Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 93     Entry time: 03 Apr 2017, 10:03
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Schedule for PLC and Karabo 3 April after 09:30 Meeting 

Tunnels closed today and tomorrow

- AE updates Vacuum and motion loop in the morning

- V. Bondar, J. Eidam and H. Sinn test vacuum in the afternoon (emphasis on understanding interlock conditions)

- A. Koch tests XTD2 imagers in the afternoon

See also  https://in.xfel.eu/redmine/projects/sase1/agile_board

 

Problems solved on Friday last week:

- Arms 2 & 4 of SRA are now moving. Apparently spindles had mechanical resistance that resulted in error condition. After moving a few times, this appears to be gone

- One of the problematic ion pumps had the serial line disabled. However, other lines 

 

 

 