Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 211     Entry time: 08 May 2017, 15:18
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status after the 9.30 Meeting 

 Vacuum (M. Dommach):

  • Systematic tests of ion pumps in XTD9 almost finished - ongoing
  • Interface with MPS has to be tested
  • Problem with the fast valve in XTD2 and 9 - it is possible to close it remotely but not possible to open it again. Checking of the cabling is ongoing by Vacuum group
  • After restart of the vacuum loop many pumps in XTD 9 and 2 show an unknown error and some of them are not readble - CAS working on that.

 

PLC (P. Gessler, T. Freyermuth):

  • Implementation of shutters in Karabo ongoing -XS3 shutter in the VAC loop now. XTD9 to do.

Karabo (A. Silenzi):

  • GUI stability improved with a temporary solution. This should be enough to guarantee the proper functioning of images acquisition.
  • Update of devices list ongoing
  • Library for motors (base device), elmo and technosoft, being worked out.

Plans for today:

  • XGM work on gas injection
  • Bring back Karabo and clear XGM error codes
  • Perform systematic test of DPS in XTD9

Other topics:

  • No 09:30 meeting tomorrow - next meeting will be on Wednesday