rays will be done
  • 2-3 weeks from now LPD could move to FXE
  • Readiness of FXE needs to be checked as KARABO versions are currently not compatible

Electronics

  • FXE Loop 7 firmware is ready

Software

  • Working on a more systematic approach to upgrades and support. In this scheme a candidate version can be fully set up and switch from old and new and back can be done quickly
  • Working on a definitive list of supported devices in order to organise proper support

 

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 31 May 2017, 11:05 

 General

  • Photon tunnels will be searched starting at 1500 today and then closed. Machine will go back into regular operation this afternoon
  • XTD9 stays open until further notice
  • Flooding damaged several connectors in SPB Optics and FXE Instrument. 
  • Jovo will replace connectors that show optical damage and test all cables that were in the water. A list is being compiled by Adriano. Meeting held for this purpose today at 1330 in XTOB.

XTDs

  • Work continues on stability problem of SR imager 
  • 2 updates were done on motion loop since a bug was still found for the MC2 lib after the first update
  • 1 update was done for vacuum loop but another one needs to be done since there is still an issue with the NAGIOS system
  • Test with the PBLM is still outstanding and will be done today
  • The systems should be in a fully functional state again this afternoon!

FXE

  • Vacuum gate valves can be controlled now after some work by J. Tolkiehn. Ion pumps are not controlled yet
  • Next update of firmware should resolve the problem with ion pumps 
  • Cables for loops 4&5 were in the water and hence work on these components has to wait

SPB

  • Full E2E test was done for the PSLIT.
  • Further tests will have to wait for fixes to cables

PLC

  • AE works on AGIPD today and will go back to instruments tomorrow
  • An update to the EPS needs to be done at some point in the near future to implement the end switches of the screens
  • When cables are fixed and tested, all modules in the respective loop have to be pulled out as they are daisy-chained

KARABO

  • New system implemented for deploying new versions that allows quick switch and possible roll-back
  • Script system implemented that performs schema evolution for scenes. Hence, old scenes will be adapted to changes automatically. This is important for the many scenes developed by the PCT.
  • Deployment of next Karabo version with bug fixes to be done before machine restart this afternoon

 

 

Entry   Vacuum Loop, posted by NEREA JARDON on 31 May 2017, 10:45 

Dear all, we will proceed with the update of the Vacuum loop.

Thank you!

Entry   Vacuum Loop, posted by NEREA JARDON on 30 May 2017, 20:42 

Dear all,

We have detected with Karabo guys that there was a problem in the IonPumps in SASE1. The IonPumps are working, Raúl went to the Tunnel to check the controllers in XTD9 to confirm that.

According with Raúl and CAS people, we have arranged to do the next Vacuum update tomorrow early in the morning. I will post a new entry to let you know and I will contact now WP74 people in order to be quickly with the loop update tomorrow.

Thank you and sorry for the disturbing.

Entry   Motion loop, posted by NEREA JARDON on 30 May 2017, 19:43 

Dear all, we will run another update in the Motion loop.

Thank you

Entry   Vacuum Loop, posted by NEREA JARDON on 30 May 2017, 18:32 

We will run again an update in the Vacuum loop, just to fix small bug detected.

Thank you

Entry   Motion loop, posted by NEREA JARDON on 30 May 2017, 18:14 

Dear all,

I will make an update of the Motion loop in the next minutes, all the systems are in safe state.

Thank you

Entry   Vacuum Loop, posted by NEREA JARDON on 30 May 2017, 15:52 

Dear all,

We will run the update of the Vacuum loop in the next half hour.

Thank you!

Entry   Vacuum Loop, posted by NEREA JARDON on 30 May 2017, 11:08 

Dear all,

Sorry, my last message was not correct. We will do the hardware changes when we have prepared the Vacuum update also.

Thank you

Entry   Vacuum Loop, posted by NEREA JARDON on 30 May 2017, 10:56 

Dear all,

It is needed to add two digital input terminals in Rack 1.17 and 1.18 in XTD9 for the vacuum loop, and Denis will do it in the next minutes. Therefore you will loose communication for those motion racks.

Thank you

 

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 29 May 2017, 16:30 

 General

  • Photon tunnels are open until Wednesday afternoon due to the flooding on the weekend. 
  • The down time should be used to do important fixes/upgrades
  • XTD9 can stay open all week depending on the decision of the PCT
  • Photon commissioning successfully brought beam to the end of both the SPB and FXE beam lines

XTDs

  • Stability problem of SR imager is still being worked on by A. Parenti (CAS)
  • A new version of Karabo with many fixes is currently being tested and will be deployed once the test results appear satisfactory
  • Test of the PBLM motors still need to be done in XTD9. This requires an update of the motion loop that should be done today or tomorrow
  • There is also the need of an update of the vacuum loop. This should also be done during the down time

FXE

  • Problem still exist with vacuum controls. The problem appears to be understood and seems to be on the PLC side. FXE uses ion pumps with an analog output that does not interface with the alarm level settings.J. Tolkiehn is working on it
  • Work progresses on motor testing
  • FXE requests firmware for loop 7. But this work interferes with the priority on the vacuum.

SPB

  • Loop 1 is now fully available with all modules
  • Loop 2 is available with only the first module. The other modules are away for modification
  • Due to the flooding the connectors cannot be attached until cables have dried and have been re-tested

PLC

  • AE will work again on AGIPD this week. This limits resources for the instruments

KARABO

  • Problem with X2 timer interface is solved. But PCT apparently still uses the DOOCS interface.
  • Waiting for the go ahead to release the next KARABO version
  • Work progresses in parallel to intergrate DAQ into KARABO. This will be the next version after the bug-fix version

ITDM

  • The announced update of the network switches will be  done on Tuesday morning and will result in a 5 minute network interrupt

 

Entry   Status of beam commissioning, posted by Harald Sinn on 27 May 2017, 16:31 

We got the beam to the end of XTD9 onto the SPB screen and FXE Pop-in (the SPB pop-in does not work).

Everything looks quite good and the beam is quite stable.

Lasing photon engery is around 6.2 keV and 200-300 mJ per pulse.

Harald

 

Entry   CAS OCD phone numbers for the weekend, posted by Gabriele Giovanetti on 26 May 2017, 18:01 
  • Friday 7 PM - Saturday 8.00 AM    : 98060
  • Saturday 8.00 AM - Sunday 8.00 AM : 98054
  • Sunday 8.00 AM - Monday 8.00 AM   : 98055


Entry   Status after 0930 meeting, posted by Tobias Haas on 24 May 2017, 10:39 

 General:

  • DESY will try to lase again at higher energies during the next days
  • XTD9 will searched an interlocked this afternoon at 1400 as PCT will try to transport photons as far as possible
  • Company Wille has started to work on the radiation interlocks in SASE1. New TÜV date on 20 June and rehearsal on 14 June
  • Instruments should be prepared that on these days

 

XTDs:

  • CAS (A. Parenti) is still working on the instability problem of the SR imager. For the moment the workaround with reduced resolution (mono-8) seems to acceptable
  • One (non-existing) pump needs to be removed from interlock conditions in XTD9. Otherwise interlock blocks one gate valve
  • Filter was taken off the pop-in in XTD2
  • Tests for PBLMs still need to be done in XTD9 when it re-opens next week

FXE:

  • Problems exist with vacuum controls. J. Tolkiehn is currently working on it
  • Firmware of commissioning crate was upgraded
  • Test of Johan Spectrometer was done with test crate
  • CRL test are next

SPB:

  • Still waiting for firmware for loops 1&2. AE is almost ready and will deploy today
  • All cables are ready for Optics hutch
  • AE is currently pushing in the crates

PLC:

  • DESY MPS claims that a cable from the interlock to an AE crate is still missing. 
  • AE got vital information from MPS just a few days ago and is still waiting for info from the laser interlocks

KARABO:

  • CAS is working on a version with bug fixes for stability. Will be deployed when appropriately test and when a break is available
  • X2 timer interface still has issues. A. Sienzi is working on it

ITDM:

  • An update of network switches is needed. This will be scheduled for next week. Details to be discussed during Monday 1500 BKR meeting

 

Entry   Reminder: SASE1 Readiness Dispatch @ 0930 today, posted by Tobias Haas on 24 May 2017, 09:06 

see you there 

Entry   Status and Plans after 09:30 Meeting, posted by Tobias Haas on 22 May 2017, 13:31 
General:
  • No break this week on Wednesday. (Wednesday breaks for XTD10 should start next week)
  • Possibility of ZZ access to XTDs on Tuesday from 0700 - 1500. Harald organises the access for vacuum and
    diagnostics. No ZZ without previous experience
  • Expect XTD9 to close next week.

XTDs:
- SR imager crashed several times on the weekend. D. Görries spent a lot of time investigating and found that
when the configuration of the camera is set to mono-8 it runs stably. This indicates that there is a network
bandwidth issue
- D. Görries also had to restart the KARABO server for the MCP. One motor was working but the other one had
hardware problem and requires an access to the tunnel
- Tests for ELMO motor on PBLMs this week by Mahadi and A. Silenzi. N. Gerassimova is on holidays but agreed to
the test
- A. Parenti would like to deploy SW with added debugging functionality for imagers

FXE
- A. Galler and W. Gawelda are not available this week
- D. Görries reports that there are still problems with controlling the vacuum, I. e. gauges, pumps, valves,
fast valve. Some are related to cabling problems that are currently being fixed
- A firmware upgrade is requested for the commissioning crate. Will be discussed in detail with AE

SPB
- Work by AE on AGIPD for this week was called off as detector consortium wants to work on the hardware
- AE will concentrate on commissioning loops 1&2 for the optics hutch
- Firmware for loops 1&2 needs to be first regenerated
- All cabling problems should be solved by tonight
- All crates can then be pushed in
- All cables should be done except for 4 or 5 in the instrument hutch

KARABO

- The bug that results in devices not updating in the GUI server still persists
- Users are requested to inform A. Silenzi as soon as they discover this behaviour

Plan for the next days
- Start with SPB optics hutch
- Update firmware of FXE commissioning crate
- Test ELmo motor in XTD9
Entry   AE PLC OCD, posted by Tobias Freyermuth on 22 May 2017, 11:06 

From now on the PLC OCD contact person will have always the phone number:

  9 8040

Entry   SASE1 Imager FR, posted by Dennis Goeries on 21 May 2017, 17:10 

Dear all,

we are experiencing constantly crashes with the photonic science camera in the SA1 imager FR. We found now out

- If the pixel format is set to Mono16 the camera will most likely crash, go in error.

- Before instantiation the camera may show Mono16. During connection Karabo but gets a fresh update and the field in the scene switches to Mono8.

 

Please don't apply Mono16 again.

Best wishes, Dennis

Entry   CAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3, posted by David Hickin on 21 May 2017, 15:02 

Contacted at home 21:30 19.05. Request for support starting SA1_XTD2_MCP/CDC/MCP3 on cppServer/sa1_utca_17.

Located project and device server. Attempted to start SA1_XTD2_MCP/CDC/MCP3. Issue was missing fastAdc plugin. Found info on sa1_utca_17 in commissioning guidelines: say server is exflutc106.

Tried to ssh in to exflutc106 unsuccessfully. Phoned back 23:49 to give status. Informed that accelerator not running due to lightning. Suggested that if I couldn't fix issue soon they should contact next OCD person from 8:00.

Tried further to fix problem. Found section in commissioning guidelines: tried ssh -Y -l xctrl.Still couldn't access exflutc106. Wrote up notes. Sent to next contact. Stopped work 1:45.

    Reply   CAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3, posted by David Hickin on 21 May 2017, 16:28 

David Hickin wrote:

Contacted at home 21:30 19.05. Request for support starting SA1_XTD2_MCP/CDC/MCP3 on cppServer/sa1_utca_17.

Located project and device server. Attempted to start SA1_XTD2_MCP/CDC/MCP3. Issue was missing fastAdc plugin. Found info on sa1_utca_17 in commissioning guidelines: say server is exflutc106.

Tried to ssh in to exflutc106 unsuccessfully. Phoned back 23:49 to give status. Informed that accelerator not running due to lightning. Suggested that if I couldn't fix issue soon they should contact next OCD person from 8:00.

Tried further to fix problem. Found section in commissioning guidelines: tried ssh -Y -l xctrl.Still couldn't access exflutc106. Wrote up notes. Sent to next contact. Stopped work 1:45.

* Apparently the device installation failed with ansible on utca_17. Even worse, the requested  utca_18 is not even know, cannot be pinged and nothing is documented.

** Global problem: Karabo develop, checkout and install both return zero exit status from git.

** Device problem: The dependency was declared wrong in the fastAdc

FastAdc installed by hand, dependency built by hand.

Devices can now be instantiated. For the record, with the following problem

INFO  SA1_XTD2_MCP/ADC/MCP2  : Reset simply calls initialize() method now.
INFO  SA1_XTD2_MCP/ADC/MCP2  : Connecting to hardware driver, setting up the device's namespace...
ERROR  SA1_XTD2_MCP/ADC/MCP2  : Cannot create IibusMap object for /dev/pciedevs6 and maps in /home/utcaadm/maps since:
1. Exception =====>  {
    Exception Type....:  IO Exception
    Message...........:  Open '/dev/pciedevs6' : No such file or directory
    File..............:  /[...]/src/IibusMapImpl.cc
    Function..........:  utca::IibusMapImpl::IibusMapImpl(const string&, const string&, bool)
    Line Number.......:  32
    Timestamp.........:  2017-May-21 14:59:57.856975
}


INFO  SA1_XTD2_MCP/ADC/MCP2  : Reset simply calls initialize() method now.
INFO  SA1_XTD2_MCP/ADC/MCP2  : Connecting to hardware driver, setting up the device's namespace...
ERROR  SA1_XTD2_MCP/ADC/MCP2  : Cannot create IibusMap object for /dev/pciedevs6 and maps in /home/utcaadm/maps since:
1. Exception =====>  {
    Exception Type....:  IO Exception
    Message...........:  Open '/dev/pciedevs6' : No such file or directory
    File..............:  /[...]/src/IibusMapImpl.cc
    Function..........:  utca::IibusMapImpl::IibusMapImpl(const string&, const string&, bool)
    Line Number.......:  32
    Timestamp.........:  2017-May-21 15:56:50.638370
}
 

 

 

 

       Reply   CAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3, posted by David Hickin on 21 May 2017, 16:29 

David Hickin wrote:

David Hickin wrote:

Contacted at home 21:30 19.05. Request for support starting SA1_XTD2_MCP/CDC/MCP3 on cppServer/sa1_utca_17.

Located project and device server. Attempted to start SA1_XTD2_MCP/CDC/MCP3. Issue was missing fastAdc plugin. Found info on sa1_utca_17 in commissioning guidelines: say server is exflutc106.

Tried to ssh in to exflutc106 unsuccessfully. Phoned back 23:49 to give status. Informed that accelerator not running due to lightning. Suggested that if I couldn't fix issue soon they should contact next OCD person from 8:00.

Tried further to fix problem. Found section in commissioning guidelines: tried ssh -Y -l xctrl.Still couldn't access exflutc106. Wrote up notes. Sent to next contact. Stopped work 1:45.

* Apparently the device installation failed with ansible on utca_17. Even worse, the requested  utca_18 is not even know, cannot be pinged and nothing is documented.

** Global problem: Karabo develop, checkout and install both return zero exit status from git.

** Device problem: The dependency was declared wrong in the fastAdc

FastAdc installed by hand, dependency built by hand.

Devices can now be instantiated. For the record, with the following problem

INFO  SA1_XTD2_MCP/ADC/MCP2  : Reset simply calls initialize() method now.
INFO  SA1_XTD2_MCP/ADC/MCP2  : Connecting to hardware driver, setting up the device's namespace...
ERROR  SA1_XTD2_MCP/ADC/MCP2  : Cannot create IibusMap object for /dev/pciedevs6 and maps in /home/utcaadm/maps since:
1. Exception =====>  {
    Exception Type....:  IO Exception
    Message...........:  Open '/dev/pciedevs6' : No such file or directory
    File..............:  /[...]/src/IibusMapImpl.cc
    Function..........:  utca::IibusMapImpl::IibusMapImpl(const string&, const string&, bool)
    Line Number.......:  32
    Timestamp.........:  2017-May-21 14:59:57.856975
}


INFO  SA1_XTD2_MCP/ADC/MCP2  : Reset simply calls initialize() method now.
INFO  SA1_XTD2_MCP/ADC/MCP2  : Connecting to hardware driver, setting up the device's namespace...
ERROR  SA1_XTD2_MCP/ADC/MCP2  : Cannot create IibusMap object for /dev/pciedevs6 and maps in /home/utcaadm/maps since:
1. Exception =====>  {
    Exception Type....:  IO Exception
    Message...........:  Open '/dev/pciedevs6' : No such file or directory
    File..............:  /[...]/src/IibusMapImpl.cc
    Function..........:  utca::IibusMapImpl::IibusMapImpl(const string&, const string&, bool)
    Line Number.......:  32
    Timestamp.........:  2017-May-21 15:56:50.638370
}
 

 

 

 

 For record, the last message was me (DG)

          Reply   CAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3, posted by David Hickin on 21 May 2017, 16:50 

David Hickin wrote:

David Hickin wrote:

David Hickin wrote:

Contacted at home 21:30 19.05. Request for support starting SA1_XTD2_MCP/CDC/MCP3 on cppServer/sa1_utca_17.

Located project and device server. Attempted to start SA1_XTD2_MCP/CDC/MCP3. Issue was missing fastAdc plugin. Found info on sa1_utca_17 in commissioning guidelines: say server is exflutc106.

Tried to ssh in to exflutc106 unsuccessfully. Phoned back 23:49 to give status. Informed that accelerator not running due to lightning. Suggested that if I couldn't fix issue soon they should contact next OCD person from 8:00.

Tried further to fix problem. Found section in commissioning guidelines: tried ssh -Y -l xctrl.Still couldn't access exflutc106. Wrote up notes. Sent to next contact. Stopped work 1:45.

* Apparently the device installation failed with ansible on utca_17. Even worse, the requested  utca_18 is not even know, cannot be pinged and nothing is documented.

** Global problem: Karabo develop, checkout and install both return zero exit status from git.

** Device problem: The dependency was declared wrong in the fastAdc

FastAdc installed by hand, dependency built by hand.

Devices can now be instantiated. For the record, with the following problem

INFO  SA1_XTD2_MCP/ADC/MCP2  : Reset simply calls initialize() method now.
INFO  SA1_XTD2_MCP/ADC/MCP2  : Connecting to hardware driver, setting up the device's namespace...
ERROR  SA1_XTD2_MCP/ADC/MCP2  : Cannot create IibusMap object for /dev/pciedevs6 and maps in /home/utcaadm/maps since:
1. Exception =====>  {
    Exception Type....:  IO Exception
    Message...........:  Open '/dev/pciedevs6' : No such file or directory
    File..............:  /[...]/src/IibusMapImpl.cc
    Function..........:  utca::IibusMapImpl::IibusMapImpl(const string&, const string&, bool)
    Line Number.......:  32
    Timestamp.........:  2017-May-21 14:59:57.856975
}


INFO  SA1_XTD2_MCP/ADC/MCP2  : Reset simply calls initialize() method now.
INFO  SA1_XTD2_MCP/ADC/MCP2  : Connecting to hardware driver, setting up the device's namespace...
ERROR  SA1_XTD2_MCP/ADC/MCP2  : Cannot create IibusMap object for /dev/pciedevs6 and maps in /home/utcaadm/maps since:
1. Exception =====>  {
    Exception Type....:  IO Exception
    Message...........:  Open '/dev/pciedevs6' : No such file or directory
    File..............:  /[...]/src/IibusMapImpl.cc
    Function..........:  utca::IibusMapImpl::IibusMapImpl(const string&, const string&, bool)
    Line Number.......:  32
    Timestamp.........:  2017-May-21 15:56:50.638370
}
 

 

 

 

 For record, the last message was me (DG)

 A deeper look into the dev namespace provides only pciedev0 and pciedevs3 are available. (DG)

Entry   AE OCD Mai 19 -- Mai 22, posted by Nicola Coppola on 19 May 2017, 15:42 

AE on call service:

    Contact person:

        Nicola Coppola

    Phone:

        9 - 5627

Entry   Update of Instrument component priority list , posted by Monica Aresté on 19 May 2017, 12:46 170519_Instrument_Components-Priority-list.xlsx

Find attached the Instrument Component priority list discussed this morning.

Regards,

Monica

 

Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 19 May 2017, 11:30 

General (T. Haas)

  • Due to problems with interlock cabling the approval date with the TÜV on 1 June has been cancelled
  • The MB, SASE1 Instruments, AE, CAS  and PSPO met yesterday and agreed that in view of the schedule risks with technical commissioning the focus of the next weeks should be enabling both FXE and SPB/SFX to accept beam for doing radiation safety measurements no later then end of June.
  • SPB/SFX were asked to identify the minimum functionality for this goal. The respective components will be marked in the component priority list

FXE (A. Galler)

  • So far work has concentrated on motors
  • This week PSLITs and BIU2 successfully underwent E2E tests
  • JJ was back this week to fix some problems on patch panels
  • Johan spectrometer is back in the hutch

SPB (B. Weinhausen)

  • Work continued on the tunnel loops.
  • The power supply problem with photonics cameras has been solved by AE (Additional 12V terminals installed)
  • Triggers for the cameras are working
  • Valve between optics hutch and tunnel vacuum was opened for the first time
  • There is still the unsolved problem with the TECHNOSOFT motor.
  • Work will now move to the optics hutch.

Laser (T. Jezynski)

  • Alarm systems are (smoke, gas etc) are now connected
  • Big problems with AC systems. The effort with FM to stabilise the humidity now results in temperature swings of up to 2 degrees. The same problem also appears in the instrument laser hutches
  • AC problems lead to large instabilities of the laser
  • Alignment beam is now delivered to both instrument laser hutches
  • No new information was received on the topic of optical synchronisation

Detector (M. Kuster)

  • Management decided that LPD will be moved to FXE in June, in weeks 23/24 to allow further testing of AGIPD in HERA-S
  • Interlock test on AGIPD continue
  • CAS is working on integrating the DAQ of AGIPD. When this is done an update of Karabo is needed. This will not happen this week and hence not before S. Hauf is on holidays

Electronics (P. Gessler)

  • There is still some work for the tunnels:
  • For integration of MCP tests were done in the lab yesterday. One of the two axes is working, the other one not yet
  • Tests for PBLMs could not be done as there was no common window between on N. Gerassimova and M. Umar. Tests could be done by M. Umar if N. Gerassimova agrees. She is on holidays for two days next week
  • The interface of the vacuum loop and the EPS loop to the DESY MPS requires additional work for XTD9 in the next days
  • Work also continues on AGIPD for one more day
  • There are some absences due to sickness and holidays that also slow down the work

Karabo (A. Silenzi/B. Brockhauser)

  • There will be a swap of the GUI server today to allow debugging the issue that the device states are sometimes not properly shown. People will need to re-connect
  • Tests of TECHNOSOFT motor were successful. (Does not include encoder needed for SPB motor)
  • There is a fundamental problem with the Photonics camera used in the SR imager. It has a rolling shutter that does not allow to get well-timed, triggered images. The same issue might be persent for the HIREX camera
  • The KARABO/DOOCS driver has been re-established. This should allow to set time delays directly from Karabo again

Discussion/Next Steps

  • SPB should start with technical commissioning of OPTICS hutch
  • Instruments identify components needed for beam in the hutch for radiation safety measurements
  • AE finishes pending tunnel work and then focus on SPB/SFX and FXE
  • Displatch meetings on Monday and Wednesday at 09:30 in XHQ/MCR (*not at DESY*)
Entry   Motion loop, posted by NEREA JARDON on 18 May 2017, 16:36 

Dear all,

I have already contacted Andreas Koch, and Alessandro has contacted the BKR in order to do a new update of the motion loop because of one small bug detected.

