Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 553     Entry time: 27 Aug 2018, 09:57
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SASE3 general

  • Deployment of the new interlock definitions will be done in the next 2 days. Final test foreseen for Thursday.

SPB

  • Users collecting data. Problems of clogging of the sample injection, this could result in empty image files. Wil be checked by the users..

AE

  • FXE requeste a 2nd digitizer channel. Will be finalized with CAS.
  • SQS digitizers issies reported on Friday solved.

DET

  • FXE - LPD module is showing flickering. To be investigated after the users run.
  • AGIPD pipeline issues (crashing). Are probably caused by misconfiguration of the detector by the users. 

 CAS

  • XTD6 technical commissioning will be focussed of the MID CRL this week. No feedback from LBatchelor and MID received relative to the bellows. If no feedback is received, the bellows will be aligned in the central position and the motors disconnected.
  • Log for GATT almost ready (related to the new interlock definitions for the SASe3 operation)