SASE1 Status and SASE3 Readiness
 | 
|   Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  | 
Not logged in | 
  | 
   | 
| 
Message ID: 567
    Entry time: 01 Oct 2018, 10:49
 |  
| Author: | 
Adriano Violante  | 
 | Location: | 
General  | 
 | Severity: | 
Information  | 
 | Subject: | 
Status report after dispatch meeting 09.30  | 
 
  |  
 
 | 
SPB 
FXE 
SQS 
SCS 
MID 
	- Loop4 is ready but after the electrical shutdown form last week the PLCs racks aha to be re initialized (not powered right now). This is done by AE and is ongoing.
 
 
HED 
	- HR mono commissioning ongoing. Being pumped down.
 
	- Pulse picker tested. Logic has to be slightly changed. CR will come soon. 
 
 
XPD 
	- FXE diamond screen for beam position measurements  has been installed in XTD9. Section being pumped this week.
 
 
VAC 
	- 3rd mirror chamber  in SASE2 being pumped now.
 
	- XTD6 all vacuum gaps are closed.
 
	- FXE MONO will be pumped probably on Wednesday
 
 
AE 
	- SASE3 Master loop has to be updated. 
 
	- MPS update for SQS being worked out. Conditions have been clarified with SQS.
 
	- MPS update for SPB is ready and has to be done. This includes the interlock definition for the detector's z motion.
 
 
ITDM 
	- Commissioning SQS - CAS support needed to configure the DAQ for the cameras.
 
	- DAQ links for Basler cameras in MID are needed. This will be done asap.
 
 
CAS 
	- 2.2.6. hot fix will be released probably today. It will include fixes for the DAQ middle layer device.
 
 
AoB 
Status of the redundant power for the racks in the SASEs according to Technical Services: 
	- All the works have been successfully done: the foreseen racks get now 2 working redundant power lines.
 
 
	- The power is back and no further interruptions are planned/needed.
 
 
	- This week a visual inspection and relative "Abnhame" will take place, without any actual electrical works being involved.
 
 
	- All eventual / additional interventions will be scheduled for the winter shutdown.
 
  |