Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 510     Entry time: 16 Apr 2018, 12:38
Author: Adriano Violante 
Location: XHEXP 
Severity: Information 
Subject: Emergency off test in FXE - Update and next steps 

Dear all,

 

I was just informed by Ulf Brueggmann that the emergency power off test was successfully performed in FXE.

The  reality is now reflecting the planned logic, exeption being the power plugs in the experiment hutch. They do not go off. This is due to some missing cables. These will be installed in the next weeks and a new test will be planned for next shutdown.

The tests will continue tomorrow in SPB/SFX.

 

 

 