I will do the update in the next few minutes.

Thank you,

Entry   Imager status, posted by Andreas Koch on 18 May 2017, 16:32 

After the update of the PLC firmware, the imagers are in following status:

SR: auto gain off seems to work, correct image, screens are out. Beamview just crashed, I asked Alessandro and Dennis to have a look.

Pop-In: Everything fine.

FEL: strange image. We had this before, no idea what the reason is. I will keep trying.

Another update of the motion loop is planned later. Contact Nerea for details.

Entry   OCD AE Group, posted by NEREA JARDON on 18 May 2017, 15:30 

Dear all,

The OCD AE numbers for the following days will be:

PLC support: 9-8040

DAQ Electronics (incl. timing, MicroTCA) Support:  9-8041

 

If there are any change in the numbers, we will let you know.

Thank you.

 

Entry   Motion loop, posted by NEREA JARDON on 18 May 2017, 13:38 

The Motion loop is again up and running.

Thank you

Entry   Motion loop, posted by NEREA JARDON on 18 May 2017, 12:18 

Dear all,

The motion loop will be updated in 5 minutes. The IMGs are already in safe state, please do not operate nothing. I have already contacted the control room and Harald Sinn as representative of the commissioning team.

Thank you!

Entry   Vacuum issue in XTD9 during cycling of PLC loop yesterday, posted by Jan Grünert on 18 May 2017, 11:57 

During the usual recovery procedure after the planned and announced cycling of the SASE1 VAC loop yesterday, we observed a serious mistake by somebody:

The gatevalve(s) of the DP section in XTD9 were opened before the related turbo pumps were (fully) operating.
This caused a pressure increase on the UHV-side to briefly 1E-2mbar (!) and for about 30min to 1E-3mbar before this was cured.
Essentially the prevacuum side gases entered the UHV-side through the DP-turbos, that's not good at all.
Especially it would be tragic, if we had the XGM high voltages on during such a mistake (which was luckily not the case)
Below is the pressure record of the XGM UHV vacuum gauge.

This must not happen again ! Therefore please observe the following points:
1) after PLC reboots, these valves shall only be opened by the experts who know the correct sequence
2) the pressures and TP operation must be verified before opening these valves.
3) WP74 (e.g. Jan or Theo) and VAC (e.g. Raul) must be informed about a planned recycling of the VAC loop (this is an established scheme and always worked very well, also yesterday)

https://ttfinfo.desy.de/XFEL-WP74-elog/data/2017/20/17.05/2017-05-17T14:02:31-03.jpg

Explanations to graph:
13h30 the preparation of the cycling started with closing the XGM vatterfly valves by WP74
14h00 apparently the gate valves of the entire gas section closed at the PLC reboot which increases slightly the pressure at the XGM
around 14h18 the pressure shoots up although nothing changed at the XGM, and it is found that DP gatevalves are open without full operation of the associated turbos
around 14h50 (after some cross-checking and phone calls) the concerned gate valves were closed and the vatterfly valves at the XGM were opened to bring the XGM (and the entire gas section) down to about 1E-7mbar

 

Entry   Motion loop, posted by NEREA JARDON on 17 May 2017, 17:51 

Dear all,

The Motion loop will be updated tomorrow due to some delays during the day. It will include the MCP XTD2 X movement.

Thank you and sorry for the inconvenience.

Entry   CAS OCD, posted by Sergey Esenov on 17 May 2017, 16:17 

 CAS on call service for the night 98057

Entry   Vacuum Loop, posted by NEREA JARDON on 17 May 2017, 13:57 

Dear all,

The Vacuum Loop will be updated now. You will be able to connect to it again in few minutes.

Thank you,

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 17 May 2017, 11:55 

 Interlock in XTD10 is broken today and tunnel is open until 15:00

General:

  • Unfortunately, info on access to XTD10 came too late for Vacuum group to organise the work in XTD10
  • Technical issues and coordination between AE/CAS and PCT/Instruments continues to happen via SASE1 Readiness Log

Vacuum:

  • Issue of spurious beam aborts due to short term vacuum spikes in XGM is solved (respective gauges taken out of interlock?)
  • Change to interlock logic was requested by H. Sinn: V0 always closes if one gate valve closes) The reason is that after V0 is closed the accelerator has beam permission and can continue
  • This logic will now be implemented in the next update by AE

Imagers:

  • Problems with several photonics cameras for data collection exist. The data transfer is sensitive to packet losses. Hence dedicated servers need to be set up to avoid loss of data.
  • ITDM has provided one additional server in balcony room. Eventually a dedicated server should be set up in the tunnel
  • Maybe the way the camera sends the data could also be optimised
  • Auto-scaling switch problem has not been tackled yet and is considered second priority after solving general readout problem

PLC:

  • Fix for MC2 lib for TECHNOSOFT motors is ready. Tests together with N. Gerassimova can start today after motion loop update 
  • SPB can perform a parallel test on the PSLITs
  • Motion loop and vacuum loop updates are scheduled for 12:00. 

KARABO:

  • A bug was found where device clients drop messages and hence the GUI looses the state of the device
  • There is a fix that needs to be deployed.  This should happen in parallel to the cycling of the loops between 12:00 and 14:00

Next Steps:

  • Cycling of vacuum and motion loop at 12:00. T. Freyermuth informs the Photon Commissioning team
  • Update of Karabo betweem 12:00 and 14:00
  • Tests of PBLM with updated MC2 lib today
  • Tests of PSLITS with updated MC2 lib by SPB

 

Entry   Reminder S1R Dispatch at 09:30 today in front of MCR (Mockup Control Room), posted by Tobias Haas on 17 May 2017, 08:52 
 
Entry   cycling of SASE1 tunnel VAC loop (if needed), posted by Jan Grünert on 16 May 2017, 22:54 

If the recycling of the VAC loop for XTD2+9 is required as I understand from AE,
tomorrow would be a good time because there is no beam (in SASE1 until at least 15h).

After about 10h30 would be ok for me.

@ AE : Please call me on my mobile when you want to start - I might be in XTD10.

@ CAS : please have someone ready to "reconnect karabo to Beckhoff"

Entry   Request for imager checks, posted by Andreas Koch on 16 May 2017, 15:59 

Since tomorrow there is no beam I want to use the time for some checks of the imagers in XTD2. Please, let the motion loop up if possible until 10 am, otherwise let me know.

Entry   CAS On-Call Duty Planning (Until 11/06), posted by Hugo Silva Santos on 16 May 2017, 14:55 

 Dear All,

I would like to share the CAS OCD Planning until 11/06: https://goo.gl/LL6vO1

 

In this planning, we show the numbers that can be called in case of incidents. Unfortunately, we are still trying to have a single number for all phones.
 
PS: I am sorry for the google.docs document, but once we are keeping it in a collaborative way in CAS, share the link with all of you will guarantee that you can see the updated version.
 
Best,
Hugo
Entry   Motion loop, posted by NEREA JARDON on 16 May 2017, 13:50 

Dear all,

Due to local test needed in Rack 1.18 for the Motion loop, it will be interrupted only in Rack 1.18 XTD9 from now till tests finish. It will not affect any other part of the Motion loop.

Thank you.

Entry   OCD CAS, posted by Thomas Michelat on 15 May 2017, 22:17 

 Dear all,

The OCD number for tonight (15/05) for the CAS group is 98053.

thanks

Entry   OCD AE Group, posted by NEREA JARDON on 15 May 2017, 11:32 

Dear all,

The OCD AE numbers for the following days will be:

PLC support: 9-8040 / 0151-68822383

DAQ Electronics (incl. timing, MicroTCA) Support:  9-6941

 

If there are any change in the numbers, we will let you know.

Thank you.

Entry   Status and plans after 09:00 meeting in BKR, posted by Tobias Haas on 15 May 2017, 11:02 

 Issues observed by PCT over the weekend (from H. Sinn entry in the PCT log)

- The interlock of the vacuum valves worked as expected. However, we had two times the gas section around the XGM tripping the beam, because the gate valves around the XGM were closing. The reason for these trips will be investigated (probably noise on one of the involved pressure gauges). In the future it would be good to change the Vacuum-to-MPS interlock such that V0 always closes, if any of the other gate vales closes. Then the accelerator permission would come automatically come back after the trip. However re-booting of the vacuum loop needs to be planned (trips the DESY beam permission and potentially shuts down the turbo pumps). 

- The SR Imager may loose steps when moving larger distances (speed too high?)

- Several general problems of Karabo were observed, which make live difficult: For example, the 'V0 closed' and 'B4C in' indication on our main screen may just lock, even when the state of the device is changing (was observed mostly on GUI server1). It means that the status displayed on a scene can be in general not be trusted. In many cases we observed that connecting freshly opened scenes to devices take unacceptably long times (many minutes or never).  The policy of saving projects and sub-projects leads to overwriting changes, if more people work on projects and projects stay open for longer time.  

- The fact that the PLC does actually not store values through a reboot causes many problems. It basically means that motor positions are lost (set to zero) at every reboot and can be only recovered, if homing or absolute encoders exist. Also that positions of motors cannot be reset to their theoretical values means that in practice the state before the PLC reboot cannot be recovered by resetting the values.

- The imagers, in particular the SR-imager, caused a lot of problems because they were often crashing and require advanced and complicated procedures to make them run again (e.g. setting after re-instantiating the imagers are lost and come up with wrong pre-sets). The SR-imager does auto-scaling on the intensity, also when this is disabled in the software. This make the imager only useful for qualitative studies (e.g. not for gain curve or flux measurements).

General

  • Parameters of motors get lost after reboot of the PLC
  • Setting trigger delays can currently only be done with special authorisation from DOOCS. 
  • Suggested solution from AE: Hardwire the correct defaults in the firmware
  • A better procedure is needed to communicate the parameters between hardware experts and AE
  • L. Samoylova suggests that CAS person on call contacts BKR once per day to establish contact and get an overall impression
  • The support of CAS during the weekend was greatly appreciated

Vacuum

  • No calls to experts over the weekend
  • Issue with the XGM vacuum (spurious triggers of the interlock) needs to be fixed 
  • Interlock logic should be changed so that V0 always closes if one of the gate valves closes

Imagers

  • SR Imager crashed frequently and was hard to bring back
  • Auto-scaling of SR-imager cannot be switched off. This needs fixing with high priority

XGM

  • Commissioning starts today
  • See above about vacuum issues

PLC

  • No calls over the weekend to the experts
  • Firmware for MC2 lib (TECHNOSOFT motors) is prepared and waiting for tests

Karabo

  • CAS was called a few times on the weekend
  • Running more than one camera at the same time appears  to cause crashes. Possibly network bandwidth is insufficient
  • A procedure can be set up to read out the motor parameters at a well defined point in time for storing them in the firmware 
  • Setting trigger delays should be made to work from Karabo

Work for next days

  • Karabo test with MC2 Lib in the lab. As soon as this is successful it will continue in XTD9. Will be done on the SPB attenuator as N. Gerassimova is not available for PBLM tests due to a beam time
  • Fix the Photonics camera driver so that auto-scaling can be turned off

 

 
Entry   CAS OCD from today to Monday, posted by Valerii Bondar on 12 May 2017, 15:58 

Dear all,

CAS phone numbers for OCD:

Friday: Alessandro (98054),

Saturday: Valerii (98053),

Sunday: Gabriele (98060),

thank you.

Entry   OCD AE Group, posted by NEREA JARDON on 12 May 2017, 15:37 

Dear all,

The OCD numbers for this weekend and today will be:

PLC Support: 9-8040 / 0151-68822383

DAQ Electronics (incl. timing, MicroTCA) Support: 9-8041 / 0151-68822386

Thank you.

Entry   V0 open!, posted by Harald Sinn on 12 May 2017, 13:59 IMG_4609.jpg

V0 is open now!

Janni opened this morning at 11:00 the V0 valve towards the accelerator vacuum.

We removed the B4C absorber in front of the valve and now the spontaneous radiation can enter the Schenefeld vacuum. 

The interlock conditions for Vacuum loop and EPS loops towards the DESY MPS were tested and they are now enabled. 

This means that rebooting SA1 VACUUM  or EPS loop will stop the beam during the reboot (therefore call 4500 before you do it).

 

IMG_4609.jpg 

Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 12 May 2017, 13:33 AttendanceS1R120517.pdf

Focus of meeting is on SASE1 Instruments, Laser and Detectors

SPB (B. Weinhausen)

  • All motors in the SPB tunnel loop have been commissioned except for one TECHNOSOFT motor where the updated driver was not yet available
  • Comment by P. Gessler:
    • The updated MC2 lib was deployed yesterday evening. Testing should be possible now
  • The second camera of the screen broke. Concern exists over possible overvoltage in the power that comes directly from the PLC
  • All encoders are working
  • The vacuum in the Optics hutch is closed
  • Info by A. Violante:
    • All cabling in D02/D03 is done
    • There are a few damaged connectors that prevent pushing in the modules. This should be fixed on Monday
    • Pins are swapped in one connector. Will be fixed locally
  • Comment by P. Gessler:
    • This week AE was busy with AGIPD and tunnels
    • Next week resources should be available to support start of commissioning loop 1 

FXE (A. Galler)

  • E2E tests are progressing 
  • A recent update of the Beckhoff firmware generated new problems with encoders
  • Info from T. Korsch:
    • The vacuum in the hutch is closed and has reached 5e-7 mb
    • There is a minor leak in one of the bellows
    • Compressed air is working to operate the gate valves
    • Vacuum gauges can be read out remotely
  • Attention should be paid to being able to read out detectors, e. g. diodes

Laser (D. Kane/M. Lederer)

  • Slides were provided in INDICO with a detailed account of the status. Only Key points are summarised here:
    • Hutch infrastructure is working in general and temperature stability is ok but laser group is lacking access to controlling the parameters, humidity is oscillating and smoke detectors are not connected
    • Pre-assembly of PP laser is 75% done
    • Beam delivery to instruments is on the list now
    • Synchronisation with optical system might not be available before October
    • Control are generally working and software has improved a lot but some stages cannot be controlled and Karabo appears still to have some resource leaks

Detectors (M. Kuster)

  • LPD is in E2E tests and AGIPD is still being integrated into the XFEL environment
  • This week it was possible to run the DAQ chain on LPD for the first time
  • All tests on LPD including data taking in the X-Ray chamber in HERA-S should be done by end June
  • Situation with AGIPD is more difficult as basic integration is still not complete

Discussion

  • Follow up on progress with instruments, laser and detectors will continue in S1R meeting from now on
  • The S1R dispatch meeting takes place on Mondays 09:00 in BKR and on Wednesday 09:30 in XHQ 
  • Groups that require help from AE and CAS and that need to coordinate with other activities should attend
Entry   New Deployment of Karabo for the SASE1 control machines., posted by Alessandro Silenzi on 11 May 2017, 12:43 download.sh

I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.

To install a new version of Karabo use the script attached on your terminal

move your the karabo directory to a backup or remove it.

to backup:
$ mv ~/karabo ~/karabo.bkp
 

to remove:
$ rm -fr ~/karabo

then execute:
$ bash PATHTO/download.sh

    Reply   New Deployment of Karabo for the SASE1 control machines., posted by Alessandro Silenzi on 11 May 2017, 15:08 

Alessandro Silenzi wrote:

I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.

To install a new version of Karabo use the script attached on your terminal

move your the karabo directory to a backup or remove it.

to backup:
$ mv ~/karabo ~/karabo.bkp
 

to remove:
$ rm -fr ~/karabo

then execute:
$ bash PATHTO/download.sh

 The system is up.

The users using virtual machines will encounter problems installing karabo 2.1.10 in the way that was described.
Further instructions will come later in the day

       Reply   New Deployment of Karabo for the SASE1 control machines., posted by Alessandro Silenzi on 12 May 2017, 13:19 

Alessandro Silenzi wrote:

Alessandro Silenzi wrote:

I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.

To install a new version of Karabo use the script attached on your terminal

move your the karabo directory to a backup or remove it.

to backup:
$ mv ~/karabo ~/karabo.bkp
 

to remove:
$ rm -fr ~/karabo

then execute:
$ bash PATHTO/download.sh

 The system is up.

The users using virtual machines will encounter problems installing karabo 2.1.10 in the way that was described.
Further instructions will come later in the day

 for Users with a VM:
- use the download script
- Remove the karabo directory:
   $ rm -fr ~/karabo 
- then execute:
   $ bash PATHTO/download.sh

Sorry for the delayed instructions

 

Entry   Update of Instrument component priority list , posted by Monica Aresté on 12 May 2017, 12:26 170512_Instrument_Components-Priority-list.xlsx

Find attached the Instrument Component priority list discussed this morning.

Regards,

Monica

Entry   Motion loop, posted by NEREA JARDON on 12 May 2017, 09:23 

Dear all,

Due to local test needed in Rack 1.18 for the Motion loop, the loop will be interrupted only in Rack 1.18 XTD9 from now till the people in the Tunnel finish the tests. It will not affect any other part of the Motion loop.

Thank you.

Entry   Restart vacuum loop now, posted by Harald Sinn on 12 May 2017, 08:21 

 We are in the BRK and corrected the vacuum interlock condition.

We will restart the SA1 vacuum loop in a few minutes

 

Entry   WP74 OCD contacts, posted by Jan Grünert on 11 May 2017, 19:12 WP74-OCD-5-2017.xlsx

Plan of WP74 OCD contacts for May.
Assignments are subject to change.

Initially availability is 10h-18h on the given days.
This might be adapted as well for later weeks.

Entry   XTD10 not open on Monday, posted by Harald Sinn on 11 May 2017, 18:26 

 Dear all, 

contrary to the rumor that I spread last Tuesday in the PBS meeting, the magnet tests in XTD2/4 will be NOT done coming Monday and therefore the XTD10 will be be NOT open. It is still the plan to have one access day in XTD10 per week in the future (Monday or Wednesday to be clarified with the magnet group), but this will start only later this month.

Best regards

Harald 

 

Entry   Motion loop, posted by NEREA JARDON on 11 May 2017, 16:41 

Dear all,

I will update the Motion loop to include the mc2 motors, it will be running again in few minutes.

Thank you!

Entry   CAS OCD, posted by Gero Flucke on 10 May 2017, 18:52 

CAS on call service for the night:

Gero Flucke: 9-8053

 

 

 

Entry   karabo Beckhoff link not reestablished for SASE1 tunnel VAC loop, posted by Jan Grünert on 10 May 2017, 13:03 

Could somebody please re-establish the karabo controls of the SASE1 tunnel VAC loop (connection with Beckhoff server) ?

The karabo devices for XGM vacuum XTD2 and XTD9 are still all in UNKNOWN STATE.

We urgently would like to check the XGM vacuum status and restart the pumps before they are vented.

Thanks,

Jan

    Reply   karabo Beckhoff link not reestablished for SASE1 tunnel VAC loop, posted by Jan Grünert on 10 May 2017, 13:07 

Jan Grünert wrote:

Could somebody please re-establish the karabo controls of the SASE1 tunnel VAC loop (connection with Beckhoff server) ?

The karabo devices for XGM vacuum XTD2 and XTD9 are still all in UNKNOWN STATE.

We urgently would like to check the XGM vacuum status and restart the pumps before they are vented.

Thanks,

Jan

 Jan,

We are working on it. 

Entry   Vacuum Loop, posted by NEREA JARDON on 10 May 2017, 12:34 

Vacuum is up and running again.

Thank you

Entry   Vacuum Loop, posted by NEREA JARDON on 10 May 2017, 11:06 

Sorry for disturbing you, but I will have to wait till WP74 group finish a training in order to be able to put the XGM up again .

Entry   Vacuum loop, posted by NEREA JARDON on 10 May 2017, 10:59 

Dear all,

The update of the Vacuum loop will take place in the next few minutes, later on, you would have access again to it.

Thank you.

Entry   EPS loop, posted by NEREA JARDON on 09 May 2017, 17:04 

EPS loop in SASE1 is running again

Entry   EPS loop, posted by NEREA JARDON on 09 May 2017, 16:43 

Dear all,

I will make an update on the EPS loop, it will take only a moment.

Thank you

Entry   Status after the 9.30 Meeting, posted by Adriano Violante on 08 May 2017, 15:18 

 Vacuum (M. Dommach):

  • Systematic tests of ion pumps in XTD9 almost finished - ongoing
  • Interface with MPS has to be tested
  • Problem with the fast valve in XTD2 and 9 - it is possible to close it remotely but not possible to open it again. Checking of the cabling is ongoing by Vacuum group
  • After restart of the vacuum loop many pumps in XTD 9 and 2 show an unknown error and some of them are not readble - CAS working on that.

 

PLC (P. Gessler, T. Freyermuth):

  • Implementation of shutters in Karabo ongoing -XS3 shutter in the VAC loop now. XTD9 to do.

Karabo (A. Silenzi):

  • GUI stability improved with a temporary solution. This should be enough to guarantee the proper functioning of images acquisition.
  • Update of devices list ongoing
  • Library for motors (base device), elmo and technosoft, being worked out.

Plans for today:

  • XGM work on gas injection
  • Bring back Karabo and clear XGM error codes
  • Perform systematic test of DPS in XTD9

Other topics:

  • No 09:30 meeting tomorrow - next meeting will be on Wednesday
Entry   WP74 OCD contacts for this weekend, posted by Jan Grünert on 06 May 2017, 14:50 

WP74   OCD  for the  weekend 6.5.-7.5.2017:

Saturday: Jan, jan.gruenert@xfel.eu, 9-5777

Sunday: Theo, theophilos.maltezopoulos@xfel.eu, 9-6792

 

Entry   AE OCD Mai 5 -- Mai 8, posted by Nicola Coppola on 05 May 2017, 14:35 

AE on call service:

    Contact person:

        Nicola Coppola

    Phone:

        9 - 5627

 

Entry   VAC loop up and running again, posted by Tobias Freyermuth on 05 May 2017, 09:44 

The vacuum loop is up and running again, with the version 1.11.4.

Denis Finze will connect the shutter signals of the XS3 shutter to the vacuum loop in rack 1.7.

