Dear All,
Please, see below the updates regarding Karabo 2.2.4.1 deployment:
SA3: 05.07, Thursday (references: Chris, Wajid, and Valerii) - Done
SA2: 06.07, Friday (references: Chris, Wajid, and Valerii) - Done
SA1 + FXE: 09.07, Monday (references: Wajidi) - Done
SPB: 10.07, Tuesday (references: Gabriele) - Done
- BKR: 10.07, Tuesday (references: Wajid, Jan, Harald) ToDo
- LAS, SQS and SCS dates have to be agreed with the respective contact persons. (references: Cyril, Riccardo, and David) In Progress
- ITDM: We are working to understand and solve a problem reported by Nasser in Karabo 2.2.4 Configurator (references: Dennis, Cyril, and Nasser) In Progress
Hugo Silva Santos wrote: |
Dear All,
I would like to inform that we released last Friday (22.06) the Karabo 2.2.4 version. We got around five days delayed to prioritize issues regarding Karabo-DAQ integration and MDL devices that were found in the last steps of the test cycle. However, fortunately, those issues are solved.
Based on this run, the new dates that we (CAS) are proposing to start the deployment in operation will be:
- SA3: 28.06, Thursday (CAS references: Chris, Wajid, and Valerii)
- SA2: 02.07, Monday (CAS references: Chris, Wajid, and Valerii)
- SA1 + SPB + FXE: 03.07, Tuesday (CAS references: Alessandro, Dennis, Gabriele, Wajid)
- SPB deployment should not impact AGIPD firmware test week, as agreed before.
- BKR: 28.06? (Wajid and Jan, could you please agree offline?)
- LAS, SQS and SCS dates have to be agreed with the respective contact persons.
-
Hugo
|
|