Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 340     Entry time: 24 Jul 2017, 10:03
Author: Gerd Wellenreuther 
Location: General 
Severity: Information 
Subject: Tunnel access schedule updated 

Dear all,

access to XTD9 and XTD10 will be available from tomorrow Tuesday the 25.7. 7:00 (Vacuum group will make sure the interlock is broken), until Wednesday 26.7. 14:00:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Please send any additional access requests to M. Dommach and T. Tschentscher.

Cheers, Gerd

ELOG V3.1.4-7c3fd00