Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 594     Entry time: 21 Jan 2019, 10:43
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Report after dispatch meeting 09.30 

SPB/SFX

FXE

SQS

  • AQS chamber has been removed. The reaction microscope is now being installed. (Currently sitting next to the beamline)
  • New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. ==> Master loop will be updated until tomorrow. Tests still planned for Wednesday.
  • Mpots control and integration is still being debugged by CYoungman. Additional tests planned for tomorrow.

SCS

  • All the PLC hardware is now fixed, with the exception of some high voltage interlock controls, which is waiting for the E-plan to be finalized. 
  • Firnware update needed and planned for the next days.
  • Updated interlock definition will be given to AE by SCS
  • Electronics and cabling for the laser hutch is coming next. MTeichmann will talk to EET to agree on priority concerning the cables production and pulling. It may be necessary for SCS to pull a few cables as soon as possible (by themselves?). Anyway, cables route will be needed.
  • This morning the PLCs in the SCS raclroom went off. The information from TS is that the emergency power off button was pushed in the SCS experiment hutch. 

MID

  • Has to be clarified when the chiller is going to be back
  • Homing test motors in XTD1. Small issues found. Update needed.
  • MC2 Motors are working properly
  • Workin out commissioning priorities with AE and CAS based on the cables availability

HED

OPT Lasers

XRO

  • Tomorrow the M2 in XTD will be ready for commissioning
  • On Wednesday the MOV2 loop in SASE2 tunnels will be updated. CAS is saving the motor parameters right now.

​​XPD

  • Screens have been exchanged
  • XTD2 photonic science camera is back and working
  • XTD10 SQS2 pop in monitor back and working
  • All tasks foreseen for the Winter shutdown have been completed.

 

VAC

AE

  • AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. ==> MOV 1 will be updated. Also CAS will be asked to save the motor parameters. NO EPS and MOV 2 loops update necessary for now.

ITDM

DET

CAS

  • Data logger schould be working for every component right now.
  • On Wednesday the MOV2 loop in SASE2 tunnels will be updated. CAS is saving the motor parameters right now.

AoB