 

Entry   Slow loading in karabo GUI, posted by Jan Grünert on 04 May 2017, 19:40 

The current slow response times in the karabo GUI are the following (some measured times for reference):

- opening a project from the project manager : 45sec (just loading, not yet touching any device or scene)
- opening a scene and receiving the status for all devices e.g. XGM@XTD2 : between 90 and 120 sec
- beyond that, it's never clear if the displayed gauge values are true/actual and must be separately read.
- reading explicitly a gauge value (with command READ in configurator) gives currently an updated value after about 10 sec (should be almost immediate when requested)
-----> working with this (getting actual work done) is practically almost impossible

- this is using the "new" gui server "sa1-br-sys-con-gui2"
- this is after 19h30 (shouldn't less traffic help the performance ?)

 

Entry   CAS support during the afternoon: 9-6776, posted by Sandor Brockhauser on 04 May 2017, 12:14 

Dear All,

 

During the afternoon CAS has a group activity. Any support can be requested via my phone number: 9-6776.

 

See you,

Sandor 

Entry   Info from H. Sinn, posted by Tobias Haas on 04 May 2017, 11:36 

 Hallo allerseits

 
der Beschleuniger wird heute um 13:00 Uhr abgeschaltet und erst wieder Montag 
angeschaltet. Ich hab Winni überredet, dass wir den XTD10 brechen können, damit ihr 
heute und  morgen im XTD10 Zugang habt. 
Allerdings solltet ihr nicht die Magnettür zum XSDU2 öffnen, weil dann auch der komplette XTD4 
aus dem Interlock fällt. 
Ich hab mit Michael Bieler verabredet, dass wir in der zweiten Maihälfte Absuchtraining für XFEL Leute 
machen können (bis ca. 10 Leute auf einmal wäre sinnvoll), damit wir in Zukunft dann XTD10 und XTD9 selber 
absuchen könnnen (Termin kommt noch). 
 
Grüße 
 
Harald 
 
Entry   Gas Section Interlock on XTD9 - Shut off valve also operative, posted by Raúl Villanueva-Guerrero on 03 May 2017, 14:38 45.png

 Dear all,

during the test run today by our colleagues of WP74, the interlock condition inside the XGM module was met (small volume pressure burst up to 10-2 mbar range). Now we can see also the expected cut-off event of the gas injection (see attached pictured). It seems that the reason why there was any feedback from the respective shut-off valve was the solenoid actuator on the respective shut-off valve was set in manual mode.

This means that XTD9 Interlock for the whole gas section has been up and running as expected the whole time.

Best Regards.

Entry   Accelerator Schedule for the next days, posted by Tobias Haas on 03 May 2017, 13:38 

 Author: Decking

Run Coordinators: W. Decking (93430), D. Sanzone

Tunnels XTIN, XTL, XTD2-4, XTD10 closed
Temporary access to XTL,XTD2-4, XTD10 possible on Wed, 4.5.
Next open access XTIN, XTL, XTD2-4, XTD10 on Wed, 10.05. 08-16

|01/05 Mo M |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz
|01/05 Mo A | Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz
|01/05 Mo N |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz
|02/05 Tu M |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 1 Hz; establish 6, 8 GeV File
|02/05 Tu A |  Beam operation  to T4D 6 GeV, 1 bunches, 0.5 nC, 1 Hz
|02/05 Tu N |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz
|03/05 We M |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz; study beam optics
|03/05 We A |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz
|03/05 We N |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz 
|04/05 Th M |  Beam operation  to T4D 6.4 GeV, 1 bunches, 0.5 nC, 1 Hz
|04/05 Th A |  No beam operation, tunnels closed
|04/05 Th N |  No beam operation, tunnels closed
|05/05 Fr M |  No beam operation, Acces to TLD for leak search, Temporary access to T2-T4 possible
|05/05 Fr A |  No beam operation, Acces to TLD for leak search, Temporary access to T2-T4 possible
|05/05 Fr N |  No beam operation, tunnels closed
|06/05 Sa M |  No beam operation, tunnels closed
|06/05 Sa A |  No beam operation, tunnels closed
|06/05 Sa N |  No beam operation, tunnels closed
|07/05 Su M |  No beam operation, tunnels closed
|07/05 Su A |  No beam operation, tunnels closed
|07/05 Su N |  No beam operation, tunnels closed
|08/05 Mo M |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 10 Hz
|08/05 Mo A |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 10 Hz
|08/05 Mo N |  Beam operation  to T4D 11 GeV, 1 bunches, 0.5 nC, 10 Hz

Entry   *IMPORTANT* Change of plans re Access tomorrow, posted by Tobias Haas on 03 May 2017, 13:29 
Due the recent results from XFEL, the urgent maintenance is shiftet from Thursday 4th to Friday 
5th. On Thursday, there will be operation till 14:00, after 14:00 the machine will be 
switched to standby. All the work planned will shift accordingly by one day. No ZZ before 
Thursday 14:00. 
 
The machine will be shut down Friday moring 7:00. 
 
Interlock situation: The machine will stay in interlock, only the access to XTL from OSDORF will 
be brocken.  
 
XTL: Access from Osdorf 
- activation measurement XS1 XTL/rear part by D3 
- Leak search and repair in the TLD beamline by MVS 
- A20 work by MHF-p (Exchange of filament heating, work on phase shifter) 
- CS8 RF measurement on load (MHF-p) 
- Repair of wire scanner relais 
 
XTL: Access from Bahrenfeld 
- Exchange of filter in the BCM monitors by MKS 
- Repair of DCCT of a B2D quad 
- Change of AMC board in A8 by MSK 
 
XTD2: 
- ZZ for repair of a BPM system 
XTD10:  
ZZ for Photon Beamline Work 
 
 
All further work has to be agreed by the run or machine coordination. 
 
Entry   GUI Server redeployment, posted by Alessandro Silenzi on 03 May 2017, 12:32 

The GUI server has been redeployed and a second one has been added.

In order to access those:

please log out of the gateway and log in again using the usual command

ssh desyusername@exflgateway -L 44444:sa1-br-sys-con-gui1:44444

or

ssh desyusername@exflgateway -L 44444:sa1-br-sys-con-gui2:44444
Entry   Correction to plans for Vacuum (e-log message n3. 199) in XTD9, posted by Raúl Villanueva-Guerrero on 03 May 2017, 11:15 

 Dear all,

it seems that this morning was somehow a misunderstanding. The XTD9 Gas Section Interlock test was succesfully finished the last 26th of April (see e-log message nr. 179).

There´s no further activity planned for this system.

 

Regards.

 

r.

Entry   Status after 0930 meeting, posted by Tobias Haas on 03 May 2017, 11:04 

Tunnel Status: XTD2/4/10 closed. XTD9 open. Controlled Access to 2/4/10 possible upon request

 

Vacuum (M. Dommach):

  • Systematic tests of ion pumps in XTD9 concluded
  • Tests of DPS in XTD9 should happen today with R. Villanueva
  • Systematic tests of all interlock conditions in XTD9 should happen tomorrow

PBLMs (H. Sinn, P. Gessler):

  • Debugging session for the ELMO controller was successful. The problem was traced to details in the parameter settings
  • Proper setting of parameters is tricky and requires care and expert knowledge.
  • Proper parameters now need to be programmed into the firmware. Manual setting is also possible but not favored.
  • AE will set this up and deploy next week in order to maximise optimal use of resources (This week only one expert, TF, is here)

Imagers (A. Koch):

  • Imagers in XTD2 and XTD9 are ready for beam
  • It is important that images can be stored. This is not yet the case and will be required latest when PBS commissioning starts
  • AK will be away from tomorrow until next Thursday

XGM (J. Grünert):

  • Late yesterday, Karabo went into error triggering the interlock on the Vatterfly valves on both XGMs. Pressure is still low but slowly rising
  • If the condition cannot be resolved remotely a local intervention is necessary. This can possibly wait until the scheduled interrupt tomorrow
  • Today tests should occur with the DESY experts for gas injection
  • Tests are currently hindered by the Karabo problem. AS suspects that this may have to do with the redeployment of Karabo yesterday. He is now working with high pressure on solving the problem

FXE (A. Galler):

  • Currently commissioning loop 1. There is still a problem reading out encoders. It appears that this is a firmware issue. TF is working on this.

SPB (B Weinhausen):

  • Fixes were deployed in the firmware for the Reinshaw encoder problem (16/32 bit issue). Still one encoder is in error. TF points out that this is a different problem. He will investigate

PLC (P. Gessler, T. Freyermuth):

  • CRL in XTD2 was integrated into the PLC motion loop yesterday during the access.
  • Meeting today with DESY experts to finalise the EPS logic
  • Focus this week on SPB and AGIPD

Karabo (A. Silenzi):

  • Karabo (Components Beckhoff-Device and Beckhoff-Com) were re-deployed yesterday.
  • This maybe the origin of the problems observed in the evening 

Plans for today:

  • XGM work on gas injection
  • Bring back Karabo and clear XGM error codes
  • Perform systematic test of DPS in XTD9

Other topics:

  • No 09:30 meeting tomorrow due to access. 
  • Request should be made to break the interlock in XTD10 on maintenance days in order to allow continuation of installation work

 

Entry   XTD9 vacuum now ok, but not in XTD2: turbos on XGM@XTD2 still in ERROR, posted by Jan Grünert on 02 May 2017, 22:27 

Wajid and Leonce from CAS have managed to get us the karabo controls back.
We have now put the XGM@XTD9 back into normal vacuum operation, and opened finally the vatterfly valves, this one is ok, and we checked also the entire XTD9 gas section to be ok.

However, in XGM@XTD2, both XGM turbo pumps are still in ERROR and we cannot get them out - it is an error on the PLC level ? It's something we have not seen before.
The vacuum is at a controlled level of 5E-7mbar thanks to interlock-closed vatterflys.

Request to AE: tomorrow morning, we must remotely get the two turbos out of error (PLC client ?), otherwise we have to request a ZZ access to the tunnel XTD2 for local intervention on the turbo pump controllers.

Request to the AE+CAS group leaders: apparently we need to organize OCD also during nights on weekdays.

 

Entry   XGM scenes/devices offline - UHV pressures increasing - Please respond now !!, posted by Jan Grünert on 02 May 2017, 20:11 

All devices went into unknown state in the karabo XGM scenes in XTD2 and XTD9 at 19h52.

Pressures INCREASE since then (as measured/shown in DOOCS):

XTD2:  2,5E-7mbar and rising

XTD9:  7,7E-7mbar and rising

Please respond now !! We are still in but want to go home !

Entry   Access to XTDs on Thursday, posted by Adriano Violante on 02 May 2017, 15:30 

 This Thursday the XTDs will be accessible with ZZ procedure. Access can be requested via T. Haas. 

Entry   Status of Vacuum System , posted by Harald Sinn on 02 May 2017, 10:56 

XTD2: All gate valves are now OK (not interlocked) after re-instantiating and re-setting the XGM_DP_OK. 

The interlock errors of some valves in XTD9 are shown in the screen shots below (Janni and Valerii starting now in XTD9 to debug some more controllers)

 

 

Entry   PBLM Motor drivers in PreOP, posted by Tobias Freyermuth on 02 May 2017, 10:05 

Hi all,

 

due to ongoing tests with the PBLM motor drivers I have to set the Elmo drivers in PreOp mode.

That should not affect any other terminal in the loop.

 

Cheers,

    Tobias

Entry   ERRATA: CAS - On-Call Duty Planning - Valerii, Gabriele and Wajid , posted by Hugo Silva Santos on 29 Apr 2017, 10:04 

 Dear All,

Still in time, I would like to correct out schedule.

The scheduled previous agreed for this weekend/holiday was from 10:00 to 17:00. Therefore,

  • Saturday 10:00 to 17:00 - Valerii - Phone: 95471
  • Sunday 10:00 to 17:00 - Gabriele - Phone: 96894
  • Monday 10:00 to 17:00 - Wajid - Phone: 95630

Best,

Hugo

Entry   Vacuum group call service, posted by Janni Eidam on 28 Apr 2017, 16:29 

Not really official, but in emergency case you can call 96993 for vacuum group. Next week Martin is back and I think we will have official on call service.

Have a nice weekend with hopefully no problems :-)

Entry   WP74 OCD contacts for the coming weekend, posted by Jan Grünert on 28 Apr 2017, 15:44 

WP74   OCD  for the coming weekend 29.4.-1.5.2017:

 

Saturday: Theo, theophilos.maltezopoulos@xfel.eu, 9-6792

Sunday: Jan, jan.gruenert@xfel.eu, 9-5777

Monday: Theo, theophilos.maltezopoulos@xfel.eu, 9-6792

 

Note: Theo has Torbens work phone this weekend since Theo has not yet his own mobile work phone

Entry   CAS - On-Call Duty Planning - Valerii, Gabriele and Wajid, posted by Hugo Silva Santos on 28 Apr 2017, 14:43 

 Dear All, 

I would like to share the CAS members on the OCD from 29/04 to 01/05:

  • Saturday 08:00 to Sunday 08:00 - Valerii - Phone: 95471
  • Sunday 08:00 to Monday 08:00 - Gabriele - Phone: 96894
  • Monday 08:00 to Tuesday 08:00 - Wajid - Phone: 95630

Best,

Hugo

 

Entry   AE OCD April 29 - Mai 1, posted by Tobias Freyermuth on 28 Apr 2017, 14:31 

AE on call service:

    Contact person:

        Tobias Freyermuth

    Phone:

        9 - 6822

   

Entry   Small correction to minutes posted just before, posted by Tobias Haas on 28 Apr 2017, 13:24 

Note that plans for next week (points 2& 3) should refer to XTD9 and *NOT* XTD2

 Plans for next week:

  • Consolidate vacuum in XTD2 so that V0 can be reliably opened when first beam should be transported
  • Finish work in XTD9, in particular PBLMs and instrument components
  • Finish systematic tests of ion pumps in XTD9
  • Deploy fix for Renishaw encoders in firmware
  •  
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 28 Apr 2017, 13:08 

 Tunnel Status (T. Haas):

  • Tunnels XTD2/4/10 were interlocked yesterday afternoon
  • Beam is already going through the T2 and T4 beam lines to T4D
  • XTD9 remains open until approximately 15 May

Vacuum (J. Eidam, R. Villanueva):

  • The interlock in the gas section was tested successfully in XTD9. The interlock does currently not include the gas injection. This still needs setting up and testing
  • Systematic testing of ion pumps and interlocks is ongoing in XTD9 but needs to continue next week
  • The system generally works reliably
  • However, there was an incident this week in which the gas sections in XTD2 and XTD9 went completely off. The reason is still not understood

Mirrors and PBLMs (H. Sinn):

  • All three mirrors in the SASE1 beam line in XTD2/9 are installed and pumped
  • N. Gerassimova installed PMTs in XTD2 yesterday and set up the cameras of the PBLMs
  • The problem with injected properties disappearing was identified on the Karabo side and fixed. The fix still needs to be deployed
  • The motors of the PBLMs are still not functioning completely. 
  • The read out rate of the cameras is ok (of the order of 10Hz or better)

Imagers (A. Koch):

  • Imagers in XTD2 and XTD9 are ready for beam
  • Work continues on improvements
  • Read out rate is ok, but the latency is sometimes high and needs to be unterstood

XGM (J. Grünert):

  • The gas on the XGM in XTD2 was changed at the request of K. Tiedtke from Ar to Ne
  • Tests were done with the remote control of the gas system. This is now fully functional
  • The HV/Vacuum interlock is not operational yet
  • Otherwise the XGM is ready accept beam. Next week software tests should be performed with the readout

FXE (A. Galler):

  • Currently commissioning loop 1. There is still a problem reading out encoders. It appears that this is a firmware issue. TF is working on this.

SPB (B Weinhausen):

  • Currently commissioning the SPB tunnel components. The encoders have the same problem as the one reported by FXE
  • I broken terminal required changing

PLC (T. Freyermuth):

  • CRL in XTD2 was integrated into the PLC motion loop yesterday during the access.
  • A first version of the EPS logic was agreed upon and implemented. Details to be discussed again with DESY next week

Karabo (A. Silenzi):

  • ITDM provided an additional control server
  • A redeployment of Karabo is necessary and will be done later today (users will need to re-connect afterwards) 
  • The problems previously observed with the GUI server have not re-occured. 

Plans for next week:

  • Consolidate vacuum in XTD2 so that V0 can be reliably opened when first beam should be transported
  • Finish work in XTD2, in particular PBLMs and instrument components
  • Finish systematic tests of ion pumps in XTD2
  • Deploy fix for Renishaw encoders in firmware

Other topics:

  • We continue the 09:30 meetings next week until further notice

 

 

Entry   Fertigmeldung phase II cables SPB Optics Hutch D.02 and SPB laser hutch D.13, posted by Adriano Violante on 28 Apr 2017, 08:25 

 ACTEMIUM has delivered the handover document for the phase II cables installed in D,02 and D.13. The beckhoff crates can be connected to the cables in these areas of SASE1.

 

Entry   Motion Loop is up, posted by Valerii Bondar on 27 Apr 2017, 17:41 

Dear all,
motion loop is up and all Karabo devices in it are running.

Thank you.

Entry   Accelerator plans for the next 5 days, posted by Tobias Haas on 27 Apr 2017, 15:28 
27/04 Th A Beam operation to TLD 10 GeV, 1 bunches, 0.1 nC, 1 Hz; interlock 
set XTD2-XTD4
27/04 Th N Beam operation to TLD 10 GeV, 1 bunches, 0.1 nC, 1 Hz, EOD shift
28/04 Fr M Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
28/04 Fr A Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
28/04 Fr N Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz 
29/04 Sa M Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
29/04 Sa A Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
29/04 Sa N Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
30/04 Su M Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
30/04 Su A Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
30/04 Su N Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz 
01/05 Mo M Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
01/05 Mo A Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
01/05 Mo N Beam operation to T4D 10 GeV, 1 bunches, 0.1 nC, 1 Hz
 
Access to TLD:  
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 27 Apr 2017, 15:11 

 XTDs Info:

Tunnel XTD2/4 will be accessible today until 1500. Dosimeter and General radiation training required. 

XTD10 will be closed starting this afternoon

Vacuum:

 

  • DPS with interlocks was tested successfully yesterday evening but...
  • ... Complete failure of gas sections in both XTD and XTD9 some time tonight. Valves were closed and turbo pumps were off. Reason is still being investigated
  •  
  • Systematic tests of ion pumps in XTD9 done for 3 vacuum sections. Currently only the pumps are tested. Tests of the interlock will follow
     

Karabo:

  • The problem with the GUI server has unfortunately not re-occured. Hence it can currently not be debugged.
  • Second GUI server is available for fall back
  • Remote reset of TP controllers has been implemented and will be deployed in the next release

PLC

  • A problem was found in the MC2 library affecting the ELMO controller.  This only affected the systems deployed in the tunnel. 
  • The non-linear behaviour of the PBLM motors was reproduced independently of PLC and KARABO. Suggestion: Could this happen when the motor has to work against vacuum pressure? Evidence: It does not occur in the lab (no vacuum!)
  • A video session with the manufacturer is schedule for next week to look at the problem

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
  • ASilenzi will discuss offilen with Natalia the acceptance test definition for PBLM
  • List of errors and relative solution concerning ELMO absolute encoder implementation being worked out by AE/CAS

EPS

  • Logic of EPS was agreed between AE and H. Sinn:
    • Currently only covers devices up to XS3
    • Vacuum ok requires all valves to be out of the way
    • Any screen down  forces single bunch mode
    • All imagers in safe position allows full beam mode
  • Meeting next week @ DESY to discuss technical details with MPS group

SPB Tunnel components

  • Renishaw encoder can be read out reliably after fix for error signal line
  • SPB would like to work on the pulse picker next and is waiting for it to be integrated

FXE

  • FXE guys would like to help with tests of Hard X-Ray Mono 

Tasks for today:

  • Perform various maintenance tasks in XTD2, e. g. integrate CRLs, exchange photo tubes, exchange gases
  • Investigate why gas sections switched off yesterday
  • Continue test of vacuum components in XTD9

 

Entry   Update MOV loop, posted by Tobias Freyermuth on 27 Apr 2017, 09:34 

Hi all,

 

in order to integrate the CRL in XTD2 I am going to update the motion loop.

I will let you know as soon as this is done.

 

Cheers,

    Tobias

Entry   XTD2 Differential Pumping completely OUT OF OPERATION!, posted by Raúl Villanueva-Guerrero on 27 Apr 2017, 07:04 

 Dear all,

 

I just checked the Karabo Scene for both XTD9 and XTD9, finding out the not-so-nice situation where all the valves and pumps were respectively closed and stopped. What really worries me is again the fact that these situations are happening without aparent reason. I´m right now trying to start the system remotely but obviously one needs again to access the tunnel for that is the only reason to actually be sure that everything is up an running normally again.

 

 

    Reply   XTD2 Differential Pumping completely OUT OF OPERATION!, posted by Raúl Villanueva-Guerrero on 27 Apr 2017, 07:11 

Raúl Villanueva-Guerrero wrote:

 Dear all,

 

I just checked the Karabo Scene for both XTD9 and XTD9, finding out the not-so-nice situation where all the valves and pumps were respectively closed and stopped. What really worries me is again the fact that these situations are happening without aparent reason. I´m right now trying to start the system remotely but obviously one needs again to access the tunnel for that is the only reason to actually be sure that everything is up an running normally again.

 

 

 UPDATE:

XTD2

The Upstream sector is back into operation.

The Downstream one is still out of order since the turbopumps are whether in error or in an unknown/un-instantiated status.

 

 

XTD9

Upstream sector is back to full operation

Downstream sector: only one of the turbos is running. The other one P11280T cannot be reset

 

Right now that is the only thing I can do.

 

Entry   XTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESFUL, posted by Raúl Villanueva-Guerrero on 26 Apr 2017, 19:21 

 Dear all,

Finally the tests were run with the expected results: Pressure thresholds for the 3 involved gauges were forced on the system and the interlock on the two gate valves that limit the whole gas section were automatically closed in every case. Also the release switch was tested and the valves were able to be normally operated again.

However the interlock definition also involves the closing of the so-called "shut-off" valve in the gas injection line at the XGM. Unfortunately its behaviour couldn´t be completely observed since the Karabo device is not fully implemented. On the other hand, J. Grünert reported that after the interlock was triggered the valve was shown as also "interlocked" (despite the actual status, open or closed was not clear). This situation may require a second test, combined for instance with the gas injection test to be run by WP74 in the upcoming date). 

In any case the final results were rather positive. (despite there still some permanent uncertainty about devices being reachable or not through Karabo, as it has been previously reported).

 

Thanks to everyone involved.

 

Raúl Villanueva on behalf of B. Rio, N. Jardon and V. Bondar.

 

 

Entry   SA1-VAC loop down (only XTD9) and later restarted, posted by Jan Grünert on 26 Apr 2017, 18:34 

Since around 17h30 all XTD9 VAC loop is in error. It came back in karabo around 17h50. XTD2 not affected.

At that point, we had to reset every single karabo device of the XGM, then restart pumps etc.

