Group Selection Page
HELP
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 303
Entry time: 30 Jun 2017, 11:33
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1 Readiness Meeting |
|
|
Data Acquisition and Data Archiving
- K. Wrona summarised the basic ingredients of the system.
- All components are ready and tested individually
- Integration in the instrument environment is needed and will be done first in the context of commissioning LPD in FXE starting from 5 July
- DAQ and archiving for the tunnels was originally not foreseen but is being worked on now
- The split up of the KARABO environment into several "Topics" was done on purpose to allow development with minimal interference
- The separate topics have to be re-integrated now
- The sildes from Krzysztof can be found here
XTDs
- KMONO integration should happen next week starting on Monday
- The planned work on the network switches should only start on Tuesday as it interferes with KMONO integration
FXE
- Topics to be worked on next:
- Vacuum interlock integration
- LPD integration
- uTCA digitizer (was already working in Karabo 1.4.7)
- Great Eyes Detector has a rate limitation that was not there before
- Longer term topics
SPB
- Loops 12 and 5 are prepared and uploaded but need to be commissioned now
- Firware for loop 13 is needed next
- Many motors seem to be getting 24V, but should be ruuning with 48V. What is wrong? This needs to be checked in the EPLAN and CRDs
- Loops appear to be missing components
Detectors
- LPD goes to FXE on 5 July. Integration work in the hutch starts immediately after
- AGIPD then goes into the X-Ray test stand in HERA-S
- Note that the DAQ infrastructure can only support one detector at full rate at a time.
- In principle this should not be an issue at 30 bunches but it requires the veto system to work which needs testing
Electronics
- Work this week concentrated on preparing everying for deploying the instrument vacuum interlocks next week
- The problem with wrong names in the PP laser was identified as a wiring issue in one crate
- Work also concentrates on timing and train builder to support detector integration from next week
|