Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 303
Entry time: 30 Jun 2017, 11:33
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1 Readiness Meeting |
|
|
Data Acquisition and Data Archiving
- K. Wrona summarised the basic ingredients of the system.
- All components are ready and tested individually
- Integration in the instrument environment is needed and will be done first in the context of commissioning LPD in FXE starting from 5 July
- DAQ and archiving for the tunnels was originally not foreseen but is being worked on now
- The split up of the KARABO environment into several "Topics" was done on purpose to allow development with minimal interference
- The separate topics have to be re-integrated now
- The sildes from Krzysztof can be found here
XTDs
- KMONO integration should happen next week starting on Monday
- The planned work on the network switches should only start on Tuesday as it interferes with KMONO integration
FXE
- Topics to be worked on next:
- Vacuum interlock integration
- LPD integration
- uTCA digitizer (was already working in Karabo 1.4.7)
- Great Eyes Detector has a rate limitation that was not there before
- Longer term topics
SPB
- Loops 12 and 5 are prepared and uploaded but need to be commissioned now
- Firware for loop 13 is needed next
- Many motors seem to be getting 24V, but should be ruuning with 48V. What is wrong? This needs to be checked in the EPLAN and CRDs
- Loops appear to be missing components
Detectors
- LPD goes to FXE on 5 July. Integration work in the hutch starts immediately after
- AGIPD then goes into the X-Ray test stand in HERA-S
- Note that the DAQ infrastructure can only support one detector at full rate at a time.
- In principle this should not be an issue at 30 bunches but it requires the veto system to work which needs testing
Electronics
- Work this week concentrated on preparing everying for deploying the instrument vacuum interlocks next week
- The problem with wrong names in the PP laser was identified as a wiring issue in one crate
- Work also concentrates on timing and train builder to support detector integration from next week
|