Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 524     Entry time: 14 May 2018, 10:17
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Summary of the dispatch meeting 09.30 

SQS

  • Loop1 still being worked by AE. Not yet up and running. 
  • Loop 3 is needed to be up and running in 2 weeks since the mirror motors ar eincluded in this loop and they are needed for the final check with FMB.

SCS

  • Bernard has been added to the SCS operation logbook and he is getting al the updates concerning commissioning.
  • Testing of the Loop 1 motors ongoing., 2 out of 20 motors have problems. Being investigated.
  • Some connectors names are reported not to be consistent with the EPLANS. Martin Teichmann will check that with EET.

​​AE

  • SCS:
    • loop 2 running. Bernard has recommended that you start with commissioning of KBS_VDM, _HFM, _BFL, VFM motors because they are using MC2MOTOR soft device class (controller is Elmo).
    • Crate BKF00157 can be removed and refresh terminal will be added without interrupting the PLC - only equipment connected to this crate will not be available during this period of change.
  • SASE3:
    • -Request from Andreas Koch about interlocks for MCP and LED Power in SQS/SCS (this installation is unique in SASE3). For that purpose we have to update EPS, MOV2 and Master loop in SASE3. PRC will be triggered by E-Mail
  • SASE2:
    • -We want to update SASE2 in order to get beam permission interlocks properly. Therefore we need to update, EPS, Vacuum loop and Master loop. PRC will be triggered by E-Mail
  • SPB:
    • -Today we will deploy loop 12 and 13 and Master loop. In the Master loop we will add beam permission conditions, so we want to test it and therefore we will need to open all the valves in SPB as well as the last ones in the Tunnel. Has to be decided when it is possible with the SPB people.
  • FXE:
    • -All loops updated past week. Waiting for answer from FXE about when we can test the same beam permission conditions as in SPB. To be agreed with FXE.

 

DET

  • Working of the optimization of the python piece of code allowing the display of online images. Right now 30 images per second rate is possible.

ITDM

  • GPFS server fixed.

CAS

  • XTD1 CRLs will be integrated iin the control system in KW 22
  • 20.07 is the goal date for beam in MID and HED optics Hutch.  

 