Message ID: 274     Entry time: 31 May 2017, 11:05
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 meeting 

 General

  • Photon tunnels will be searched starting at 1500 today and then closed. Machine will go back into regular operation this afternoon
  • XTD9 stays open until further notice
  • Flooding damaged several connectors in SPB Optics and FXE Instrument. 
  • Jovo will replace connectors that show optical damage and test all cables that were in the water. A list is being compiled by Adriano. Meeting held for this purpose today at 1330 in XTOB.

XTDs

  • Work continues on stability problem of SR imager 
  • 2 updates were done on motion loop since a bug was still found for the MC2 lib after the first update
  • 1 update was done for vacuum loop but another one needs to be done since there is still an issue with the NAGIOS system
  • Test with the PBLM is still outstanding and will be done today
  • The systems should be in a fully functional state again this afternoon!

FXE

  • Vacuum gate valves can be controlled now after some work by J. Tolkiehn. Ion pumps are not controlled yet
  • Next update of firmware should resolve the problem with ion pumps 
  • Cables for loops 4&5 were in the water and hence work on these components has to wait

SPB

  • Full E2E test was done for the PSLIT.
  • Further tests will have to wait for fixes to cables

PLC

  • AE works on AGIPD today and will go back to instruments tomorrow
  • An update to the EPS needs to be done at some point in the near future to implement the end switches of the screens
  • When cables are fixed and tested, all modules in the respective loop have to be pulled out as they are daisy-chained

KARABO

  • New system implemented for deploying new versions that allows quick switch and possible roll-back
  • Script system implemented that performs schema evolution for scenes. Hence, old scenes will be adapted to changes automatically. This is important for the many scenes developed by the PCT.
  • Deployment of next Karabo version with bug fixes to be done before machine restart this afternoon

 

 