Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 109     Entry time: 06 Apr 2017, 11:27
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Schedule after 09:30 meeting 

 Tunnel Open.

Mirrors:

Status:

  • Vacuum will be closed on M1
  • M2 installation tomorrow or latest on Monday

Vacuum Loop:

Status:

  • Loop is up
  • XGM was integrated but tests needed on the interlocks. Hence valves to DPS now in manual mode (overrides interlock)
  • Interface to MPS has been successfully tested
  • Need to test fast valve connection to VAC and to MPS (Status re cabling was unclear this morning)
  • A few pumps still  have communication problems (to be discussed between AE and CAS)

EPS Loop:

Status:

  • AE did most of the missing wiring
  • Description of EPS interlock still missing. It is planned to start with just one imager in for first beam commissioning
  • One fiber connection from Balcony room to DESY still to be done by DESY

Motion Loop:

Status:

  • Problem on ELMO motors with linear drive persists. Needs additional testing

Imagers

Status:

  • Both motors working on FEL imager
  • Work should now concentrate on SR imager

Karabo:

Status:

  • Problem in TCP implementation identified that is suspected to cause the long delays observed e. g. with the imagers. Now needs extensive testing
  • Still no data recording achieved
  • Stability still needs monitoring

 

 

Tasks for today:

  • Work on GUI for the vacuum loop (J. Eidam, V. Bondar)
  • Test XGM interlocks (N. Jardon, M. Planas, T. Matsopoulos)
  • Continue tests with PBLM in the tunnels (M. Jidda)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Push DESY to install fiber connection from Balcony rooms to MPS (P. Gessler)

Tasks for tomorrow:

  • Put XGM into the vacuum interlock
  • Perform careful testing of all interlock conditions for the vacuum

Other topics

  • Regular SASE1 readiness meeting at 09:00 tomorrow in XHQ E1.173
  • Need to perform tests with EPS interlock conditions
  • Need to test fast valve connection to VAC and to MPS
  • Gas system for diagnostics needs to be flushed