Did the same also for the DPS upstream and downstream of XGM@XTD9.

XGM vatterfly valves will be opened by me only when I see that no further errors occur.

Currently, all but one pumps were restarted, also in Rauls DPS, only one of these not

Entry   Motion loop, posted by NEREA JARDON on 26 Apr 2017, 18:06 

Dear all,

I will do an update into the Motion loop. Would take only few minutes and the PLC will be running again.

Thank you and sorry

Entry   Access XTD2 tomorrow, posted by Tobias Haas on 26 Apr 2017, 17:48 

I added the requests that I was made aware of to the list of access requests for tomorrow. While the interlock in XTD2 will be broken and hence the tunnel is accessible without special procedures, please note the followoing

  • Please make sure your request in in the DESY table of access requests 
  • You have valid access permissions and two (!) dosimeters, one from XFEL one from DESY

 

 

Entry   XSDU2 access, posted by Adriano Violante on 26 Apr 2017, 12:58 

 The XSDU2  area will be open (as XTD2) tomorrow between 9 ans 12. To register the access, please send also in this case a mail to T.Haas.

Entry   Status and Plans after the 9:30 meeting, posted by Adriano Violante on 26 Apr 2017, 11:55 

 

XTDs Info:

Tunnel XTD2 will be accessible this Thursday (TUNNEL OPEN, NO ZZ), 27.04. between 9 and 12. Dosimeter and General radiation training required. Access requests should go to T.Haas.

XTD10 will be closed starting from this Thursday, 27.04. at 12:00

Provided that the authorities give the "go ahead", DESY plans to put beam in XTD2 on Thursday evening.

Access to XSDU2 being clarified - separate entry will be posted.

Karabo:

  • System running  but performance of the GUI still sluggish - CAS was not able to reproduce the problem, still under investigation
  • Second server has been set up as workaround.
  • In parallel experts are working on a definitive solution
  • Deployment today on a new beckhoff device for the decodification of PLC and interlock error messages. 

Vacuum:

  • Systematic tests of ion pumps ongoing. in XTD 9 two controllers/beckhoff terminal for pumps were wrongly connected (exchanged). To reconnect the controllers in the right orders the loop has to be interrupted. This will be done after the vacuum test on the XGM is done.

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
  • ASilenzi will discuss offilen with Natalia the acceptance test definition for PBLM
  • List of errors and relative solution concerning ELMO absolute encoder implementation being worked out by AE/CAS

SPB Tunnel components

  • Error message fore the Renishaw encoders is coming from wrond specifics of the interpolator between encoder and input terminal. This is due to wrong datasheet provided by the company. This is not a problem for reading of the encoders and their reliability. Error signal is currently ingnored
  • The same problem also affects FXE components
  • The cameras operated at 1Hz deliver delayed images. 1/3 Hz operation (almost live mode) is OK - probably related to GUI memory issues

FXE

  • Encoders of Loop1 have the same error message as SPB - the encoder positions are reliable - local components test can go on (e.g. OGT1)
  • Encoders of loop2 are not powered - AE to investigate today

 

Tasks for today:

  • XGM vacuum test and solution implementation of pump restart in Karabo
  • GUI server resource problem ongoing
  • Deployment of a beckhoff device for the decodification of the error messages.
  • Find a solution for the Renishaw encoder problem SPB Tunnel/ FXE Loop1
  • Investigation of the FXE Loop2 encoders power
  • Continue testing of ion pumps in XTD9
  • Vacuum signal alarms to be checked by AE,Harlad, Janni
  • Implement and test the CRLs in XTD2 in the Beckhof loop for test.

Tasks for tomorrow:

  • Vacuum signal alarms to be checked by AE,Harlad, Janni
  • Implement and test the CRLs in XTD2 in the Beckhof loop for test.
  • Checking of the absober for first lasing (inc. filter chamber). 
Entry   Motion loop, posted by NEREA JARDON on 26 Apr 2017, 11:44 

Dear all,

I will do an update of the motion loop so the PBLM could be tested. I will do it know and the PLC will be again available in few minutes.

Thank you!

Entry   karaboGUI issues - during cycling of PLC loop (shutdown and restart) - effects on XGM XTD2 and XTD9, posted by Jan Grünert on 26 Apr 2017, 10:51 45.png49.png10.png
Problems described in detail below (this entire procedure takes way too much of our time, effectively still nearly 2 hours!):

Nerea/AE requested yesterday afternoon to shutdown and restart the SASE1 VAC PLC loop once again. We start today morning (wednesday) at 8h30. 
8h30
karabo is not showing status of all devices, see three screenshots (attached). karabo-GUI issue.
These devices have to be shutdown and reinstantiated to show a status and to operate them. 
Several valves and gauges and scroll pumps affected both in XGM of XTD2 and XTD9. 
 
9h00 finally I can close all four vatterfly valves 
 
9h15 Nerea shuts down and restarts the SASE1 VAC PLC loop 
 
9h25 still waiting for karabo to reconnect to Beckhoff PLC (I cannot do anything in karabo, and 
 no current status updates of anything) 
 
9h40 SPB_XTD9_XGM scene has loaded (seems like at least). I start the reactivation procedure (switch 
 on scroll, open valves etc.). Need to reinstantiate several devices. 
 
10h00 SPB_XTD9_XGM: reinstantiate both turbo pumps, CRemotePriority ON, COn, CPump (if CRemotePriority 
 not visible, again reinstantiate) 
      READ ADriveCurrent, ARPMIn several times, both should change from time to time, don't 
 worry about "0" every second read time 
10h05 SA1_XTD2_XGM: reinstantiate both turbo pumps, StartPumpingStation 
      READ ADriveCurrent, ARPMIn several times, both should change from time to time, don't 
 worry about "0" every second read time 
10h10 READ the actual value of the gauges in configurator (not to trust value shown in scene) 
10h15 observe DOOCS RVC300 UHV pressures, open vatterfly valves 
 
10h20 end of intervention 
Entry   Motion and Vacuum, posted by NEREA JARDON on 26 Apr 2017, 09:14 

Vacuum is running again and Motion also, yesterday I forgot to update you about the Motion PLC.

Sorry and best regards,

Entry   Vacuum Loop, posted by NEREA JARDON on 26 Apr 2017, 09:10 

Dear all,

We need to update the Vacuum loop in order to correct and add some configuration to the interlock conditions.

It would be running in few minutes again.

Thank you!

Entry   Motion loop, posted by NEREA JARDON on 25 Apr 2017, 14:20 

Dear all,

We have to make some changes again into the Motion loop. Therefore I will do an update at 14.45h.

I will keep you inform when it is running again.

Thanks!

Entry   XTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - Not Working (yet), posted by Raúl Villanueva-Guerrero on 25 Apr 2017, 13:49 

 After some minor issues, the first test has been done today and the interlock wasn´t triggered despite the conditions were met (also visible in Karabo).

 

This requires intervention and revision from AE

 

The next try-out should be done as soon as possible during this week.

 

Regards.

 

Raúl, Benoit and Valerii

 

 

 

Entry   Motion loop, posted by NEREA JARDON on 25 Apr 2017, 10:51 

Dear all.

Motion loop is running again.

Thank you

Entry   Status and Plans after the 9:30 meeting, posted by Adriano Violante on 25 Apr 2017, 10:49 

XTDs Info:

Tunnel XTD2 will be accessible this Thursday, 27.04. between 9 and 12. Dosimeter and General radiation training required. Access requests should go to T.Haas.

XTD10 will be closed starting from this Thursday, 27.04. at 12:00

Provided that the authorities give the "go ahead", DESY plans to put beam in XTD2 on Thursday's evening.

 

Karabo:

  • System running  but performance of the GUI still sluggish
  • There appears to be a resource leak. Second server will be set up tomorrow as workaround. Experts are working on it.
  • In parallel experts are working on a definitive solution
  • Deployment today on a new beckhoff device for the decodification of PLC error messages.

Vacuum:

  • Systematic tests of ion pumps started again

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
  • ASilenzi will ask Natalia for acceptance test definition for PBLM
  • Motion loop will be down until 10:30 for update. An entry will be written when the loop is again up. 

SPB Tunnel components

  • The Renishaw encoders can be read and positions are reliable. An error message is coming from the encoder and is probably due to a wrong voltage level delivered to the encoder. The encoders can be operated in this condition.
  • T. Freyermuth is in contact with the encoder company tu understand the problem and work on a fix
  • The same problem also affects FXE components
  • The cameras operated at 1Hz deliver delayed images. 1/3 Hz operation (almost live mode) is OK - probably related to GUI memory issues

FXE

  • Encoders of Loop1 have the same error message as SPB - the encoder positions are reliable - local components test can go on (e.g. OGT1)
  • Encoders of loop2 are not powered - AE to investigate

 

Tasks for today:

  • Identify a fix/workaround for the GUI server resource problem
  • Deployment of a beckhoff device for the decodification of the error messages.
  • Find a solution for the Renishaw encoder problem SPB Tunnel/ FXE Loop1
  • Investigation of the FXE Loop2 encoders power
  • Continue testing of ion pumps in XTD9
  • Test of gas section interlock in XTD9

Tasks for tomorrow:

  • Setup of the second server for karabo GUI
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 24 Apr 2017, 11:08 

 

Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open

Karabo:

  • Bad crash of GUI server occured on Friday.
  • System running over the weekend but performance of the GUI was sluggish
  • There appears to be a resource leak. Experts are working on it.
  • Fix is urgently needed for continued testing

Vacuum:

  • Systematic tests of ion pumps start again since V. Bondar is back
  • Fix for the interlock of the gas section in XTD9 to be deployed today.
  • Gas system tests to be done starting tomorrow

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.

SPB Tunnel components

  • The Renishaw encoders can not be read out via the PLC
  • The problem appears to be that the signal level is not TTL. 
  • T. Freyermuth is working on a fix
  • Work can continue once the encoder problem is solved
  • The same problem also affects FXE components
FXE
  • FXE team not represented

 

Tasks for today:

  • Re-deploy vacuum loop for the tests of the gas section tomorrow
  • Identify a fix/workaround for the GUI server resource problem
  • Find a solution for the Renishaw encoder problem
  • Restart testing of ion pumps in XTD9

Tasks for tomorrow:

  • Test of gas section interlock

Other topics

  • J. Grünert requests to put the XGM in XTD10 under PLC/Karabo control
  • This would require extensive work by several groups (ITDM, AE, CAS) and cannot be done at the moment in view of established priorities

 

Entry   CAS OCD April 22-23, posted by Sandor Brockhauser on 21 Apr 2017, 17:22 

In case of any problems, please, call the CAS personnel on 9-6443, 9-5630, or 9-6840.

Have a nice week-end, Sandor

Entry   SASE EPS RACK 1.14 connected, posted by Tobias Freyermuth on 21 Apr 2017, 15:30 

The EPS-loop is now complete again.

The interface from EPS to MPS is working now. One broken wire in the cable between EPS and MPS was found. We are using now other pairs for the signals "SA1_SYS_EPS2MPS/DCTRL/MODE1", "SA1_SYS_EPS2MPS/DCTRL/MODES" and "SA1_SYS_EPS2MPS/DCTRL/MODEM".

Cheers,

    Tobias

Entry   Cycling of PLC loop (shutdown and restart) - effects on XGM XTD2 and XTD9, posted by Jan Grünert on 21 Apr 2017, 15:26 
Together with Nerea and Wajid and Alessandro

  • 10:00 closed vatterflies at XTD9 and XTD2 from Karabo
  • Florian is at XTD9 next to the XGM
XTD9: 
  • LOOP re-cycle
  • All valve closed and scroll off (turbos in unknown state; Florian in tunnel sees 990 Hz)
  • Scroll and turbos switched ON
  • Angle valve opened over Karabo
  • Problem to open gate-valve
  • Set Karabo offline
  • Nerea switched turbos at XTD2 ON (XTD9 were on) by PLC
  • Karabo is reconnected to PLC (brought online again)
XTD2: (with Alessandro) 
  • Scene optimized: Turbo speed, new prevac display, and preliminary scroll icon
  • Open KF angle and gate valve (follow "XGM vacuum incident procedure")
XTD9: (with Alssandro) 
  • Scene optimized: Turbo speed, new prevac display, and scroll icon
  • Open angle and gate valve (follow "XGM vacuum incident procedure")
New project created "SASE1-XGM" which contains both XTD2 and XTD9 XGM vacuum projects, thus scenes from both can be opened from one GUI simultaneously.

11:55 XTD9 vatterflies OPEN 
12:00 XTD2 vatterflies OPEN  
      (V10120V could only be opened after shutdown of device and re initialization) 
 
Maybe upper pressure probes need new calibration -> Check formula 
Prevacuum pressures: 
  • XTD9: 6.4E-4 mbar (G11081P)
  • XTD2: 2.5E-2 mbar (G10100P) and 1.2E-3 mbar (G10101P)

Summary : both XGMs in XTD2 and XTD9 are now back in normal pumping operation, and they were never exposed to more than a few 10E-6mbar. Good. But it took 2 hours and 4 experts.

Entry   OCD, posted by NEREA JARDON on 21 Apr 2017, 15:22 

Dear all,

The service of On-call Duty will be available from AE group during weekend in this number: 6442

Please make a post with the OCD numbers from CAS, WP74 and WP73.

Thank you and bests.

Entry   SASE EPS RACK 1.14 disconnect, posted by Tobias Freyermuth on 21 Apr 2017, 14:36 

We have to disconnect the EPS crate in RACK 1.14 in order to check the interface to the MPS.

I will keep you updated

Entry   Access to control PC, posted by Jan Tolkiehn on 21 Apr 2017, 13:54 

exflplcgwSA1 seems not reachable. This inhibits support for the PLC systems.

Entry   FAILED - Interlock test of the whole gas section in XTD9 - NOT SUCCESSFUL, posted by Raúl Villanueva-Guerrero on 21 Apr 2017, 12:28 

 Due to problems and lack of support of CAS for accessing the devices in XTD9 tunnel through KARABO we couldn´t run the test. The system has been returned to manual operation and will remain like that until next notice.

 

 

    Reply   FAILED - Interlock test of the whole gas section in XTD9 - NOT SUCCESSFUL, posted by Raúl Villanueva-Guerrero on 21 Apr 2017, 13:23 

Raúl Villanueva-Guerrero wrote:

 Due to problems and lack of support of CAS for accessing the devices in XTD9 tunnel through KARABO we couldn´t run the test. The system has been returned to manual operation and will remain like that until next notice.

 

 

As soon we received the request we worked on that one.  After analysing the issue proper response was sent.

​​​----- Forwarded Message -----

​​​​From: "Wajid Ehsan" <wajid.ehsan@xfel.eu>

To: "Raul Villanueva" <raul.villanueva@xfel.eu>

Cc: "Alessandro Silenzi" <alessandro.silenzi@xfel.eu>, "Nerea Jardon" <nerea.jardon@xfel.eu>

Sent: Friday, 21 April, 2017 12:56:14

Subject: Re: Karabo problems in XTD9 - Urgent!


​​​​​Hi Rahul,

we checked all the devices that are in error. The issue is realted with hardware.

Error description is mentioned below:

0x1001 FlagCtrl Error flag from controller

Regards,


Wajid Ehsan 

 
       Reply   FAILED - Interlock test of the whole gas section in XTD9 - NOT SUCCESSFUL, posted by Raúl Villanueva-Guerrero on 21 Apr 2017, 13:35 

Raúl Villanueva-Guerrero wrote:

Raúl Villanueva-Guerrero wrote:

 Due to problems and lack of support of CAS for accessing the devices in XTD9 tunnel through KARABO we couldn´t run the test. The system has been returned to manual operation and will remain like that until next notice.

 

 

As soon we received the request we worked on that one.  After analysing the issue proper response was sent.

​​​----- Forwarded Message -----

​​​​From: "Wajid Ehsan" <wajid.ehsan@xfel.eu>

To: "Raul Villanueva" <raul.villanueva@xfel.eu>

Cc: "Alessandro Silenzi" <alessandro.silenzi@xfel.eu>, "Nerea Jardon" <nerea.jardon@xfel.eu>

Sent: Friday, 21 April, 2017 12:56:14

Subject: Re: Karabo problems in XTD9 - Urgent!


​​​​​Hi Rahul,

we checked all the devices that are in error. The issue is realted with hardware.

Error description is mentioned below:

0x1001 FlagCtrl Error flag from controller

Regards,


Wajid Ehsan 

 

 

Here is the list of devices that are in error:
 

SA1_XTD9_VAC/VALVE/V11090A  Error 3 -> valve stayed between open and closed for too long time (3s set on the valve) (the reset command is sent to the PLC and it cannot clear the error)
SA1_XTD9_VAC/VALVE/V11100A  Error 3 -> valve stayed between open and closed for too long time (3s set on the valve)
SA1_XTD9_VAC/VALVE/V11110A  Error 3 -> valve stayed between open and closed for too long time (3s set on the valve)
SA1_XTD9_VAC/TPUMP/P11220T Error 0x1001 -> err_FlagCtrl -> Error flag from controller (need manual reset on the controller) after reset error is now cleared.
SA1_XTD9_VAC/TPUMP/P11280T Error 0x1001 -> err_FlagCtrl -> Error flag from controller (need manual reset on the controller) after reset error is now cleared.
SA1_XTD9_VAC/VALVE/V11210G Error 0x10001 ->  _err_InterlockDevNotFound  -> Interlock device not found. (the valves depends from a SA1_XTD9_VAC/SWITCH/DP_XGM_DP_ERROR which does not exist. a SA1_XTD9_VAC/SWITCH/DP_XGM_DP_OK is present in the list though, likely a PLC configuration error).
SA1_XTD9_VAC/VALVE/V11220G Error 0x10001 -> _err_InterlockDevNotFound -> Interlock device not found.
 

For the last 2 errors, which are the only one that have a clear PLC problem, I created a bug report in the redmine project of AE.
https://in.xfel.eu/redmine/issues/16510

Cheers

Alessandro Silenzi

Entry   XGM status, posted by Jan Grünert on 21 Apr 2017, 09:59 

XGM status 21.4.2017

During Easter break, the two XGMs in the control system (XTD2+9) had no issues.
XGM@XTD10 however had an issue: tuesday morning it was found that all pumps had stopped. The scroll pump showed an error. UPS apparently had excess load sunday evening 19h30 but couldn't send email (network error). Possibly vented with tunnel air up to 10mbar since that time. Investigation is ongoing.

Thursday enabled DOOCS pressure reading of XGM in XTD10, UPS rechecked

System surveillance on coming weekend: Jan and Theo 1 day

Other remarks:
- WP74 staff have received their dosimeters for ZZ access if required
- some automatic monitoring and info system is needed soon, e.g. karabo to NAGIOS connection

 

Entry   Maintenance/Access in KW17, posted by Tobias Haas on 20 Apr 2017, 17:18 

 In KW17 there will be NO maintenance day on Tuesday (25.04.) 

 
On Monday (24.04.) morning up to about 11:00 we will have the TÜV approval of CS8. During that time 
NO access of "other people" to the XTL tunnel is possible. After the TÜV approval 
up to 13:00 there will be the possibility for URGENT access to the XTL. Access requests 
have to written to the logbook/access requests entry. 
 
The tunnel XTL/XTIN will stay in interlock, access will be possible by ZZ only. 
 
The northern branch XTD2->XS3->XTD4->XDU2 will stay closed, in order not to interrupt the 
magnet commissioning. 
 
This elogbook entry was sent to following experts: 
xfel-opl@desy.de RC mailing list  
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 20 Apr 2017, 10:25 

 Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open

Vacuum:

  • PLC/Karabo Running stably
  • Local tests of ion pumps in XTD9 being done by J. Eidam
  • Work continues on M3 in XTD9 and on the vacuum in XTD10 
  • DPS in XTD9 should be integrated into the vacuum loop. This requires a cycling of the loop. Timing should be coordinated with WP74 because of XGM in XTD2. Unfortunately nobody from WP74 attended the meeting. Hence it was decided to perform the work tomorrow morning.

EPS Loop:

  • Checks for the signal from the undulators and for the fast valve will be done with DESY MPS today

PBLM/Motion Loop:

  • Work on the PBLM motors (ELMO controller) continues.
  • Yesterday it was possible to align the screens 
  • There is a resource problem when trying to read out the cameras. For this reason an additional server needs to be set up dedicated to acquiring the images from the cameras.

SPB Tunnel components

  • Crate that was checked in the lab yesterday was moved back into the tunnel
  • The unstable support of the imager was fixed
  • B. Weinhausen and M. Messerschmidt are testing
  • All modules necessary for loops 1 & 2 were received from Poland
  • Waiting for the "Freigabe" of the cables for SPB Optics

FXE

  • Loops 1,2 and 4 are waiting for input from EETF
  • Loops 3&5 are running
  • No visible testing activity from FXE team

Karabo:

  • Cleanup continues

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Prepare mirror M3 installation
  • Continue testing of PBLMs in XTD9
  • Continue local tests of ion pumps in XTD9
  • Continue testing of SPB tunnel loop

Tasks for tomorrow:

  • Cycle vacuum loop for inclusion of DPS in XTD9

Other topics

  • Weekly SASE1 Readiness meeting tomorrow at 09:00 in XHQ 1.173
  • L. Samoylova requests access to XTD2 to install another webcam
  • Magnet current tests will likely continue through Wednesday in XTD2. Maintenance day to be shifted accordingly probably to Thursday/Friday. More information later
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 19 Apr 2017, 11:49 

Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open

Vacuum:

  • Running stably
  • Work continues on M3 in XTD9 and on the vacuum in XTD10 

EPS Loop:

  • Input from undulator still missing. This requires  fixing a cable in balcony rooms and then testing

PBLM/Motion Loop:

  • Work on the PBLM motors (ELMO controller) continues.
  • It appears that the uneven movement is due to improper setting of motor parameters

Imagers

  • Trigger problem reported yesterday was due to a cabling issue. Apparently during work on the relevant rack cables were unplugged and then wrongly put back
  • Network issue with pop-in (245) in XTD9 solved

SPB Tunnel components

  • Crate with "problem on signal pins" was brought to the lab and checked. Everything was ok. Problem was due to spurious measurement.

Karabo:

  • PSLIT was tested successfully yesterday
  • Behaviour of Karabo when a loop goes down needs to be made more graceful. 
  • Cleanup continues

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Prepare mirror M3 installation
  • Continue testing of PBLMs in XTD9
  • Continue testing of SPB tunnel loop

Other topics

  • None
     

 

Entry   Motion loop, posted by NEREA JARDON on 19 Apr 2017, 11:47 

Dear all,

Today from 13:30h  Mahadi and Natalia will be doing local tests in the PBLM in Rack 1.14 of XTD9, therefore, if someone will be working in the following racks of XTD9, will loose connection to the Motion loop.

Thank you and best regards,

Entry   Trigger and IP address, posted by Andreas Koch on 18 Apr 2017, 16:36 

All trigger problems in XTD2 and XTD9 solved except for one: spb_xtd9_imgpi, probably a cabling issue on the camera side.

