Message ID: 344     Entry time: 26 Jul 2017, 10:35
Author: Adriano Violante 
Location: XHEXP 
Severity: Information 
Subject: Status after 9.30 Meeting 

General

  • Today the machine is being prepared to lase with 30 bunches in order to allow the radiation measurements in SASE1 Exp. Hall on Thursday and Friday.
  • Today GUI will be down for a couple of minutes at 11.30 to allow modifications of the servers for bugs fixing.
  • Specific SASE1 areas will be off limits during the test, scheduled for    SPB OPT 27.07.17   12:00-16:00 ,  SPB EXP 28.07.17 9:00-15:00   and  FXE 03.08.17  9:00-15:00.  Please address Eric Boyd's presentation for details. A mail reminder will be also sent to notify the beginning and ending of the tests.
  • The machine will be running with 30 bunches during the test and with 1 bunch during the night. Since no EPS is implemented, screens and sensitive components need to be taken out during the 30 bunches operation.
  • New version of Karabo ready to be deployed. The time slot when this will happen will be discussed on Friday,
  • Screens controlled by Karabo cannot be read from DOOCS. The Karabo/DOOCS interface problems will be be addressed with high priority by CAS.

XTDs

  • Fast valve in XTD9 still has issues with noise. Issue will be addressed tomorrow with AE support.

FXE

  • The detector group is updating the firmware for the LPD to fix the trigger signal problems. A test on just 1 quadrant will be done today together with ITDM
  • Interlock implementation in Loop 1 ongoing.

SPB

  • Integration of the turbo pumps in  the VAC loop ongoing. Interlock possible.
  • Chiller control being included in Loop 5 - Crate has been modified this morning. Loop will be updated checking that this will not stop the turbo pumps.
  • SMARACT motors being implemented. First motor is ready to be tested today after hardware problems have been fixed.
  • Work on in vacuum interlock in SPB ongoing.
  • The ELMO controllers for the motors of the liquid jet manipulator in Loop 13 should be brought and ready by CW 32. AE working on that. 