Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 140
Entry time: 12 Apr 2017, 12:52
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after 09:30 meeting |
|
|
Tunnel Closed.
Mirrors:
Status:
- No information on status of mirrors and PBLM since Optics group was not at the meeting
Vacuum Loop:
Status:
- All vacuum sections were successfully tested in XTD2 yesterday (work ended very late)
- DPS was tested successfully and all interlocks and remote controls were working
- The protection switch on the ion pumps can still not be actuated remotely
- XGMs in XTD2 and XTD9 fully in the interlock
- V0 valve and absorber were moved and interlock tested. Communication with DESY was also tested and is ok.
EPS Loop:
Status:
- No explicit information today (see remark above)
Motion Loop:
Status:
- No explicit information today (see remark above)
Imagers
Status:
- All imagers in XTD2 are ok
- Trigger is not working on one of three imagers.
- Testing proceeded in XTD9 yesterday
- One camera in one pop-in can not be reached (Network problem?)
Karabo:
Status:
- Running stably
- Work required now:
- Photonics Camera driver
- Clean up the project database
- Clean up master equipment list
Tasks for today:
Note: All loops should be left running and no changes to Karabo.
- Proceed with remote testing
- Check out adequacy of scenes
- Monitor stability and responsiveness of GUI Server and Log Servers
- Set up monitoring of temperatures and pressures overnight (A. Silenzi)
- Cleanup Karabo
Tasks for tomorrow:
- Tunnels should re-open tomorrow
- Continue tests from remote and check stability and robustness of systems
Other topics
- Tunnels open over the Easter weekend and also during the day on Tuesday 18 April
- There will be a SASE Readiness Meeting at 09:00 on Thursday in XHQ E1.173
|