SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 344
Entry time: 26 Jul 2017, 10:35
|
Author: |
Adriano Violante |
Location: |
XHEXP |
Severity: |
Information |
Subject: |
Status after 9.30 Meeting |
|
|
General
- Today the machine is being prepared to lase with 30 bunches in order to allow the radiation measurements in SASE1 Exp. Hall on Thursday and Friday.
- Today GUI will be down for a couple of minutes at 11.30 to allow modifications of the servers for bugs fixing.
- Specific SASE1 areas will be off limits during the test, scheduled for SPB OPT 27.07.17 12:00-16:00 , SPB EXP 28.07.17 9:00-15:00 and FXE 03.08.17 9:00-15:00. Please address Eric Boyd's presentation for details. A mail reminder will be also sent to notify the beginning and ending of the tests.
- The machine will be running with 30 bunches during the test and with 1 bunch during the night. Since no EPS is implemented, screens and sensitive components need to be taken out during the 30 bunches operation.
- New version of Karabo ready to be deployed. The time slot when this will happen will be discussed on Friday,
- Screens controlled by Karabo cannot be read from DOOCS. The Karabo/DOOCS interface problems will be be addressed with high priority by CAS.
XTDs
- Fast valve in XTD9 still has issues with noise. Issue will be addressed tomorrow with AE support.
FXE
- The detector group is updating the firmware for the LPD to fix the trigger signal problems. A test on just 1 quadrant will be done today together with ITDM
- Interlock implementation in Loop 1 ongoing.
SPB
- Integration of the turbo pumps in the VAC loop ongoing. Interlock possible.
- Chiller control being included in Loop 5 - Crate has been modified this morning. Loop will be updated checking that this will not stop the turbo pumps.
- SMARACT motors being implemented. First motor is ready to be tested today after hardware problems have been fixed.
- Work on in vacuum interlock in SPB ongoing.
- The ELMO controllers for the motors of the liquid jet manipulator in Loop 13 should be brought and ready by CW 32. AE working on that.
|