General:
- G. Wellenreuther has created a link to the first version of a central schedule of "our" tunnels: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
- Any changes of schedules should be put in there first, and THEN a short message can be sent using the e-log pinpointing people always to this page. Please check correctnesss, and feel free to provide Gerd with any feedback.
XTDs
- Minor problem with Ion pump controllers, AE working on it.
- Vacuum loop needs an update but it is not urgent.
FXE
- Ion pumps controller issue already fixed.
- Test of CRL with PLC is on going. There are some issues with encoders, could be a cable mismatch problem in PP, JJ to check. The cables for CRL have been already measured and are correct.
- Radiation safety measurements being doing today.
SPB
- EET is working to generate the exports for loops 7 and 12. Export for loop7 will be ready this week and EET will continue with loop 12.
- Tests with loop2 on going.
- Firmware for Loop 3 is available, but cables have to be repaired.
- Modules BKF00056, 00057 affected by Ion pumps issue already modified.To double check with N. Coppola if more modules are also affected by this problem.
- Cameras are not in Karabo, this is a requirement before cameras can be connected. A. Silenzi to work on that.
Laser
- After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need some additional information from Laser group.
- There is a mismatch beween the motors and the control, AE will check if it ia a firmware or hardware problem.
Diagnostics
- External trigger not always working, CAS working to find the cause and provide a solution.
Software
- Karabo version installed in a different domain, this will permit to fix errors. When this version will be ready, CAS will need 2 hours of downtime to implement.
|