Entry   overview of required racks, posted by Sabine Cunis on 03 Nov 2016, 17:00 VCCT_Rack_1p06_b.jpgVCCT_Rack_1p07_b.jpg

just for reference ... here are pictures and schematics of the racks which are involved in the current commissioning.

Entry   Current PLC-Karabo Conflict, posted by Alessandro Silenzi on 03 Nov 2016, 12:58 

Tobias Freyermuth and me worked on the system and as of last night, we found two new issues between Karabo and the PLC interlock:
 - one is a Karabo issue from the Interlock PLC interaction, the Karabo device waits for a PLC response that does not come when the PLC is interlocked (i.e. Karabo wants to open a valve but the PLC correctly refuses and ignores the command)


 - one is a PLC issue, the interlock is not triggered in all cases after testing (e.g. a ion pump out of set point does not closes a gate valve closure as specified).

The first one was reproduced with the BeckhoffSim simulation. It can therefore be fixed by CAS without dependencies from AE (except for the next integration test).

Entry   Minutes of last week's meeting, posted by Tobias Haas on 26 Oct 2016, 14:26 

 http://tinyurl.com/gvvv392

Entry   Start of Logbook, posted by Tobias Haas on 26 Oct 2016, 13:55 

Dear Colleagues,

in the future we would like to use this mechanism to record and exchange information that concerns the work done within the context of this task force. Please use this generously. We shall also put a link to the minutes after each weekly meeting.

 