IP address problem for camera of sa1_xd2_imgpii45 solved.

Entry   KW16 Accelerator Plans, posted by Tobias Haas on 18 Apr 2017, 13:21 

 Author: Decking

Goals:
- Operation with 10 GeV, 500 pC, 5 kA, 30 bunch
- Increase gradient limits in RF stations
- Technical comissioning of north branch 

XTIN closed all week
XTL open till Tue, 11:00
XTD2 open till Tue, 15:00
XTD4 open till Tue, 15:00
XTD9&XTD10 open all week


|17/04 Mo M |  Easter shutdown
|17/04 Mo A |  Easter shutdown
|17/04 Mo N |  Easter shutdown
|18/04 Tu M |  Interlock pre-test CS8, set XTL interlock at 11:00, Injector beam operation
|18/04 Tu A |  A2 calibration after phase shifter change, Beam operation  to TLD 10 GeV, set interlock XTD2-XTD4
|18/04 Tu N |  Beam operation  to TLD 10 GeV, 30 bunches, 0.5 nC
|19/04 We M |  Slice emittance in BC2; Magnet PS test XTD2-XTD4 
|19/04 We A |  BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4 
|19/04 We N |  BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4 
|20/04 Th M |  Collimation set-up; Magnet PS test XTD2-XTD4 
|20/04 Th A |  BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4 
|20/04 Th N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC; Magnet PS test XTD2-XTD4 
|21/04 Fr M |  Collimation set-up with 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|21/04 Fr A |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|21/04 Fr N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|22/04 Sa M |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|22/04 Sa A |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|22/04 Sa N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|23/04 Su M |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|23/04 Su A |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|23/04 Su N |  Beam operation  to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4 
|24/04 Mo M |  Beam set-up 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo A |  Beam operation  to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo N |  Beam operation  to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 18 Apr 2017, 13:06 

XTD Tunnels open until 15:00. Later XTD2 and XTD4 are closed, XTD9/10 remain open

Vacuum Loop:

Status:

  • One broken Beckhoff terminal was exchanged before the weekend. This was the first failure of this type in 2 years
  • After this the system ran without hickup over the Easter weekend
  • The fix applied for ion pumps that avoids triggering an interlock condition when there is a communication failure on the serial output should be also applied now to other vacuum device, e. g. the turbo pumps

 

EPS Loop:

Status:

  • Requires an update to be done asap so that N. Gerassimova can continue tests with the PBLMs afterwards

Motion Loop:

Status:

  • Movement of the PBLM motors (ELMO controller) is not satisfactory yet. Motors start and stop but the movement is uneven and stops not always requested
  • There is no test set up in the lab. So tests have to be done in the tunnels (XTD9)

PBLMs:

  • All systems in XTD2 were tested and cameras calibrated including some at the beginning of XTD9
  • Work continues on remaining systems in XTD9
  • System with motor movement is still unsatisfactory (see above)

Imagers

Status:

  • 2 Imagers in XTD2 have no trigger signal. Suspicion is that this might be configuration problem. P. Gessler will investigate
  • One pop-in (245) in XTD9 cannot be reached with IP. Suspicion is incorrect network configuration -> K. Fillipakopoulos

SPB Tunnel components

  • Signal pins of the Attenuator crate were tested. DC voltage is seen there at different levels on different pins. This looks problematic -> P. Gessler

Karabo:

Status:

  • Ran stably over the weekend 

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Take equipment and junk out of tunnels
  • Check trigger cabling for imagers in XTD2
  • Check PBLM motor movement and continue testing in XTD9

Other topics

  • Controlled access to tunnels is possible after 1500. Coordination with T. Haas and the DESY run coordination

 

Entry   EPS loop, posted by NEREA JARDON on 18 Apr 2017, 12:09 

Dear all,

The EPS loop is running again with the last modifications concerning devices' names.

Thank you.

Entry   Motion loop, posted by NEREA JARDON on 18 Apr 2017, 11:14 

Dear all,

The Motion loop would be updated now in order to fix names problems with PSLITs motors. In few minutes would be reachable again.

Than you!

Entry   VAC loop up and running agian, posted by Tobias Freyermuth on 13 Apr 2017, 16:21 

The first EtherCAT coupler in 1.7 VAC was broken and is replaced now. The loop is up and running again.

Cheers,

    Tobias

Entry   Interlock tests are finished in Northern Fan, posted by Tobias Haas on 13 Apr 2017, 14:09 

All northern tunnels XTD2/4/9/10 are fully accessible again! 

Entry   Status Interlock Tests Today, posted by Tobias Haas on 13 Apr 2017, 13:19 

Radiation Interlock Tests are finished. Tunnels XTD9 and XTD10 up to the fence at the dump can be accessed right now. Magnet current interlock tests still takes a bit of time (ca. 1h). Once this is also done, I shall post a note 

Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 13 Apr 2017, 12:07 

 Tunnel Closed until approx 1300, Open over the Easter Weekend until Tuesday 1500.

Vacuum:

  • All valves and pumps in XTD2 are working and can be operated remotely
  • The vacuum system including DPS and XGM is interlocked. Interlocks have been tested and are working properly
  • The fast valve and the absorber at the interface to the electron beam vacuum are working and interlocked. The communication with DESY has been successfully tested
  • Some issue exist when switching turbo pumps on/off in Karabo. Then erratic behaviour is observed. Doing the same remotely communicating via TCP directly works ok
  • More testing needs to be done in XTD9

Mirrors, PBLMs, SRA, Attenuator

  • M1 and M2 are installed and under vacuum. M3 will be installed after easter
  • 3 out of 5 motors can be operated in M1 and M2. The mirrors have been moved into a safe position
  • PBLM motors (ELMO driver) can be operated (started and stopped) but operation is still problematic (motors stop in wrong position, movement not linear)
  • On the SRA the connection to two motors is interchanged
  • On the attenuator certain motors occasionally get stuck
  • Slits have been moved out so the beam line is safe for first operation

Imagers:

  •  
  • All imagers tested, motors and cameras, motion loop, EPS loop, for 3 imagers XTD2, and 3 imagers XTD9.
  • All blocking issues concerning tunnel closure solved.
  • Some remaining points that can be treated remotely: Trigger, software delays, others.
  • The Photonics Camera driver is now working in Karabo.
  • Cameras can currently be read out at 3 Hz which is too slow but ok for first beam commissioning

XGM:

  •  
  • XGM inserted into vacuum loop and interlock (in XTD2 and XTD9)
  •  
  • Grounding completed in XTD2+XTD9 (power cycle of rack was needed)
  • Gases ready to be used in XTD2
  • XGM @ XTD2 ready for beam         (need DOOCS middle-layer servers activated) 

FXE

  • Testing finished for all devices in loop1
  • Now waiting for loops 2 and beyond
  •  

SPB

  • SPB tunnel loop deployed. Testing can start next week
  • For the Optics hutch some Beckhoff crates are still missing 
  •  

PLC

  • Fixes to MC2 library (ELMO and TECHNOSOFT motors) will deployed next week and then tested in XTD9
  • FXE loop 2 was modified and loops 3&4 are deployed
  • SPB loop 1 to be deployed today. Working on loop 2

 

KARABO

  • Slow response appears to be solved
  • There are other not so severe bugs on the backlog
  • Currently all high priority components are supported
  • No requires cleanup and day-one component list
  • Monitor stability and robustness

 

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Fix the issue with the disconnected vacuum loop after tunnel reopens

Tasks for the weekend:

  • Relax and look for Easter Eggs
  • AE and CAS will provide contacts on a good will/best effort basis in case an intervention should be necessary

 

 

Entry   EtherCAT loop broken for Vacuum loop, posted by Alessandro Silenzi on 13 Apr 2017, 10:15 

The EtherCAT loop for the vacuum PLC is interrupted at crate 1.6 (XTD2).

This triggered all Beckhoff Terminals  default behaviour from this point on (i.e. Valves Closed, Digital Outputs low, etc.).

 

 

Entry   Status and plans after 09:30 meeting, posted by Tobias Haas on 12 Apr 2017, 12:52 

 Tunnel Closed.

Mirrors:

Status:

  • No information on status of mirrors and PBLM since Optics group was not at the meeting

Vacuum Loop:

Status:

  • All vacuum sections were successfully tested in XTD2 yesterday (work ended very late)
  • DPS was tested successfully and all interlocks and remote controls were working
  • The protection switch on the ion pumps can still not be actuated remotely 
  • XGMs in XTD2 and XTD9 fully in the interlock 
  • V0 valve and absorber were moved and interlock tested. Communication with DESY was also tested and is ok.

EPS Loop:

Status:

  • No explicit information today (see remark above)

Motion Loop:

Status:

  • No explicit information today (see remark above)

Imagers

Status:

  • All imagers in XTD2 are ok
  • Trigger is not working on one of three imagers. 
  • Testing proceeded in XTD9 yesterday
  • One camera in one pop-in can not be reached (Network problem?)

Karabo:

Status:

  • Running stably
  • Work required now:
  • Photonics Camera driver
  • Clean up the project database
  • Clean up master equipment list

 

Tasks for today:

 

Note: All loops should be left running and no changes to Karabo.

  • Proceed with remote testing
  • Check out adequacy of scenes
  • Monitor stability and responsiveness of GUI Server and Log Servers 
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Cleanup Karabo

Tasks for tomorrow:

  • Tunnels should re-open tomorrow
  • Continue tests from remote and check stability and robustness of systems

Other topics

  • Tunnels open over the Easter weekend and also during the day on Tuesday 18 April
  • There will be a SASE Readiness Meeting at 09:00 on Thursday in XHQ E1.173

 

Entry   Imager status, posted by Andreas Koch on 12 Apr 2017, 09:16 

Imager Status, 12.4.17

-          All imagers tested, motors and cameras, motion loop, EPS loop, for 3 imagers XTD2, and 3 imagers XTD9.

-          All blocking issues concerning tunnel closure solved.

-          Remaining issues:

o   Camera trigger, tbd. for 4 imagers.

o   Camera driver for SR imager, Photonic Science, tbd.

o   Camera of sa1-xtd9-imgpii45-cam-beamview not reachable via IP address, tbd..

o   Camera display is now at around 2 Hz, not yet full speed.

o   Store image function, tbd.

o   Firmware update to operate braking switches for homing procedure, tbd.

Entry   XGMs in loop, posted by Jan Grünert on 11 Apr 2017, 22:36 

Both SASE1 XGMs (in XTD2 and XTD9) are now again in the Vacuum Control Loop, their vacuum being controlled by Beckhoff/karabo. This works fine.

Therefore: DO NOT FOOL AROUND WITH THE VACUUM LOOP !

Since we all cannot enter the tunnel XTD2 in the next two days, it's agreed that the Vacuum Loop is NOT going to be touched at all, since  we cannot intervene in the tunnel if something goes wrong.

Entry   Beam Stopper and V0 valve test - SUCCESSFUL, posted by Raúl Villanueva-Guerrero on 11 Apr 2017, 18:38 

 The Interlock conditions for these two components has been positively tested but not exhaustively done:

The triggering of both via the actuation on the Fast Valve----------------->DONE and OK

Their triggering via HV down of each of the 6 ion pumps------------------>Partially DONE and OK: Partially means that only one of the pumps randomly chosen has been deactivated. The agreement is that the other remaining 5 can be done later, also from the office since the correspondence between the devices and the physical components has been confirmed. 

Also, the individual actuation of both, Beam Stopper and V0 valve has been proof showing a consistent behaviour regarding the interlock definition.

Finally the XFEL Vacuum OK signal is available but AE is currently improving it. By the moment is not automatically sent to DESY, but instead it needs to be activated manually. According to AE feedback this should be corrected in the following days.

 

Entry   Fast Valve Test - SUCCESFUL, posted by Raúl Villanueva-Guerrero on 11 Apr 2017, 18:29 

 The Fast Valve test has been positively tested. 

It has been consider that the signal on the EPS to open again, should be also available in the vacuum loop. Still this need to be further discussed.

 

 

Entry   XTD2 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESSFUL, posted by Raúl Villanueva-Guerrero on 11 Apr 2017, 17:44 

 The interlock definition for complete isolation of the whole section based on high pressure signal has been successfully tested. 

DPS (Upstream and Downstream) are now fully "controlled" by Karabo.

XGM has been reported by J. Grünert that it will be re-integrated during the evening.

 

Still some problems to call the remote operation of the turbopumps from Karabo, but it doesn´t compromise any of the interlock definitions (only is troublesome if the one needs to work with the pump, for instance after the interlock has been triggered).

Entry   EPS loop, posted by NEREA JARDON on 11 Apr 2017, 15:38 

Dear all,

The EPS loop would be stopped, in order to correct some issues with the hardware in Rack 1.1 and Rack 1.5 in XTD2. We will upload it as soon as possible and I will post a new entry here when it is running again.

Thank you,

Entry   Big issue with XGM vacuum in both XTD2 and XTD9 !, posted by Jan Grünert on 11 Apr 2017, 15:24 
Both XGMs were and are on manual control (but the remote cables into the turbo pump controllers remained plugged in as usual) = both XGMs are "out of the VAC loop". 

In XTD2, I saw around 13h that both turbos were off (0 Hz) and the pressure was at 10E-4 mbar !

The green light above the ON-button was flickering. 
I switched parameter 023 (Motor TMP) to ON and restarted both pumps. The green light above the ON-button 
 stops flickering and goes steady green. 
 
---going to XTD9 
 
In XTD9, I saw that the upstream turbo was off (0 Hz) and the pressure was in the lower 10E-6mbar. 
The downstream turbo in XTD9 was still operating. 
Parameter 023 to ON, and restart pump. 
 
---going to XTD2 
 
Error codes 6, 6, 98, 2, 37 on one pump, error codes 6,6,6 on the other (XTD2).
I unplugged the REMOTE cables in XTD2 and XTD9 to avoid further trouble as long as we are on "manual". 
This info was also sent by email to the involved experts.
Entry   Script to install the latest karabo, posted by Alessandro Silenzi on 11 Apr 2017, 13:48 download.sh

Please find in attachment the dowload bash script for the latest Karabo.

if your system has a "karabo" directory, this script will not overwrite it, but the update will fail.
In this case, remove or rename the karabo directory.

To use it:
1. download the script in a directory of your choice.

2. open a terminal and execute it with
   $ bash PATH_TO/download.sh

Where PATH_TO is the path where the download script was saved.

Entry   Motion loop, posted by NEREA JARDON on 11 Apr 2017, 13:32 

Dear all,

Sorry for disturbing again, I will do a small update to put one missing coupler in the hardware configuration in rack 1.18, the loop would be running again in few minutes.

Thank you!

Entry   Motion Loop, posted by NEREA JARDON on 11 Apr 2017, 13:24 

Dear all,

Motion loop is running again with the last update (names for PSLIT and LVDT have been changed).

Thank you,

Entry   Status after 0930 meeting, posted by Tobias Haas on 11 Apr 2017, 12:51 

Tunnel Open.

Mirrors:

Status:

  • Vacuum on M2 should be good enough to switch on ion pumps
  • Surveying work going on 

Vacuum Loop:

Status:

  • Several vacuum sections successfully tested in XTD9 yesterday
  • Tests need to proceed in XTD2 today
  • The protection switch on the ion pumps cannot be actuated remotely 
  • Loop needs an update for the XGM
  • XGM was in the vacuum interlock overnight. Will be taken out during the day but should be put back at the end of the day
  • Interlock of High Voltage with vacuum in XGM not working yet
  • V0 valve needs to be exercised in collaboration with DESY 

EPS Loop:

Status:

  • The terminal exchanged for the FEL imager was not the broken one. Another terminal needs to be exchanged today
  • The MCP needs to be moved out of the beam manually. This will be checked using the EPS switch. For this the EPS loop is needed

Motion Loop:

Status:

  • An improved fix for the motors not stopping was deployed yesterday
  • The loop needs to be reconfigured to replace the SRA motors 
  • One broken motor was exchanged on the mirror chambers and needs to be tested

Imagers

Status:

  • All motion tests in XTD2 done. Now continue in XTD9
  • Photonics camera driver still not working but not critical for tunnel closure (there is also a workaround by the name of ebus player)
  • EPS switch on FEL imager needs testing  after terminal replacement

Karabo:

Status:

  • New version with TCP was deployed. Experience overnight is good

 

Tasks for today:

 

Note: Loop reconfiguration and updates of Karabo to be done in the morning. Testing can resume after lunch. Status updates should please be recorded in the log

  • Reconfigure vacuum, motion loop (updates for XGM interlock, SRA motors)
  • Replace broken terminal in EPS loop for FEL imager 
  • Move MCP out of the beam manually and check using EPS
  • Continue systematic test of the vacuum components (J. Eidam, V. Bondar)
  • Test EPS switch on FEL imager after terminal exchange (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Test V0 and absorber

Tasks for tomorrow:

  • Tunnels closed
  • All loops should run stable
  • No or only minimal interference with Karabo
  • Continue tests from remote and check stability and robustness of systems

Other topics

  • Tunnels open over the Easter weekend and also during the day on Tuesday 18 April
  • There will be one more standup 09:30 meeting tomorrow (Wednesday)
  • There will be a SASE Readiness Meeting at 09:00 on Thursday
Entry   Vacuum Loop, posted by NEREA JARDON on 11 Apr 2017, 11:48 

Dear all,

Vacuum loop is up and running, we would wait till Raul check the interlock of the "OK" signal for the Vacuum and then, if everything is correct, we would put again the XGM controlled by the Vacuum PLC.

Thank you!

Entry   EPS & Motion, posted by NEREA JARDON on 10 Apr 2017, 20:05 

Dear all,

EPS and Motion loop have been updated to the last framework version with the last hotfixed. Vacuum loop would be done tomorrow in order to let the XGM work the hole night and part of the morning tomorrow.

Best Regards,

Entry   update of the EPS loop, posted by Tobias Freyermuth on 10 Apr 2017, 19:19 

Dear cllougues,

 

we will run an update of the EPS-loop, in order to have a proper solution for the latest hotfix, as it was announced this morning in the standup meeting.

 

Cheers,

    Tobias

Entry   Vacuum Loop, posted by NEREA JARDON on 10 Apr 2017, 18:13 

Dear all,

Right now both XGMs are into the loop and would be running. The loop must run continuously, in case you should do any work, just let me know in advanced.

Thank you,

Entry   KARABO Update maintainance, posted by Alessandro Silenzi on 10 Apr 2017, 12:31 

The karabo services will be down for an upgrade for an hour.

The access will resume at 13:30.

Entry   Schedule after 09:30 Meeting, posted by Tobias Haas on 10 Apr 2017, 10:47 

Tunnel Open.

Mirrors:

Status:

  • Both mirrors M1 & M2 installed
  • Vacuum being closed in M2 today should be ready for ion pumps tomorrow
  • Surveying work going on (see email by M. Schlösser below)

Vacuum Loop:

Status:

  • Needs reconfig for XGM in XTD9
  • Interlock tests on XGM in XTD2 should go on. 
  • 2 Turbopumps still have a communication problem (J. Tolkiehn is working on this)
  • 6 Ion pumps in XTD9 still have communication problems (list was given by AS to JE)
  • Systematic testing according to the list by J. Eidam with V. Bondar starting this afternoon

EPS Loop:

Status:

  • One terminal needs to be exchanged for FEL Imager 
  • Description of EPS interlock still missing. It is planned to start with just one imager in for first beam commissioning
  • One fiber connection from Balcony room to DESY still to be done by DESY. AFter this testing of communication should start

Motion Loop:

Status:

  • Quick fix for motors not stopping was deployed on Friday. Now TF is working on a better fix to be deployed this evening

Imagers

Status:

  • EPS switch on FEL imager should be checked after exchange of terminal
  • Photonics camera driver still not working but not critical for tunnel closure
  • Work should now concentrate on SR imager

Karabo:

Status:

  • New version with TCP fix needs to be deployed. This should also be done to the local software run by users.

 

Tasks for today:

 

Note: Loop reconfiguration and updates of Karabo to be done in the morning. Testing can resume after lunch. Status updates should please be recorded in the log

  • Reconfigure vacuum and motion loops (updates for XGM interlock, motors not stopping)
  • Replace broken terminal in EPS loop for FEL imager 
  • Continue test XGM interlocks (N. Jardon, M. Planas, T. Matsopoulos)
  • Go through systematic test of the vacuum components (J. Eidam, V. Bondar)
  • Continue tests with PBLM in the tunnels (M. Jidda)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Test communication between XFEL and DESY MPS once fiber connection from Balcony rooms to MPS is available (B. Fernandes)

Tasks for tomorrow:

  • Put XGM into the vacuum interlock
  • Continues testing of all interlock conditions for the vacuum

Other topics

  • Surveying is going on for mirror chambers M1 and M2 in XTD2
  • We need a well defined startup configuration of PLC, Karabo, Parameters, List of devices (A. Silenzi)

Email by M. Schlösser re alignment

Hi Tobias, hi Markus, Hi Winni,

Tobias, we discussed briefly the schedule for the T9 and T10 beamlines for the next few days, when we met in the tunnel yesterday.

From what i understand it is impossible to finish T10 until April 11th from the alignment and vacuum side. And probably more important, this also holds true for T9. There is at least one major problem with the alignment of the mirror chambers of T9 in XTD2, which will need some additional days to solve.
From my understanding at least the T9 beamline should be closed and aligned before putting SASE1 in operation. While it will of course be possible to send electrons down to the XSDU2 dump, it will not be possible to send photons to the experimental hall with the current state of the beamline.

Since it is not possible to work in XTD10 while the SASE1 electron beamline is in operation, i would propose to also finish this beamline before SASE1 electron startup. Since there is major work to do in XTD10 to finish the beamline, there is no hope to  do the remaining work during maintenance days. Finishing the beamline would require a major shutdown of the SASE1 branch later.

Since there will be no alternative to send the beam to (e.g. SASE2) for the next year (?), it does not make sense to stop work in XTD10 now, just to continue later then, without any overall benefit for the machine.

Of course i don't have a complete overview of all the machine schedule, but from my point of view it would make more sense to finish work in the northern branch, at least to align all components and to close the vacuum system, even if that means some more weeks before the SASE1 startup.

cu
Markus

Entry   Vacuum Loop, posted by NEREA JARDON on 10 Apr 2017, 10:09 

Dear all,

The Vacuum loop is running again, now with XGM XTD9 included. We will be testing interlocks in XGM XTD2, so could be needed another upload.

Thank you,

Entry   Vacuum Loop, posted by NEREA JARDON on 10 Apr 2017, 09:36 

Dear all,

I will update the Vacuum loop in order to add the XGM XTD9 into it. It will be running in few minutes again.

Thank you.

