Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Entry   Status and plans after Readiness meeting, posted by Monica Aresté on 10 Jan 2018, 13:22 
    Reply   Re: Status and plans after Readiness meeting, posted by Hugo Silva Santos on 10 Jan 2018, 14:53 
Message ID: 441     Entry time: 10 Jan 2018, 13:22     Reply to this: 442
Author: Monica Aresté 
Location: General 
Severity: Information 
Subject: Status and plans after Readiness meeting 

PSPO:

- G.Wellenreuther inform that MKK is planning to test the Umschaltautomatik, this will affect XHE1, XHE3, XHPSC, XHEXP, XHVAC. Oleg Engelmann will send a mail with detailed information.

 

SPB:

- AGIPD is fully occupied again and restarted this morning as scheduled. Everything works well so far and it is expected to finish the test on time. Further test with new Microcontroller are scheduled for next week.

- Most of the loops that required modifications are updated or on going.

- Module BKF00128 will be modified this week, update of Loop 5 will folllow.

- Loop 12 is ready to be deployed, to confirm if modifications in the modules are finished and reorganization on rack UH2.12 is ready.

- It is necessary to correct an error in module BKF00220,  AE will agree with SPB  when this will be possible.

 

FXE:

- New Vacuum device in operation.

- Karabo 2.2.0 being deploy today for FXE.

 

AE:

- Replace one Micro-TC in SASE3, a cooling unit is failing and one module will be replaced by a new one today. This is providing timing for XGM and K-mono. AE will inform by the logbook before to start the replacement.

 

 