The Interlock conditions for these two components has been positively tested but not exhaustively done:
The triggering of both via the actuation on the Fast Valve----------------->DONE and OK
Their triggering via HV down of each of the 6 ion pumps------------------>Partially DONE and OK: Partially means that only one of the pumps randomly chosen has been deactivated. The agreement is that the other remaining 5 can be done later, also from the office since the correspondence between the devices and the physical components has been confirmed.
Also, the individual actuation of both, Beam Stopper and V0 valve has been proof showing a consistent behaviour regarding the interlock definition.
Finally the XFEL Vacuum OK signal is available but AE is currently improving it. By the moment is not automatically sent to DESY, but instead it needs to be activated manually. According to AE feedback this should be corrected in the following days.
|