Group Selection Page
HELP
Controls Group
ITDM
WP76
DET
Vacuum
EEE
WP78
FXE
SPB
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
MigratedByGroup
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 548
Entry time: 23 Jul 2018, 13:45
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
SPB
- Controls for the pulse picker being prepared. High priority for SPB
- Coordinated motion tests ongoing. High priority.
- ATT motors need to be re checked in XTD9. The closing dates for the tunnels are not known excactly. SPB should phone BKR for the last information
SQS
- Radiation safety test preparation ongoing.
- Loop 5 motors being tested.
CAS
- in XTD6 the VAC loop applied labels for the max excursions of the bellows.
- PBLM commissioning ongoing
- CRLs for MID to be repaired.
General
- Starting from this Wednesday the dispatch meeting will be shifted back to 9:30.
|