Entry   Acceptance test IMAGERS (FRIDAY 07-04-2017), posted by wajid ehsan on 07 Apr 2017, 19:13 

 

SA1_XTD2_IMGPII45:
 
1) MOTOR/SCREEN(DONE)
2) Check operation of range of movement, defined by end switches (DONE
3) Check repeatability (DONE)
4) Switch on/off LED (DONE)
5) Switch on/off camera (DONE)
6) Acquire images with a camera (DONE)
7) Hardware Trigger of camera (DONE)
8) EPS switch (DONE)

SA1_XTD2_IMGFEL:
 
1) Move all motors (DONE)
 1.1) MOTOR/SCREEN (DONE)
 1.2) MOTOR/FILTER (DONE)
3) Check operation of range of movement, defined by end switches (DONE)
 3.1)  END_ Switches/SCREEN (DONE)
 3.2) END_Switch/FILTER (DONE
4) Check repeatability (DONE)
5) Switch on/off LED. (DONE)
6) Switch on/off camera. (DONE)
7) Take images with a camera. (DONE)
8) Trigger of camera (DONE)
9) ESP switch (NOT WORKING, hardware issue, to be tested)
10) Braking switch_SCREEN_MOTOR (NOT WORKING, to be tested)

SA1_XTD2_IMGSR:
1)  Test motors.  (DONE)
 1.1) Motor/Screen (DONE)
 1.2) Motor/y (DONE)
 1.3) Motor/ Focus (DONE)
 1.4) Motor / IRIS (DONE)
2) End Switches:
 2.1 Motor/Screen (DONE)
 2.2 Motor/y (DONE)
3. Check repeatability(DONE)
4. Switch on/off LED (DONE)
5. Switch on/off camera (DONE)
6. Acquire images (NOT DONE, Photonic science camera device is not working but acquired images with eBus(low level driver))
7) EPS (DONE)
8) Braking switch_SCREEN_MOTOR (NOT WORKING)

 

Entry   Hotfix for all loops (VAC, MOV, EPS) deployed, posted by Tobias Freyermuth on 07 Apr 2017, 17:43 

Dear collogues,

 

all loops are up and running after deploying the hotfix.

 

Have a nice weekend,

    Tobias

    Reply   Hotfix for all loops (VAC, MOV, EPS) deployed, posted by Tobias Freyermuth on 07 Apr 2017, 17:54 

Tobias Freyermuth wrote:

Dear collogues,

 

all loops are up and running after deploying the hotfix.

 

Have a nice weekend,

    Tobias

 

 Confirmed from Karabo side.

Entry   Hotfix for all loops (VAC, MOV, EPS), posted by Tobias Freyermuth on 07 Apr 2017, 16:41 

Dear collogues,

we have added a hotfix to the framework, to make sure, that no motor can be moved if the feedback signals are missing. This update will be done due to the mentioned issue in the readiness meeting this morning.

We will update the loops again after the weekend, with a proper solution.

The hotfix will send all devices of a loop into error if the feedback of a terminal in the loop is missing.

I will write a new entire in the Logbook, if we are done with the updates.

 

Cheers,

    Tobias

Entry   Test on Karabo trunk show promising results, posted by Alessandro Silenzi on 07 Apr 2017, 16:02 02.png12.png

I have deployed the Karabo master (the HEAD of our development) in the control network for the Vacuum loop device server.

During last weeks Karabo was not able to cope with the data coming from the PLC for this loop (our biggest to date)
and would become unresponsive after 5 to 10 minutes.

The current system is online since 3.5 hours and is still responsive.

Please note:
This is a partial release and the GUI might show unwanted behaviour.
Please leave the vacuum loop untouched during the weekend.

In attachment you can find an example of unwanted behaviour and the DPS gui

Thank you very much and have a nice weekend!

Alessandro

Entry   EPS loop, posted by NEREA JARDON on 07 Apr 2017, 11:57 

Dear all, EPS loop is again up and running.

Thank you!

Entry   EPS loop, posted by NEREA JARDON on 07 Apr 2017, 11:12 

Dear all, I will update EPS loop in order to integrate new hardware changes. I will post a new entry when the work is done.

Thank you!

Entry   Motion loop, posted by NEREA JARDON on 07 Apr 2017, 10:31 

I have made an update for the Motion loop requested to test correctly the Attenuators. Now the loop is running again.

Thank you and sorry for inconvenience.

Entry   motion loop not working !?, posted by Andreas Koch on 06 Apr 2017, 13:36 

Has anyone an idea why the motion loop is not working? Thanks Andreas

    Reply   motion loop not working !?, posted by Andreas Koch on 06 Apr 2017, 14:32 

Andreas Koch wrote:

Has anyone an idea why the motion loop is not working? Thanks Andreas

Hello Andreas,
please use redmine for bug reports. I opened a redmine issue for this:

https://in.xfel.eu/redmine/issues/16265

Please log in and give more details on what you experienced.

In case of emergency contact your main contact person Wajid.

Cheers

Alessandro

       Reply   motion loop not working !?, posted by Andreas Koch on 06 Apr 2017, 14:45 

Andreas Koch wrote:

Andreas Koch wrote:

Has anyone an idea why the motion loop is not working? Thanks Andreas

Hello Andreas,
please use redmine for bug reports. I opened a redmine issue for this:

https://in.xfel.eu/redmine/issues/16265

Please log in and give more details on what you experienced.

In case of emergency contact your main contact person Wajid.

Cheers

Alessandro

 Thanks, Alessandro,

It's working again.
It was the Wifi that slowed down.
Andreas
 
Entry   Status and Schedule after 09:30 meeting, posted by Tobias Haas on 06 Apr 2017, 11:27 

 Tunnel Open.

Mirrors:

Status:

  • Vacuum will be closed on M1
  • M2 installation tomorrow or latest on Monday

Vacuum Loop:

Status:

  • Loop is up
  • XGM was integrated but tests needed on the interlocks. Hence valves to DPS now in manual mode (overrides interlock)
  • Interface to MPS has been successfully tested
  • Need to test fast valve connection to VAC and to MPS (Status re cabling was unclear this morning)
  • A few pumps still  have communication problems (to be discussed between AE and CAS)

EPS Loop:

Status:

  • AE did most of the missing wiring
  • Description of EPS interlock still missing. It is planned to start with just one imager in for first beam commissioning
  • One fiber connection from Balcony room to DESY still to be done by DESY

Motion Loop:

Status:

  • Problem on ELMO motors with linear drive persists. Needs additional testing

Imagers

Status:

  • Both motors working on FEL imager
  • Work should now concentrate on SR imager

Karabo:

Status:

  • Problem in TCP implementation identified that is suspected to cause the long delays observed e. g. with the imagers. Now needs extensive testing
  • Still no data recording achieved
  • Stability still needs monitoring

 

 

Tasks for today:

  • Work on GUI for the vacuum loop (J. Eidam, V. Bondar)
  • Test XGM interlocks (N. Jardon, M. Planas, T. Matsopoulos)
  • Continue tests with PBLM in the tunnels (M. Jidda)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Push DESY to install fiber connection from Balcony rooms to MPS (P. Gessler)

Tasks for tomorrow:

  • Put XGM into the vacuum interlock
  • Perform careful testing of all interlock conditions for the vacuum

Other topics

  • Regular SASE1 readiness meeting at 09:00 tomorrow in XHQ E1.173
  • Need to perform tests with EPS interlock conditions
  • Need to test fast valve connection to VAC and to MPS
  • Gas system for diagnostics needs to be flushed
Entry   Imager, posted by Andreas Koch on 06 Apr 2017, 09:16 

-

XTD2, FEL imager with Wajid

Screen, motor, switches - ok, minor braking switch issue.

LED, camera power – ok.

Filter, motor, parameter issue, should be solved now, to be tested again today.

EPS tests and SR imager tests, to be done.

 

XTD9 cameras, no power, will check today with Bernard.

 

Entry   DESY wants to close XTD2 & XTD4 over the weekend..., posted by Tobias Haas on 05 Apr 2017, 16:40 

I expect that some of us may need the weekend as a reserve (e. g. mirror installation). So we should probably say no. Let's discuss more tomorrow at 09:30 

Entry   alio monocromator tests, posted by Nicola Coppola on 05 Apr 2017, 16:24 

test finshed.

both stages were moved.

voltage value and position read out from encoder opposite in directionality

some strange limitation on the postiion range seen.

both stages are now at around the 0 position with few mm error.

XD to ask alio/nanoomotion on the matter

XD will provide few lines of comment

Entry   Vacuum Loop, posted by NEREA JARDON on 05 Apr 2017, 14:27 

Dear all,

The XGM XTD2 is already into the Vacuum loop and the loop is running. We would continue with the interlock tests today in the afternoon, but would not affect to other parts of the Vacuum loop.

Also was requested to change the Karaboo names of the devices in XGM XTD2, therefore a firmware updated would be necessary and would be performed today in the afternoon after VAC-MPS communication tests.

Thank you!

Entry   Please inform on rack status 1.18, posted by Andreas Koch on 05 Apr 2017, 14:14 

The rack 1.18 in XTD9 is not operational at the moment because Nicola is working on it. Nerea, Tobias or others let me know when it is fully operational again. This avoids checking it in the tunnel. Alternatively, let me know if I can check remotely.

Entry   Schedule after 0930 Meeting, posted by Tobias Haas on 05 Apr 2017, 10:15 

Tunnel Open.

Vacuum Loop:

Status:

  • Communication problem with Ion pump controllers is fixed after adjusting controller settings
  • Loop is now down to allow inclusion of XGM

EPS Loop:

Status:

  • Temperature sensors return reasonable values after EPS loop fix
  • EPS to MPS interface is working but fiber to central desy interface still lacking

Motion Loop:

Status:

  • Should be up for testing PBLMs and Imagers

Imagers

Status:

  • Test of FEL imager ok, but hampered by occasional slow response of the system
  • SR Imager needs work on the driver

Tasks for today:

  • Include XGM in Vacuum loop (N. Jardon, M. Planas, T. Matsopoulos, V. Bondar)
  • Test updated MC2 lib with PBLM in the tunnels (N. Gerasimova, M. Jidda)
  • Work on camera driver for SR imager (A. Koch and W. Ehsan)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers
  • Set up monitoring of temperatures and pressures overnight
  • Push DESY to get fiber connection to MPS (P. Gessler)

Tasks for tomorrow:

  • Terminals need to be added and firmware adjustments made in motion loop (take loop down as early as possible for one hour)
  • Test EPS inputs to MPS system with DESY people
  • Power down crate 1.15 for grounding. Could take longer than one day

Other topics

  • N. Jardon needs complete info of motor names in rack 1.18
Entry   Vacuum Loop, posted by NEREA JARDON on 04 Apr 2017, 19:25 

Dear all,

Tomorrow at first hour, some hardware modules would added in Rack 1.1 and 1.9 in XTD2 in the Vacuum loop. Therefore the communication would be interrupted till the firmware is downloaded to the PLC, around 10h-10.30h should be running again to add the XGM XTD2 into the loop. Although, I will post a new entry to let you know.

Thank you,

Entry   UPDATE on Temperature sensors for EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 18:49 

Here are the updated values for the temperature sensors inn the EPS loop.

Now Thermocouples work!

FXE_XTD9_COLB/TSENS/T1 23.1
FXE_XTD9_COLB/TSENS/T2 23.2
FXE_XTD9_PBLM/TSENS/BLADE_BOTTOM 22.94
FXE_XTD9_PBLM/TSENS/BLADE_LEFT 23.0
FXE_XTD9_PBLM/TSENS/BLADE_RIGHT 23.0
FXE_XTD9_PBLM/TSENS/BLADE_TOP 22.98
SA1_XS3_SHUT/TSENS/T1 4.0
SA1_XS3_SHUT/TSENS/T2 4.0
SA1_XS3_SHUT/TSENS/T3 4.0
SA1_XS3_SHUT/TSENS/T4 4.0
SA1_XTD2_ABS/TSENS/T1 19.5
SA1_XTD2_ABS/TSENS/T2 19.6
SA1_XTD2_ATT/TSENS/A1 30.7
SA1_XTD2_ATT/TSENS/A2 1372.0
SA1_XTD2_ATT/TSENS/A3 30.3
SA1_XTD2_ATT/TSENS/A4 31.02
SA1_XTD2_ATT/TSENS/A5 31.96
SA1_XTD2_ATT/TSENS/A6 31.11
SA1_XTD2_ATT/TSENS/A7 30.75
SA1_XTD2_ATT/TSENS/A8 31.0
SA1_XTD2_ATT/TSENS/A9 31.4
SA1_XTD2_COLA/TSENS/T1 1372.0
SA1_XTD2_COLA/TSENS/T2 1372.0
SA1_XTD2_COLB/TSENS/T1 27.8
SA1_XTD2_COLB/TSENS/T2 1372.0
SA1_XTD2_CRL/TSENS/LENS_10_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_10_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_1_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_1_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_2_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_2_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_3_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_3_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_4_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_4_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_5_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_5_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_6_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_6_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_7_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_7_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_8_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_8_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_9_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_9_T2 850.0
SA1_XTD2_DPS1/TSENS/FLOW 20.3
SA1_XTD2_DPS1/TSENS/RETURN1 20.3
SA1_XTD2_DPS1/TSENS/RETURN2 20.1
SA1_XTD2_DPS3/TSENS/FLOW 44.2
SA1_XTD2_DPS3/TSENS/RETURN1 41.6
SA1_XTD2_DPS3/TSENS/RETURN2 44.2
SA1_XTD2_PBLM/TSENS/BLADE_LEFT 32.8
SA1_XTD2_PBLM/TSENS/BLADE_RIGHT 33.7
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_B4C 19.7
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_W 19.4
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_B4C 18.6
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_W 18.6
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_B4C 19.3
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_W 19.2
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_B4C 19.4
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_W 19.4
SA1_XTD9_PBLM/TSENS/BLADE_LEFT 23.68
SA1_XTD9_PBLM/TSENS/BLADE_RIGHT 24.13
SPB_XTD9_COLB/TSENS/T1 22.9
SPB_XTD9_COLB/TSENS/T2 1372.0
SPB_XTD9_DPS1/TSENS/FLOW 850.0
SPB_XTD9_DPS1/TSENS/RETURN1 850.0
SPB_XTD9_DPS1/TSENS/RETURN2 850.0
SPB_XTD9_DPS2/TSENS/FLOW 850.0
SPB_XTD9_DPS2/TSENS/RETURN1 850.0
SPB_XTD9_DPS2/TSENS/RETURN2 850.0
SPB_XTD9_PBLM/TSENS/BLADE_BOTTOM 23.21
SPB_XTD9_PBLM/TSENS/BLADE_LEFT 23.01
SPB_XTD9_PBLM/TSENS/BLADE_RIGHT 23.19
SPB_XTD9_PBLM/TSENS/BLADE_TOP 23.12
SPB_XTD9_SHUT/TSENS/T1 1372.0
SPB_XTD9_SHUT/TSENS/T2 1372.0
SPB_XTD9_SHUT/TSENS/T3 1372.0
SPB_XTD9_SHUT/TSENS/T4 1372.0

 

Entry   Progress on Vacuum Loop, posted by Tobias Haas on 04 Apr 2017, 18:16 

J. Eidam, V. Bondor, T. Freyermuth checked Ion pump controller settings in XTD2 and XTD9.

Many controllers were found to have incorrect settings. All pumps in XTD2 now respond and give pressure readings. There remains the problem that the PLC is looking for the wrong channel in the case where 2 pumps are connected to one controller (Is 1 & 3 and PLC looks for 1 & 2). J. Eidam now checks channel numbers on all controller. T. Freyermuth then regenerates the firmware. A. Silenzi set up pressure recording for pumps P10050I, P10060I and P10200I to run overnight. 

Entry   Meeting at 17:00 should take place at 17:45, posted by Tobias Haas on 04 Apr 2017, 16:31 

since tunnel access is now possible 

Entry   Access to XTD2 and XTD9 is now possible , posted by Tobias Haas on 04 Apr 2017, 16:29 

Interlocks in the northern fan are broken! 

Entry   Access to XTD2, posted by Tobias Haas on 04 Apr 2017, 15:11 

MPS informed me that they hit some problems and that they still need 30 mins to 1 h until we can go to XTD.  

Entry   Temperatures from EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 12:28 

This is the list of data coming directly from the PLC via its TCP client connected to the EPS PLC.

Format:

deviceName  temperature  status errorCode

XTD2

==================================================

SA1_XS3_SHUT/TSENS/T1 0.4000000059604645 0xa020 0x0
SA1_XS3_SHUT/TSENS/T2 0.4000000059604645 0xa020 0x0
SA1_XS3_SHUT/TSENS/T3 0.4000000059604645 0xa020 0x0
SA1_XS3_SHUT/TSENS/T4 0.4000000059604645 0xa020 0x0
SA1_XTD2_ABS/TSENS/T1 0.0 0x20 0x0
SA1_XTD2_ABS/TSENS/T2 0.0 0x20 0x0
SA1_XTD2_ATT/TSENS/A1 30.739999771118164 0x20 0x0
SA1_XTD2_ATT/TSENS/A2 1372.0 0x15020 0x0
SA1_XTD2_ATT/TSENS/A3 30.380002975463867 0x20 0x0
SA1_XTD2_ATT/TSENS/A4 31.05000114440918 0x20 0x0
SA1_XTD2_ATT/TSENS/A6 31.130002975463867 0x20 0x0
SA1_XTD2_ATT/TSENS/A7 30.78000259399414 0x20 0x0
SA1_XTD2_ATT/TSENS/A8 30.98000144958496 0x20 0x0
SA1_XTD2_ATT/TSENS/A9 33.5 0x20 0x0
SA1_XTD2_COLA/TSENS/T1 0.0 0x1020 0x0
SA1_XTD2_COLA/TSENS/T2 0.0 0x1020 0x0
SA1_XTD2_COLB/TSENS/T1 0.0 0x20 0x0
SA1_XTD2_COLB/TSENS/T2 0.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_10_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_10_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_1_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_1_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_2_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_2_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_3_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_3_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_4_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_4_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_5_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_5_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_6_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_6_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_7_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_7_T2 33.5 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_8_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_8_T2 33.5 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_9_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_9_T2 33.5 0x1020 0x0
SA1_XTD2_DPS1/TSENS/FLOW 2.0300002098083496 0x20 0x0
SA1_XTD2_DPS1/TSENS/RETURN1 33.5 0x20 0x0
SA1_XTD2_DPS1/TSENS/RETURN2 2.0200002193450928 0x20 0x0
SA1_XTD2_DPS3/TSENS/FLOW 33.5 0x20 0x0
SA1_XTD2_DPS3/TSENS/RETURN1 4.160000324249268 0x20 0x0
SA1_XTD2_DPS3/TSENS/RETURN2 4.420000076293945 0x20 0x0
SA1_XTD2_PBLM/TSENS/BLADE_LEFT 32.900001525878906 0x20 0x0
SA1_XTD2_PBLM/TSENS/BLADE_RIGHT 33.5 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_W 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_W 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_W 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_W 0.0 0x20 0x0
 

XTD9

============================================================

SA1_XTD9_PBLM/TSENS/BLADE_LEFT 24.31999969482422 0x20 0x0
SA1_XTD9_PBLM/TSENS/BLADE_RIGHT 24.810001373291016 0x20 0x0
SPB_XTD9_COLB/TSENS/T1 0.0 0x20 0x0
SPB_XTD9_COLB/TSENS/T2 0.0 0x1020 0x0
SPB_XTD9_DPS1/TSENS/FLOW 33.5 0x1020 0x0
SPB_XTD9_DPS1/TSENS/RETURN1 85.0 0x1020 0x0
SPB_XTD9_DPS1/TSENS/RETURN2 85.0 0x1020 0x0
SPB_XTD9_DPS2/TSENS/FLOW 85.0 0x1020 0x0
SPB_XTD9_DPS2/TSENS/RETURN1 85.0 0x1020 0x0
SPB_XTD9_DPS2/TSENS/RETURN2 85.0 0x1020 0x0
SPB_XTD9_PBLM/TSENS/BLADE_BOTTOM 23.05000114440918 0x20 0x0
SPB_XTD9_PBLM/TSENS/BLADE_LEFT 22.860000610351562 0x20 0x0
SPB_XTD9_PBLM/TSENS/BLADE_RIGHT 23.05000114440918 0x20 0x0
SPB_XTD9_PBLM/TSENS/BLADE_TOP 23.05000114440918 0x20 0x0
SPB_XTD9_SHUT/TSENS/T1 0.0 0x1020 0x0
SPB_XTD9_SHUT/TSENS/T2 0.0 0x1020 0x0
SPB_XTD9_SHUT/TSENS/T3 0.0 0x1020 0x0
SPB_XTD9_SHUT/TSENS/T4 0.0 0x1020 0x0
FXE_XTD9_COLB/TSENS/T1 0.0 0x20 0x0
FXE_XTD9_COLB/TSENS/T2 0.0 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_BOTTOM 22.780000686645508 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_LEFT 22.8700008392334 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_RIGHT 22.850000381469727 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_TOP 22.93000030517578 0x20 0x0
 

    Reply   Temperatures from EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 12:43 

Alessandro Silenzi wrote:

This is the list of data coming directly from the PLC via its TCP client connected to the EPS PLC.

