SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 296
Entry time: 21 Jun 2017, 10:21
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
XTDs:
- DESY requests the KMONO to be commissioned since the K Values of the undulators appear not to be as accurately calibrated as originally advertised. Management decided to put KMONO at the top of the priority list for this reason. W. Freund should work together with Mahadi and Nerea on getting the two goniometer motors (ELMO controller) working. When software is ready a ZZ access should be requested
- Latency of FEL imager is ~ 5s which is a problem for tuning and scans. M. Messerschmitt is looking into this. A. Silenzi was not aware of the problem up to now.
Radiation Safety Tests:
- Radidation safety tests are scheduled for 26 - 28 June. Proposed order is SPB Optics, FXE instrument, SPB instrument. Detailed plans to be discussed in a dedicate meeting on Thursday and plans to be presented in the Friday TC meeting
- Vacuum interlocks will not be implemented before the rad safety tests and vacuum will be operated completely in manual mode
- Open topic: Can the instruments use the beam after the rad safety test are done and how is the procedure?
- SRP needs to make precise statements about where people can/should be during the rad safety tests
FXE:
- Ready for radiation safety tests.
SPB:
- Tested motors in loop3
- Tested valves in loops 2&3
Electronics:
- Concentrating on getting KMONO going in the next days
Software:
|