Message ID: 42     Entry time: 10 Feb 2017, 15:07
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Updated Components List 

 Added Diagnostic Screen for SPB and changed PRIO for DPS - XGM - DPS in XTD9 to high as discussed during the S1R meeting

Attachment 1: Componets-XTD2-9-new.xlsx  13 kB