Format:

deviceName  temperature  status errorCode

XTD2

==================================================

SA1_XS3_SHUT/TSENS/T1 0.4000000059604645 0xa020 0x0
SA1_XS3_SHUT/TSENS/T2 0.4000000059604645 0xa020 0x0
SA1_XS3_SHUT/TSENS/T3 0.4000000059604645 0xa020 0x0
SA1_XS3_SHUT/TSENS/T4 0.4000000059604645 0xa020 0x0
SA1_XTD2_ABS/TSENS/T1 0.0 0x20 0x0
SA1_XTD2_ABS/TSENS/T2 0.0 0x20 0x0
SA1_XTD2_ATT/TSENS/A1 30.739999771118164 0x20 0x0
SA1_XTD2_ATT/TSENS/A2 1372.0 0x15020 0x0
SA1_XTD2_ATT/TSENS/A3 30.380002975463867 0x20 0x0
SA1_XTD2_ATT/TSENS/A4 31.05000114440918 0x20 0x0
SA1_XTD2_ATT/TSENS/A6 31.130002975463867 0x20 0x0
SA1_XTD2_ATT/TSENS/A7 30.78000259399414 0x20 0x0
SA1_XTD2_ATT/TSENS/A8 30.98000144958496 0x20 0x0
SA1_XTD2_ATT/TSENS/A9 33.5 0x20 0x0
SA1_XTD2_COLA/TSENS/T1 0.0 0x1020 0x0
SA1_XTD2_COLA/TSENS/T2 0.0 0x1020 0x0
SA1_XTD2_COLB/TSENS/T1 0.0 0x20 0x0
SA1_XTD2_COLB/TSENS/T2 0.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_10_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_10_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_1_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_1_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_2_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_2_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_3_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_3_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_4_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_4_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_5_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_5_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_6_T1 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_6_T2 85.0 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_7_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_7_T2 33.5 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_8_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_8_T2 33.5 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_9_T1 33.60000228881836 0x1020 0x0
SA1_XTD2_CRL/TSENS/LENS_9_T2 33.5 0x1020 0x0
SA1_XTD2_DPS1/TSENS/FLOW 2.0300002098083496 0x20 0x0
SA1_XTD2_DPS1/TSENS/RETURN1 33.5 0x20 0x0
SA1_XTD2_DPS1/TSENS/RETURN2 2.0200002193450928 0x20 0x0
SA1_XTD2_DPS3/TSENS/FLOW 33.5 0x20 0x0
SA1_XTD2_DPS3/TSENS/RETURN1 4.160000324249268 0x20 0x0
SA1_XTD2_DPS3/TSENS/RETURN2 4.420000076293945 0x20 0x0
SA1_XTD2_PBLM/TSENS/BLADE_LEFT 32.900001525878906 0x20 0x0
SA1_XTD2_PBLM/TSENS/BLADE_RIGHT 33.5 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_W 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_W 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_W 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_B4C 0.0 0x20 0x0
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_W 0.0 0x20 0x0
 

XTD9

============================================================

SA1_XTD9_PBLM/TSENS/BLADE_LEFT 24.31999969482422 0x20 0x0
SA1_XTD9_PBLM/TSENS/BLADE_RIGHT 24.810001373291016 0x20 0x0
SPB_XTD9_COLB/TSENS/T1 0.0 0x20 0x0
SPB_XTD9_COLB/TSENS/T2 0.0 0x1020 0x0
SPB_XTD9_DPS1/TSENS/FLOW 33.5 0x1020 0x0
SPB_XTD9_DPS1/TSENS/RETURN1 85.0 0x1020 0x0
SPB_XTD9_DPS1/TSENS/RETURN2 85.0 0x1020 0x0
SPB_XTD9_DPS2/TSENS/FLOW 85.0 0x1020 0x0
SPB_XTD9_DPS2/TSENS/RETURN1 85.0 0x1020 0x0
SPB_XTD9_DPS2/TSENS/RETURN2 85.0 0x1020 0x0
SPB_XTD9_PBLM/TSENS/BLADE_BOTTOM 23.05000114440918 0x20 0x0
SPB_XTD9_PBLM/TSENS/BLADE_LEFT 22.860000610351562 0x20 0x0
SPB_XTD9_PBLM/TSENS/BLADE_RIGHT 23.05000114440918 0x20 0x0
SPB_XTD9_PBLM/TSENS/BLADE_TOP 23.05000114440918 0x20 0x0
SPB_XTD9_SHUT/TSENS/T1 0.0 0x1020 0x0
SPB_XTD9_SHUT/TSENS/T2 0.0 0x1020 0x0
SPB_XTD9_SHUT/TSENS/T3 0.0 0x1020 0x0
SPB_XTD9_SHUT/TSENS/T4 0.0 0x1020 0x0
FXE_XTD9_COLB/TSENS/T1 0.0 0x20 0x0
FXE_XTD9_COLB/TSENS/T2 0.0 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_BOTTOM 22.780000686645508 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_LEFT 22.8700008392334 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_RIGHT 22.850000381469727 0x20 0x0
FXE_XTD9_PBLM/TSENS/BLADE_TOP 22.93000030517578 0x20 0x0
 

 Now the loop is accessible to Karabo as well with the project SA1_EPS

Entry   Schedule after 09:30 Meeting, posted by Tobias Haas on 04 Apr 2017, 11:21 

 Tunnel closed today. Might re-open around 14:00

Note that that we re-convene briefly at 17:00 today in MCR (Mock-up Control Room)

Vacuum Loop:

Status:

  • Large number of ion pumps not responding properly (2 in XTD2, 63 in XTD9). There is the suspicion that the parameters on some ion pump controllers might be set incorrectly, such as baud rate or the bus address. The generated error code indicates a bad address.
  • Test in the lab requires Ion pump controller and PCL. No setup currently readily available. Check in the tunnel required. Could take place between 1200 and 1300 in XTD2 with a ZZ. (Update: B. Racky thinks she will be done around 1400 and would prefer access after this time)
  • Preparations needed to include XGM 

EPS Loop:

Status:

  • Temperature sensors return null value. Suspected firmware bug has been fixed and EPS loop updated by TF
  • EPS to MPS interface requires testing. Should be done tomorrow

Motion Loop:

Status:

  • Fixes have been applied to the MC2 lib. Tested for TECHNOSOFT driver. Should now work also for PBLMs . Tests do be done starting Wednesday

Imagers

Status:

  • Camera driver for SR imager not working
  • Camera driver for FEL driver working for imager in XTD2 but not for XTD9

Tasks for today:

  • E. Eidam, V. Bondor, , J. Tolkiehn H. Sinn go through all ion pumps in the Silenzi list
  • E. Eidam, T. Freyermuth check pump controller settings in the tunnel
  • A. Koch and W. Ehsan work on Photonics Camera driver for FEL imager

 

Tasks for tomorrow:

  • M. Planas, T. Maltezopoulos, N. Jardon, J. Eidam test XGM vacuum integration in XTD2 (not XTD9)
  • N. Gerasimova, N. Gerasimova and 1 firmware expert test PBLMs in the tunnel
  • T. Freyermuth tests EPS -> MPS interface

 

Other topics

  • The two signals from MCP to EPS shall be called MCP-upstream and MCP-downstream

 

 

 

 

 

 

 

Entry   Schedule for PLC and Karabo 3 April after 09:30 Meeting, posted by Tobias Haas on 03 Apr 2017, 10:03 

Tunnels closed today and tomorrow

- AE updates Vacuum and motion loop in the morning

- V. Bondar, J. Eidam and H. Sinn test vacuum in the afternoon (emphasis on understanding interlock conditions)

- A. Koch tests XTD2 imagers in the afternoon

See also  https://in.xfel.eu/redmine/projects/sase1/agile_board

 

Problems solved on Friday last week:

- Arms 2 & 4 of SRA are now moving. Apparently spindles had mechanical resistance that resulted in error condition. After moving a few times, this appears to be gone

- One of the problematic ion pumps had the serial line disabled. However, other lines 

 

 

 

Entry   SASE1 EPS, posted by NEREA JARDON on 31 Mar 2017, 16:02 

Dear all,

EPS loop is running with the latest hardware updates. Today, when I was trying to update the loop, I have found that someone has powered off the EPS crate in XTD2 Rack 1.5. Please, if you have to do some work in any part of SASE 1, let us know about it.

Thank you!

Entry   Meeting Minutes 31 March 2017, posted by Frederike Wittmaack on 31 Mar 2017, 15:03 
http://tinyurl.com/lttzrtm
Entry   Update of component list after weekly meeting, posted by Tobias Haas on 31 Mar 2017, 15:00 170331-Tunnel-Components-Priority-list.xlsx
 
Entry   Web cameras in SASE1 tunnels, posted by Liubov Samoylova on 31 Mar 2017, 07:24 TmpPhCom_CR_2017-03-31-1.pptx
 
Entry   Update of component priority list after weekly meeting, posted by Tobias Haas on 24 Mar 2017, 15:24 170324-Tunnel-Components-Priority-list.xlsx
 
Entry   Schedule for PLC and Karabo Week 13, posted by Tobias Haas on 24 Mar 2017, 13:21 

 

Day Motion Loop Vacuum Loop EPS Loop SPB Tunnel Loop Karabo
Monday Loop up.  Loop up.  Loop up  Loop inactive Version update by CAS 12:00 - 18:00
Tuesday Loop up.  Loop up.  Loop up  Loop inactive Running and no change
Wednesday Loop up.  Loop up  Loop up  AE brings up loop Running and no change
Thursday Loop up Loop up  Loop up  AE brings up loop Running and no change
Friday Loop up  Loop up  Loop up  Loop up Running and no change

 

 
Entry   Motion up, posted by NEREA JARDON on 23 Mar 2017, 10:06 

Dear all,

The Motion loop is up and running again.

Thank you!

Entry   Pop-In II-45 Karabo test, posted by Andreas Koch on 22 Mar 2017, 16:39 
Trigger signal now available at imager. First Karabo tests of camera device with trigger successful. Detailed
tests continue.
Entry   Motion loop, posted by NEREA JARDON on 22 Mar 2017, 16:28 

Dear all,

tomorrow morning at 10h am, we will need the Motion PLC for roughly half hour to do some tests. During this time the PLC will be stop.

 

Entry   Motion Loop, posted by NEREA JARDON on 22 Mar 2017, 15:05 

FYI. The Motion loop is again up and running.

Entry   Loop status schedule for KW12, posted by Adriano Violante on 17 Mar 2017, 15:21 

Dear all,

find here the foreseen loop status for KW12. The schedule could change. All changes will be notified by entries in the logbook.

 

Day Motion Vacuum EPS Other 
Monday Loop is up.  Loop up.  Loop up  
Tuesday Loop is up.  Loop down. AE updates loop (maybe short ) Loop up  
Wednesday Loop down. AE updates loop Loop up  Loop up  
Thursday Loop up Loop up  Loop up  
Friday Loop up  Loop up  Loop up  

 

 

Entry   Updated Tunnel component status list, posted by Thomas Tschentscher on 17 Mar 2017, 12:11 170317-Tunnel-Components-Priority-list.xlsx
Updated list of tunnel high priority components after SASE1 Readiness mtg this morning. The list has also been sent for comments/clarifications to the involved Groups/People.
Entry   Loops up, posted by NEREA JARDON on 17 Mar 2017, 10:49 

Dear all, Vacuum and Motion loops are running again.

Thank you,

Entry   Fuses replacement, posted by NEREA JARDON on 16 Mar 2017, 16:54 

Dear all,

Tomorrow in the morning is needed to add some fuses in the PLCs crate, therefore Vacuum and Motion would be down for more or less one hour from 9am. I will notify you when the PLCs are available to work again.

Thank you,

Entry   Wiring status, posted by Torben Falk on 16 Mar 2017, 13:34 

Wiring status SASE 1:

Wiring progress:

  • Internal wiring of the XGM in XTD 9 is done.
  • Vacuum part wiring of the XGM in XTD 9 is done (ready for local Beckhoff test).
  • Gas Panel wiring of the XGM in XTD 9 is done.
  • Crate wiring (ADAM & Femto crate) of the XGM in XTD 9 is done.

Upcoming work XTD 2:

  • Serial connection from Beckhoff to TCP 350.
  • Change cold plug cables into halogenfree cables.

Upcoming work XTD 9:

  • INHIBIT connection Iseg HV crate.
  • Serial connection from MTCA to RVC 300.

Upcoming work XTD 10:

  • Vacuum part wiring of XGM.
  • Gas Panel wiring of XGM.
  • Internal wiring of XGM.
  • Installing ADAM & Femto crate.
  • Measure cable lengths for Imager and prepare cables.
Entry   Vacuum and Motion, posted by NEREA JARDON on 15 Mar 2017, 17:00 

Vacumm and Motion are running again after the hardware changes.

Entry   Vacuum and Motion, posted by NEREA JARDON on 15 Mar 2017, 11:31 

Today Denis has to make some changes in the Vacuum and Motion hardware loop, therefore they would be down some time.

At least, we would try to keep the Vacuum loop up again for 3pm, therefore Valerii and Raul could use it with Karaboo.

Entry   XTD2 Imagers, posted by Andreas Koch on 15 Mar 2017, 08:13 

XTD2, IMAG.2694.T9, Pop-In II-45: Acceptance test of motor control under Karabo, done. Camera device needs further explanations and testing.

Entry   Vacuum and Motion down, posted by NEREA JARDON on 14 Mar 2017, 13:55 

Dear all,

Finally today the Vacuum and Motion will still running the hole day and I would have to stop them tomorrow morning. Before doing this operation, I will post an entry in the ELOG.

Entry   Vacuum and Motion down, posted by NEREA JARDON on 13 Mar 2017, 15:47 

Tomorrow, 14th of March, Vacuum and Motion loop will be down at least during morning due to technical reasons .

I will notify you when the works are finished.

Entry   Tunnel Commissioning Schedule for Week 11, posted by Tobias Haas on 10 Mar 2017, 16:56 
Day Motion Vacuum EPS Other 
Monday Loop is up. AE continues tests on MC2 lib Loop up. AE investigates problem with ion pump controller Loop inactive  
Tuesday Loop is up. AE continues tests on MC2 lib Loop down. AE implements fix for ion pump controller Loop inactive  
Wednesday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Thursday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Friday Loop up for testing Loop up for testing Loop up for testing  

 

In addition it should be tried to have a so called "Happy Hour" every day from 0800 - 1000. During this time loops should be up if possible. Meaning that in the evening before leaving, developers bring loops back up.

Entry   CRL, posted by Lewis Batchelor on 10 Mar 2017, 14:56 

The XTD2 CRL is now aligned and cabled.

Motor cabling is complete and ready for local testing. Encoder and PT100 cabling at rack to be completed by the middle of week 11.

Entry   Update of Tunnel Component Priority List after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 12:53 170310-Tunnel-Components-Priority-list.xlsx

Note that due to a bug in the elog the name appeared wrongly in my previous message. In general: Avoid underscores in the file names! 

Entry   Link to the redmin list of Tasks., posted by Alessandro Silenzi on 10 Mar 2017, 11:34 

https://in.xfel.eu/redmine/projects/control-support/issues

Short Instructions:

- Add your task

- Select your work package

- Do NOT set the assignee

- Do NOT set the priority

 

Entry   Instrument Component Priority List update after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 11:18 170310_Instrument_Components-Priority-list.xlsx
 
Entry   Update of Tunnel Component Priority List after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 11:15 Components-Priority-list.xlsx
 
Entry   Karabo Deployment Documentation link, posted by Alessandro Silenzi on 08 Mar 2017, 18:26 

Url to the readthedocs documentation:

https://goo.gl/vsz9hu

Entry   Karabo testing, posted by Andreas Koch on 08 Mar 2017, 16:18 

Here the link to the detailed list of issues: https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d

Entry   Karabo testing, posted by Andreas Koch on 08 Mar 2017, 16:08 

End switch testing: the in-position end switch stopped devices working, also stopped gateway connection. Stroke of motor is not correct, parameter list to be checked. More details in "Improvements / bug list".

Entry   Interlock tests DPS, posted by NEREA JARDON on 08 Mar 2017, 13:11 

The interlock test in XTD9-DPS has been done. The Vacuum PLC is again available for Karaboo.

Entry   Karabo testing on Wednesday, posted by Andreas Koch on 07 Mar 2017, 11:09 

As discussed with Wajid, I am availalbe tomorrow Wednesday the whole day to continue testing Karabo, motion loop. Wajid checked with Narea. I understand that there may be interruptions and that I have not first priority. Thanks, Andreas

Entry   XTD9-DPS, posted by NEREA JARDON on 07 Mar 2017, 10:21 

Dear all,

Tomorrow morning, 08th of March at 09.30h. I will be in the tunnel doing interlock tests in the DPS-XTD9 with Raúl.

Therefore I will need the connection of the TCP_Client in the Vacuum loop (just to let know Karaboo people).

I will post again when the PLC is available for Karaboo.

Thank you!

Entry   Pop-In II-45 Karabo test, posted by Andreas Koch on 06 Mar 2017, 18:14 

6.3.2017, Karabo tests in XTD2 with Wajid, Andreas

1. Karabo all devices, all scenes working, with restrictions.

2. Power supply, motor, LED working.

3. Scenes tested: Motor scene and camera scene need additional parameters. AK will edit a list of suggestions, improvements and bugs.

4. Bugs, observations, details in improvement list.:

- Homing not working, tried also old parameter set from prototype crate.

- Encoder position not correct, dragging behind.

- Parameter for braking switch missing “ALowSpeed”.

Entry   Minutes of weekly SASE1 Readiness Meeting, posted by Tobias Haas on 03 Mar 2017, 16:46 

 Here is the link to the minutes Minutes

Entry   Update of Component Priority list after weekly meeting, posted by Tobias Haas on 03 Mar 2017, 16:40 170303_Components-Priority-list.xlsx
 
Entry   Vacuum PLC, posted by NEREA JARDON on 02 Mar 2017, 11:55 

Dear all,

The Vacuum PLC is up and running and Karaboo guys have already started to work with it.

Thank you and regards

Entry   PLC work, posted by NEREA JARDON on 02 Mar 2017, 09:52 

Dear all,

Right now the Motion PLC is up and running. We are still working in the Vacuum one, today by midday should be also working.

Entry   Reminder: Stable operation and development periods, posted by Tobias Haas on 28 Feb 2017, 11:38 

One word of clarification:

The discussion last Friday left some people uncertain over how to define stable operation and development periods. Hence I had a discussion with Nerea and Alessandro and agreed on the following:

PLC development: Tuesday - Thursday

Stable operation with Karabo: Friday - Monday

Handover period is Thursday afternoon between AE and CAS 

 

Entry   Update of component list after weekly meeting, posted by Tobias Haas on 24 Feb 2017, 16:33 240217_Components-XTD2-9.xlsx
 
Entry   Meeting Minutes 24 Feb 2017, posted by Frederike Wittmaack on 24 Feb 2017, 15:22 
http://tinyurl.com/hhu998t
Entry   work on FXE distribution mirror chamber, posted by Martin Dommach on 24 Feb 2017, 15:15 

Dear all,

on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.

The mirror chamber (VS10130) will be vented and opened. This will affect:

V10270G and V10280G: they will be closed and disconnected

P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.

The work will take at least until Friday, March 3rd.

 

Entry   work on FXE distribution mirror chamber, posted by Martin Dommach on 24 Feb 2017, 15:14 

Dear all,

on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.

The mirror chamber (VS10130) will be vented and opened. This will affect:

V10270G and V10280G: they will be closed and disconnected

P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.

The work will take at least until Friday, March 3rd.

 

Entry   Updated Component status list, posted by Thomas Tschentscher on 17 Feb 2017, 12:40 170217_Components-XTD2-9.xlsx
See the updated component status list for XTD2 and XTD9 tunnels. As discussed at the SASE1 readiness mtg this morning. Yellow fields indicate new/changed entries. Please let me/THaas know if there are errors or further changes to be reported. I also entered the SASE1 instruments now a 'High Priority' items. However, we may need to adapt the table for These entries as the work flow seems different.
Entry   Motion loop feedback, posted by Alessandro Silenzi on 17 Feb 2017, 09:56 20170217Motion.txt

Quick feedback during the meeting:

- 63 Devices

- 29 Motors

Errors only in 

- SPB_XTD9_IMGPI

- FXE_XTD9_IMGPI

Entry   Motion loop status, posted by Alessandro Silenzi on 15 Feb 2017, 20:20 20170215MotionLoop.txt

The motion loop is as of 18:40 online.

the current status of the devices as seen by the Karabo is shown in the attachment:

In summary 63 devices (29 Motors):

18 in error

- 14 in error 0x8004 (Terminal unavailable)

- 4 in error 0x8003 (Terminal unavailable)

This is the list of motor that are behaving according to karabo

SA1_XTD2_MIRR-2/MOTOR/HMRZ Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_RIGHT Success State.OFF
SA1_XTD2_IMGFEL/MOTOR/SCREEN Success State.OFF
SA1_XTD2_FLT/MOTOR/TARGET Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRZ Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_LEFT Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMTX Success State.OFF
SA1_XTD2_IMGSR/MOTOR/TARGET_X Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMRX Success State.OFF
SA1_XTD2_IMGSR/MOTOR/IRIS Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRY Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_BOTTOM Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMRY Success State.OFF
SA1_XTD2_IMGSR/MOTOR/FOCUS Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMTX Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMTY Success State.OFF
SA1_XTD9_IMGPII45/MOTOR/SCREEN Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRX Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_TOP Success State.OFF
SA1_XTD2_IMGPII45/MOTOR/SCREEN Success State.OFF
SA1_XTD2_IMGFEL/MOTOR/FILTER Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMTY Success State.OFF
 

Entry   Current Vacuum Status, posted by Alessandro Silenzi on 15 Feb 2017, 20:10 20170215Vacuum.txt

The PLC is still not completely error free.

It is considerably better performing than the last days:

the current average pressure as measured by the Ion Pumps is 4.21e-09 mBar

there are Currently 96 ion pumps in the Tunnels as seen by the PLC:

3 cannot properly communicate with the PLC

SA1_XTD9_VAC/IPUMP/P10510I

SA1_XTD9_VAC/IPUMP/P11130I

SA1_XTD9_VAC/IPUMP/P12120I

3 have an ambiguous control name:

SA1_XTD2_VAC
SA1_XTD9_VAC2
SA1_XTD9_VAC0
 

And 4 have no channel assigned in the Karabo inteface (CAS to solve this)

SA1_XTD2_VAC/IPUMP/P10340I
SA1_XTD2_VAC/IPUMP/P10350I
SA1_XTD9_VAC/IPUMP/P10370I
SA1_XTD2_VAC/IPUMP/P10360I

The remaining 86 replied and:

Average pressure is  4.210e-09 mBar

Maximum pressure is  2.60-08 mBar

Minimum pressure is  8.90e-10 mBar

Entry   Beckhoff loop status, posted by Alessandro Silenzi on 14 Feb 2017, 09:59 

2017.02.13 19:30 Status:

- Self-Description back in shape.

- Bad SelfDescription reproduced in BeckhoffSim (Karabo implemented PLC communication) and solved in BeckhoffCom (Karabo "PLC Client").

- The build status of the Firmware is not ok. roughly 90% of the PLC soft devices are in error. It is a fault in the automatic Firmware build procedure.

Nerea and Jan will work on this until it is fixed.

 

Entry   Current Status, posted by Alessandro Silenzi on 12 Feb 2017, 14:02 Motors_Parameters.xlsx

 Vacuum loop:

- Interface between PLC and Karabo is not functioning.

The fault currently resides in the PLC behaviour, the self-description sent out is badly formatted (due to a buffer overrun)

The misbehaviour is confirmed, the PLC TCP Client from AE is also ailed by the same problem.

Motion Loop:

- As of Friday, the motor parameters were not completely sent to AE. In attachment the data collected by N. Jardon (AE). Input needed for PSLIT motors.

