SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 365
Entry time: 21 Aug 2017, 16:26
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Schedule after 09:30 meeting |
|
|
General
- Access to tunnel XTD10 ends today around midday and beam is expected back for the instruments on Thursday
SPB
- Good progress was made over the weekend with AGIPD. On Saturday first dark images were recorded
- Today the detector hybrids are being exchanged (1.0 -> 1.1)
- The injector motion system was taken into operation
- The SmarACT stages can currently not be tested since some parts are disassembled for final AGIPD installation
FXE
- Some loose ends were tied up for LPD
- JJXray was here last week and did some more installations, e. g. I0 monitors and alignment of the sample stack
- This week Gotthard integration will proceed
Tunnels
- The vacuum loop is now running for XTD10 with the full design firmware
- Approximately 40 ion pumps were locally test and are no under PLC control
- Almost all valves were locally tested and are also under PLC control
- XGM is connected to its own PLC currently (integrating Vacuum and gas supply)
CAS
- A disucssion on the details of Gotthard integration will happen with FXE after this meeting
|