Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 306
Entry time: 03 Jul 2017, 10:26
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
General
- Accelerator was down all weekend due to cold compressors that were damaged in conjunction with the power outage on Friday
- Since 0700 all interlocks are broken and tunnels are open.
- Tunnels except XTD9 stay open until Thurday.
- XTD9 can remain open longer
Availability of Networks
- Network mainentenance that was requested last Friday for Tuesday has to happen today together with the rest of the facility. It was scheduled for 0700 - 0900 and is already almost done
- Following the network maintenance, N. Jardon will bring down the motion loop for KMONO integration. This only affects the tunnels and instruments can work during this time
- After the work by N. Jardon, IT needs to replace kernels on server machines. This will result in KARABO being down until early afternoon
- Afterwards CAS needs to bring back KARABO
- All measures will be announced on this log book
Instruments
- Implementation of vacuum interlock should be implemented this week.
- SPB requires several adjacent loops to be included. Some of them are not up or complete. Maybe a simplified version should be installed first
- SPB requests loop 12 from AE. However this will take until mid July as it contains new motors (SMARAGD) that have not been tested so far
AE
- Work is currently ongoing on preparing to connect instrument interlocks to the DESY MPS system
- Work is also required to fix problems for the laser group that are most likely due to faulty wiring or a broken terminal
IT
- The dual power supply for switches saved a lot of work for IT after the power cut on Friday
- Unfortunately, the PLC CPUs in SASE1 are not on dual power. This should be upgraded as it is now also planned for SASE2/3.
- Dual power should also be put for the uTCA systems
|