 

 

 

Entry   Updated Components List, posted by Tobias Haas on 10 Feb 2017, 16:34 Components-XTD2-9.xlsx
 
Entry   Meeting Minutes 10 Feb 2017, posted by Frederike Wittmaack on 10 Feb 2017, 15:15 
Follow the link below to view the minutes and relating material on Alfresco. http://tinyurl.com/zc3nvn9
Entry   Updated Components List, posted by Tobias Haas on 10 Feb 2017, 15:07 Componets-XTD2-9-new.xlsx

 Added Diagnostic Screen for SPB and changed PRIO for DPS - XGM - DPS in XTD9 to high as discussed during the S1R meeting

Entry   Progress Beam Transport, posted by Tobias Haas on 10 Feb 2017, 08:31 

Post on behalf of Harald Sinn

Fortschritte, die ich letzte Woche beobachten konnte, sind: 

1.) Die Spiegelkammern wurden weiter lokal getestet. Benoit hat gestern abend den 
letzten Encoder am XTD9 vercrimmt. Wahrscheinlich muss der dann noch mal getestet werden, 
aber dann sollte das abgeschlossen sein. 
2.) Gestern haben wir zusammen mit Jan Tolkiehn den SRA und Filterkammer getetstet. 
SRA ist OK (incl. der Encoder), die Filterkammer auch, aber Wolfgang meinte, er müsste die 
LImit.switches noch mal etwas nachstellen (dafür sollte dann aber Karabo funktionieren, s.u.)
3.) Die PBLMs in XTD2 und die letzten beiden in XTD9 sich verkabelt und könnten von uns aus lokal 
getestet werden. Jan meinte allerdings, dass an den Elmo/technosoft (PBLM hat Elmo) Treibern noch etwas Arbeit
nötig ist, um zuverlässig Tests zu machen (MCI Library)
4.) Andreas Block hat mit Maik Neumann ausgemacht, dass sie sich Montag treffen und alle fehlenden Wasserverbindungen in 
SASE1 durchgehen und am besten sofort machen,. 
5.) Makus Schlösser hat bestätigt, dass nächste Woche (wohl leider nur) ein Team für uns arbeiten kann. 
Das wird zunächst aber in SASE3 hinten anfangen, weil wir da schnon einen Arbeitsstau in der Vakuumgruppe 
aufgebaut haben. Die relativ wenigen Komponenten in SASE1 werden natürlich auch fertig, aber Markus meinte, er würde vorhar 
lieber noch einige Daten konsolidieren. 
 
Zum lokalen testen: Das ist schon sehr wichtig, allerdings sollte es noch nicht mit dem technical commissioing 
verwechselt werden. Beim lokalen Testen wird nur festgestellt, ob sich der Motor in die richtige Richtung dreht 
und ob am Terminal die richtige LED leuchtet, wenn man den entsprechenden Endschalter drückt 
(Jan weiss dann, welche LED leuchten muss). Man sollte aber z.B. nicht auf den Endschalter fahren, weil in diesem 
Modus kein automatischer Stopp stattfindet, sondern man muss manuell eine Stopp Taste drücken. 
Auch werden nicht Motorgeschwindigkeit etc. optimiert oder gespeichert. 
Deswegen ist es wichtig, dass wir möglichst schnell Beckhoff+Karabo zum Laufen bringen, weil diese Tests 
essentiell sind und von den Komponentenverantwortlichen gemacht werden müssen. 
Falls die MCI Library tatsächlich ein Problem darstellt, was etwas dauert, würde ich vorschagen, die 
Beckhoff Motion Loop jetzt schon in Betrieb zu nehmen, mit den Motoren, die wir getestet haben. 
 
Grüße 
 
Harald 
 
 
Entry   Status of Differential Pumping, posted by Tobias Haas on 09 Feb 2017, 17:16 

Post on behalf of R. Villanueva

please find attached the updated status of the Differential Pumping
Modules in SASE 1. Just a few comments.

1. As you can imagine, no progress after KW4 in XTD2: system is ready to
deploy Karabo.
2. In XTD9, we have been pushing forward to finish the local test with AE.
Right now, everything has passed the local test except 3 vacuum gauges
that will be rechecked after the meeting. The main reasons for the little
progress (84%----->87%) are:

  a) more problems than expected with the cabling.
  b) a faulty Beckhoff Terminal.
  c) prioritization of  manpower (AE and VG) in other devices in the
tunnel.
  d)....the usual "sigmoidal" behavior of this kind of process.... ;)

3. In any case we aim to leave the system ready tomorrow so next week the
interlock code can be deployed safely.


Have a nice evening,

R.

Entry   Update of installation list for tomorrow's S1R Meeting, posted by Tobias Haas on 09 Feb 2017, 13:57 Componets-XTD2-9.xlsx

 Please check if correct. I mark all newly done things in yellow!

Entry   Meeting Minutes 03 Feb 2017, posted by Frederike Wittmaack on 03 Feb 2017, 14:22 
http://tinyurl.com/hwu4esq
Entry   Update WP74 cabling status (w5), posted by Jan Grünert on 03 Feb 2017, 08:48 

Information posted on behalf of Torben Falk (WP74 cabling)

Wir haben nun alle Kabel für den XGM in XTD2 am Beckhoff angeschlossen.

Alle Leitungen sind bereit zum einstecken in die jeweiligen Komponenten.
Es sind alle "valve connection boxes" angeschlossen, bis auf eine. Da besteht noch klärungsbedarf mit Florian. (ist aber auch schon am Beckhoff angeschlossen, nur device-seitig noch nicht)
 
Dementsprechend wäre der lokale Beckhoff Test möglich.
 
Ich habe mit Tobias Freyermuth geredet und der hat für den lokalen Beckhoff Test leider erst mitte / ende nächster Woche zeit..
 
Außerdem haben wir in XTD9 Kabel für den HiREX gewechselt. Da waren ein paar Kabel zu kurz. Die haben wir nun mit passenden ersetzt.

Andreas hat sich für die Timing verkabelung um die nötigen Kabel / Material gekümmert, die gebrauchten Längen habe ich ausgemessen und ihm zukommen lassen. Das Material soll Anfang nächster Woche da sein.
 
Entry   WP74 components in XTD2 - electrical connections, posted by Bernard Baranasic on 02 Feb 2017, 18:29 
Status of WP74 components testing and wiring this week:
 
On Monday we tested SR Imager and K-Mono:
- issue with motor connect pinouts was discovered and I wanted to correct pinout today, but K-Mono and SR imager motor connectors are Lemo with soldering pins, which make pin changing more difficult than crimp version...
- this is still not done (we can exchange all connectors to crimp version or temporary change pins on crate side).
 
This week done:
- connected SR imager EPS switch (on the imager - not yet in the crate)
- On XGM Gas Panel is installed new HUBA gauge, and I connected it to the crate (now everything from Gas Panel is connected to Beckhoff terminals in WP73_VAC crate - Rack 1.3).
- FEL imager - EPS switch is connected properly, but Digital Input terminal in WP73 EPS crate - Rack 1.5 is defect (doesn't work at all).
- I placed cable for EPS switches of MCP detector, but not placed in the Rack (Rack needs to be opened - Roxtec feedthrough is closed)
 
To be done:
- K-Mono - switch pins 1 and 2 on Motor connectors (Y-1, Y2 and X).
- SR imager - switch pins 1 and 2, and switch pins 7 and 8 on all Motor connectors.
- SR imager - EPS switch connect from WP74 crate to WP73_EPS crate (one cable inside crate).
- XGM vacuum to HV crate interlock (inhibit) is still not connected (I am waiting for Beckhoff terminal, but this connection was not tested yet).
- MCP detector - EPS switch cable needs to be laid inside Rack 1.7 (Rack needs to be opened - Roxtec feedthrough is closed).

- MCP detector - vacuum to HV crate interlock (inhibit) needs to be connected - Beckhoff crate is prepared - missing cable from MPOD to Beckhoff terminals.

Entry   XGM resistors - progress w5, posted by Jan Grünert on 02 Feb 2017, 17:54 XGM-resistors.pptx

Presentation for SASE1readiness-Meeting

on XGM resistor issue progress (w5) and plan (w6)

Entry   Status of component list as of 17:45, posted by Tobias Haas on 02 Feb 2017, 17:46 Componets-XTD2-9.xlsx
 
Entry   Installation List Update, posted by Tobias Haas on 02 Feb 2017, 16:56 Components-XTD2-9.xlsx

 Updates as of 2 Feb 16:30

Entry   SPB/SFX updates to component table, posted by Richard Bean on 02 Feb 2017, 14:29 Components-XTD2-9.xlsx

Table updated with status of SPB/SFX devices at end of XTD9 in preparation for SASE1 readiness meeting on 03.02.17

Entry   XGM resistor issue - analysis progress, posted by Jan Grünert on 01 Feb 2017, 17:42 

This is the current (w5) progress at DESY concerning the analysis of the serious XGM resistor issue (summary; a detailed report by DESY is available):

  • The new “pulser test” was verified at an operational XGMD at FLASH. The test method is (unfortuately) OK. This means that the test results with issues from last week on all our XGMs are REAL.
  • 25% of all resistors in XBPMs affected, 0% of resistors in HAMPs affected, no capacitors affected.
  • Since no HAMP resistors are damaged, damage by environmental conditions (venting, humidity etc.) can be excluded. The main differences to the affected resistors are the HV-conditioning and the experienced HV-values of the resistors (typically XBPM resisotors are tested up to 12kV, HAMP resistors each see much lower voltages).
  • An XGMD chamber at FLASH was tested-to-destruction-of-resistor by applying a large differential voltage (>3kV) between neighboring electrodes, e.g. on mesh_e and FC_e. These resistors (Caddock MS220) have a nominal voltage breakthrough rating of ~500V but never had issues. They are used in all our XGMs.
  • New, other resistors (Ohmite MOX-1N-13) with higher voltage breakthrough rating of 10kV were procured and arrived tuesday
  • The new resistors were built into the tested-to-destruction XGMD at FLASH, unit is now pumping, will be retested with applying pulsed HV (on both Caddoc and Ohmite resistors) when at suitable pressure.

Further plan (w5end + w6) concerning the XGM resistor issue:

  • If the new resistors survive the test, then next monday the XGM01 at HERA-S will be opened, the tested-defect resistors will be checked and replaced with the new resistors.
  • If all tests on XGM01 are then ok including an acceptable RGA, all other XGMs (XBPM chambers) will be opened and resistors exchanged. Even ok-tested resitors would be exchanged to avoid future unexpected failures. HAMP chamber resistors will not be exchanged (large number >20 of resistors, no failures).
  • If the RGA is not acceptable, the resistor Ohmite MOX-1N-16 is another alternative, but has increased delivery time.
Entry   Status of several XTD2 wiring tasks - on behalf of Bernard Baranasic, posted by Jan Grünert on 01 Feb 2017, 17:26 
Dear all,

 

today I connected XGM Gas Supply to Beckhoff terminals in WP73 Vacuum crate in Rack 1.3.
On Gas Panel, HUBA gauge is still not replaced, so it is not connected, I talked to Florian yesterday and give him an idea how we can connect this gauge and other signals for Gebäudeleittechnik (trough wago terminals).
Next step for this crate should be connection to all pump controllers and other vacuum equipment, after this crate should be connected to the tunnel vacuum loop. I assume that Torben and Marc can do this together with AE and Vacuum group, so I didn't take any actions...

 

Additionally in this crate we should connect Inhibit signal from HV iseg crate, for this we need to add:
Proposal from NC:
"I did not test it, to 'create' a TTL we can use either
es9505+es2624 or es9505+es2124
the only difference is that the ES2124 is short-circuit proof, the ES2624  is not, that means that in this case a Flink fuse ~0.3A-0.5A should be inserted."
- WP74 don't have these terminal here and if we order now it will take some time (I am not sure what to do because we don't have proven connection).

 

In Rack 1.7 I connected Inhibit connection to WP73 vacuum crate (terminals EL9505 & EL2624), but cable from MPOD crate to Beckhoff crate is still not there. Torben said that he has connectors so I believe he can connect according to electrical drawings (these pages are added to XTD2 MCP drawings on Alfresco)

 

In Rack 1.5 I tested FEL imager EPS switch and find out that Beckhoff terminal DI (ES1008) is not working (24V is on input, but there is no light on LED, all channels are the same).
EPS switch is removed From FEL imager, and I will reconnect it to Normal Open connection.

 

Best Regards,

___________________________________________

Bernard Baranasic

Entry   Component table update, posted by Thomas Tschentscher on 27 Jan 2017, 10:22 Components-XTD2-9.xlsx
 
Entry   Software Report, posted by Tobias Haas on 27 Jan 2017, 09:25 

Post on behalf of S. Brockhauser

 Since I am in Grenoble and visiting ESRF, I will not be able to give you the report in person. Instead Alessandro can give you a Summary.

In fact:
- we did collect the full list of the Karabo names for all the equipments involved
- we have started our sprint and we are on track
As next things:
- we are collecting all the required Karabo(!) default parameters
- we plan to finish the sprint as planned and presented last time.
Until now we have not experienced and obstacle.

Best wishes
Sandor

Entry   XGM at XTD2 / issue with in-vacuum-resistor, posted by Tobias Haas on 26 Jan 2017, 17:02 

Post on behalf of Jan Grünert:

 

during HV-tests on the installed XGMs, our DESY colleagues from Kai Tiedtkes team have found an issue with one of the electrodes / resistors inside one XGM vacuum chamber at XTD2.

 

Roughly, we know the following:

1)      If not repaired, we would lose at least the capability of monitoring shot-to-shot horizontal beam position at this XGM location. This is a lower-priority info.

2)      However, it’s not yet fully tested if other functionalities could be affected. In case the absolute calibrated intensity info is affected, then clearly we would have to repair.

3)      Since the cause of the resistor-irregularity is not understood, there is a risk to damage the other (operational) remaining resistors in the other chambers of the same XGM.

 

It is not yet fully clear 

a)      what is the cause for the irregular behavior (it concerns a resistor inside vacuum which dramatically changed its resistance, which apparently possibly might happen even during a correct dry-nitrogen venting),

b)      the entire consequences for operation with this XGM

c)       the effort/details of a potential repair (could include up to removing one of the four chambers off the girder out of the tunnel into a lab, certainly needs re-survey)

d)      if another XGM chamber is affected (so far tested 2 of 6).

 

The DESY colleagues are running various tests with us on the XGMs, also extending to all the other XGMs, to get answers to the above questions in order to allow a decision on “repair/not repair”. 

 

Since this concerns the internals of the high-prio XGM in XTD2, we could ask Kai Tiedtke to give us his brief 10min report and recommendation in the tomorrow SASE1Readiness Meeting. Should we request his presence / will you add him to the agenda ?

 

Best regards,

Jan

________________________________________

Dr. Jan Grünert

Group Leader X-ray Photon Diagnostics (WP74)

European XFEL GmbH

Holzkoppel 

Entry   Modification of the vacuum PLC loop, posted by Tobias Freyermuth on 26 Jan 2017, 13:10 

The PLC program was modified and downloaded to the PLC, due to allow work on the XGM crate in rack 1.3.

The PLC vacuum loop includes now all vacuum crates in the racks from rack 1.1 to rack 1.7 except rack 1.3 (XGM)

Entry   More items in the master equipment list, posted by Alessandro Silenzi on 24 Jan 2017, 18:36 

Master Component list is being updated.

https://docs.xfel.eu/share/proxy/alfresco/api/node/content/workspace/SpacesStore/1c6c10cd-d741-410d-bd05-bb00944514dc/MasterEquipmentList.xlsx?a=true

Best regards

Alessandro

Entry   Karabo Names in Vacuum component list, posted by Tobias Haas on 24 Jan 2017, 08:23 

 Post on behalf of Alessandro Silenzi:

 

please find below the link to the first version of the master component list and the link to the direct download:
 
 
 
Please give your comments directly to me to avoid confusion.
 
The next steps after collecting your input, will be to implement a test in the Firmware project generation that will test the deviceIds against this list.
 
Best regards
 
Alessandro Silenzi
 
Entry   Karabo Names in Vacuum component list, posted by Tobias Haas on 24 Jan 2017, 08:21 

Post on behalf of Harald Sinn:

 for the non-vacuum part of WP73 we have the following situation: 

Last Friday Alessandro and myself had a meeting and agreed to use the names given in the document
 
 
(CAS inbox for software requirement documents)
 
The only change will be in the naming of the power supplies for the hard X-ray mono 
(which will be changes to analog input /output)
 
You can use the names is this document therefore already. However, Alessandro will 
create Excel tables out of it, which will be then used in the future for reference. 
Also the extension to SASE3/2 will be done in this Excel document. 
 
Best regards 
 
Harald
 
Entry   STATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control, posted by Tobias Haas on 24 Jan 2017, 08:17 

 Post on behalf of Raul Villanueva:

As we just finished the exhaustive testing and final adjustments of local
test and the interlock program for each of the turbopumps at each
Differential Pumping Sections in XTD2 Tunnel, we are happy to announce
that the system has been released and is up and running smoothly and under
control.  That means that the isolation gate valves in front of each
turbopump is open and therefore the latter is pumping already the beamline
as expected during the upcoming operation phase of the facility. That also
means that WP74, after having already received the wiring documentation
from the Vacuum Group can proceed with the same protocol to keep the whole
gas section in XTD2 in a consistent fail-safe status.

With this positive news, we wish you to have a nice evening,

Regards,

Raúl, Tobias and Nerea,

 

Entry   VCTF-list updated, posted by Sabine Cunis on 09 Jan 2017, 10:47 

The VCTF-components-list  has been updated. Labels on components, as far as visible, are in accordance with names in list.

... please, check for consistency, when naming and labeling XGM components!

Entry   Meeting Minutes 23 Dec 2016, posted by Frederike Wittmaack on 03 Jan 2017, 08:46 
Please follow the link to view the minutes: http://tinyurl.com/h3qspzz
Entry   XGM Safe State Definition, posted by Frederike Wittmaack on 19 Dec 2016, 09:44 
as defined by Jan Grünert: available on Alfresco: XGM-safe-state.docx and available at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03 - Components\XGM-safe-state.docx
Entry   Meeting Minutes 16 Dec 2016, posted by Frederike Wittmaack on 19 Dec 2016, 09:32 
http://tinyurl.com/zzzy7sd
Entry   Meeting Minutes 09 Dec 2016, posted by Frederike Wittmaack on 09 Dec 2016, 15:31 
http://tinyurl.com/gqykf7z
Entry   Meeting Minutes 02 Dec 2016, posted by Frederike Wittmaack on 07 Dec 2016, 17:09 
http://tinyurl.com/hzq7ats
Entry   Remote access to control network form , posted by Frederike Wittmaack on 02 Dec 2016, 11:47 
http://tinyurl.com/jskzj2h
Entry   Meeting Minutes 25 Nov 2016, posted by Frederike Wittmaack on 02 Dec 2016, 11:46 
http://tinyurl.com/jydty26
Entry   new components list , posted by Sabine Cunis on 02 Dec 2016, 11:43 

please find the new (extended) components list under the old link given in the minutes http://tinyurl.com/zn7otsa ,

and check whether all components are included and charakterized by the correct data.

 

Entry   Meeting Minutes 17 Nov 2016, posted by Frederike Wittmaack on 24 Nov 2016, 11:38 
http://tinyurl.com/hxaxdm9
Entry   Meeting Minutes 11 Nov 2016, posted by Frederike Wittmaack on 14 Nov 2016, 14:10 
http://tinyurl.com/juhjcbf
Entry   Mandate for the Extension of the Vacuum Controls Commissioning Task Force, posted by Tobias Haas on 11 Nov 2016, 15:43 

The Vacuum Controls Commissioning Task Force initially helped to get the vacuum components extending from the gate valve at 2678 m to the gate valve at 2730 m in XTD2. This comprised the valves and pumps and the associated vacuum interlock logic. The necessary components were all installed and locally tested. As the next step the PLC firmware for the control of these devices was generated including the interlock logic. Finally the system was connected to version 1.47 of Karabo, which was able to monitor and control all components. A live demonstration is currently still outstanding.

 

As the next step the vacuum section considered should be extended upstream to include all components up to the gate valve at 2630m. In addition to vacuum components this should include the installed photon beam line components. The goal is to include all these systems into one continuous vacuum, commission all systems locally, generate the PLC firmware, implement the required vacuum interlocks, monitor the state of the system remotely via the PLC command line interface and eventually connect to Karabo and monitor and control the system via Karabo remotely using the consolidated version 2.0. While this commissioning effort is going on, development should occur on three days during the week (Mo-Wed) while the system should be operated continuously during the remaining time, thus also testing long-term stability. This should be achieved by the end of 2016.

Entry   Update of Component list, posted by Tobias Haas on 09 Nov 2016, 15:36 elog.tiff

I have included the status columns provided by Alessandro and Sandor in the component list. Please find it in the usual location here: http://tinyurl.com/zn7otsa

Entry   Karabo Installation back to normal, posted by Alessandro Silenzi on 07 Nov 2016, 19:15 OK.pnginterlocked.pngbackToNormal.pngafteron.png

 Karabo to PLC communication has been tested successfully in the SA1 Vacuum installation.

in attachment:

OK.png -> Initial Status, all OK

interlocked.png -> pump P10300I is turned off -> Setpoint -> off -> Valve automatically close and set "Interlock OK" to false

afteron.png ->  pump P10300I is turned on again but-> Setpoint -> off -> Valve automatically close and set "Interlock OK" to false

backToNormal.png -> Like initial status but valves stay closed

 
Entry   BeckhoffDevices back to responsive, posted by Alessandro Silenzi on 04 Nov 2016, 18:08 

 I reproduced the behaviour of the PLC on beckhoffSim. This reproduces the same behaviour seen in the tunnel devices (devices hang).

Implemented the fix and verified the correct behaviour with beckhoffSim.

Fixes will be verified next Monday with the tunnel system.

Have a nice weekend

Alessandro

 

ps: For future reference:

beckhoffSim  tags/1.1.0-1.4  (implements the recent plc behaviour (framework tag N/A Could not find tobias))

beckhoffDevices tags/2.0.1-1.4 hangs

beckhoffDevices tags/2.0.2-1.4 does not

 
Entry   Minutes - Meeting November 4, 2016, posted by Frederike Wittmaack on 04 Nov 2016, 14:22 
http://tinyurl.com/jbog6tz
Entry   Minutes of last weeks meeting (Oct 28, 2016), posted by Frederike Wittmaack on 04 Nov 2016, 08:03 
http://tinyurl.com/jy5rsbx
Entry   overview of required racks, posted by Sabine Cunis on 03 Nov 2016, 17:00 VCCT_Rack_1p06_b.jpgVCCT_Rack_1p07_b.jpg

just for reference ... here are pictures and schematics of the racks which are involved in the current commissioning.

Entry   Current PLC-Karabo Conflict, posted by Alessandro Silenzi on 03 Nov 2016, 12:58 

Tobias Freyermuth and me worked on the system and as of last night, we found two new issues between Karabo and the PLC interlock:
 - one is a Karabo issue from the Interlock PLC interaction, the Karabo device waits for a PLC response that does not come when the PLC is interlocked (i.e. Karabo wants to open a valve but the PLC correctly refuses and ignores the command)


 - one is a PLC issue, the interlock is not triggered in all cases after testing (e.g. a ion pump out of set point does not closes a gate valve closure as specified).

The first one was reproduced with the BeckhoffSim simulation. It can therefore be fixed by CAS without dependencies from AE (except for the next integration test).

Entry   Minutes of last week's meeting, posted by Tobias Haas on 26 Oct 2016, 14:26 

 http://tinyurl.com/gvvv392

Entry   Start of Logbook, posted by Tobias Haas on 26 Oct 2016, 13:55 

Dear Colleagues,

in the future we would like to use this mechanism to record and exchange information that concerns the work done within the context of this task force. Please use this generously. We shall also put a link to the minutes after each weekly meeting.

 

regards,

 

Tobias 