Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 353     Entry time: 03 Aug 2017, 10:52
Author: Eric Boyd 
Location: XHEXP 
Severity: Information 
Subject: No Radiation Measurements in SASE 1 This week 

Do to repairs that need to be made with the cold compressor. We will be unable to perform Radiation Hutch Commissioning for SASE 1 this week. We will attempt to reschedule the Measurments for Thursday or Friday (10.08 or 11.08) of next week, depending on if it can be coordinated with all involved parties.

There is no restricted access to SASE 1 until then.