Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 549
Entry time: 25 Jul 2018, 10:01
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SPB
- Interaction region cabling being reworked. By the end of the week shoud be done.
- For the 1st week of operation the Pulse Picker has to be ready - on a good track.
- For the 1st week of operation the coordinated motion and the Peltier system has to be integrated in the loop1.
- Karabo Middle layer for coordinated motion being developed.
- AGIPD z-motion encoder problems being addressed by AE/CAS
- uTCA for timing being installed.
SQS
- Trigger has been made available by AE. CAS devices ready today.
- ITDM and CAS have to meet to get the DAQ running.
- EPS signals being defined with AE.
- Loop 1 update to be agreed after the radiation safety and othe important tests have been done.
CAS
- Today between 12 and 14 the Karabo server will be unavailable in the SASE2 tunnels.
General
- Questions about the tunnel access and tunnel access schedule should go to Thomas Tschenscher and the PRC.
|