Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 140     Entry time: 12 Apr 2017, 12:52
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and plans after 09:30 meeting 

 Tunnel Closed.

Mirrors:

Status:

  • No information on status of mirrors and PBLM since Optics group was not at the meeting

Vacuum Loop:

Status:

  • All vacuum sections were successfully tested in XTD2 yesterday (work ended very late)
  • DPS was tested successfully and all interlocks and remote controls were working
  • The protection switch on the ion pumps can still not be actuated remotely 
  • XGMs in XTD2 and XTD9 fully in the interlock 
  • V0 valve and absorber were moved and interlock tested. Communication with DESY was also tested and is ok.

EPS Loop:

Status:

  • No explicit information today (see remark above)

Motion Loop:

Status:

  • No explicit information today (see remark above)

Imagers

Status:

  • All imagers in XTD2 are ok
  • Trigger is not working on one of three imagers. 
  • Testing proceeded in XTD9 yesterday
  • One camera in one pop-in can not be reached (Network problem?)

Karabo:

Status:

  • Running stably
  • Work required now:
  • Photonics Camera driver
  • Clean up the project database
  • Clean up master equipment list

 

Tasks for today:

 

Note: All loops should be left running and no changes to Karabo.

  • Proceed with remote testing
  • Check out adequacy of scenes
  • Monitor stability and responsiveness of GUI Server and Log Servers 
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Cleanup Karabo

Tasks for tomorrow:

  • Tunnels should re-open tomorrow
  • Continue tests from remote and check stability and robustness of systems

Other topics

  • Tunnels open over the Easter weekend and also during the day on Tuesday 18 April
  • There will be a SASE Readiness Meeting at 09:00 on Thursday in XHQ E1.173

 