Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 306     Entry time: 03 Jul 2017, 10:26
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 meeting 

General

  • Accelerator was down all weekend due to cold compressors that were damaged in conjunction with the power outage on Friday
  • Since 0700 all interlocks are broken and tunnels are open.
  • Tunnels except XTD9 stay open until Thurday.
  • XTD9 can remain open longer

Availability of Networks

  • Network mainentenance that was requested last Friday for Tuesday has to happen today together with the rest of the facility. It was scheduled for 0700 - 0900 and is already almost done
  • Following the network maintenance, N. Jardon will bring down the motion loop for KMONO integration. This only affects the tunnels and instruments can work during this time
  • After the work by N. Jardon, IT needs to replace kernels on server machines. This will result in KARABO being down until early afternoon
  • Afterwards CAS needs to bring back KARABO
  • All measures will be announced on this log book

Instruments

  • Implementation of vacuum interlock should be implemented this week. 
  • SPB requires several adjacent loops to be included. Some of them are not up or complete. Maybe a simplified version should be installed first
  • SPB requests loop 12 from AE. However this will take until mid July as it contains new motors (SMARAGD) that have not been tested so far

AE

  • Work is currently ongoing on preparing to connect instrument interlocks to the DESY MPS system
  • Work is also required to fix problems for the laser group that are most likely due to faulty wiring or a broken terminal

IT

  • The dual power supply for switches saved a lot of work for IT after the power cut on Friday
  • Unfortunately, the PLC CPUs in SASE1 are not on dual power. This should be upgraded as it is now also planned for SASE2/3.
  • Dual power should also be put for the uTCA systems