Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 482     Entry time: 02 Mar 2018, 14:36
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.03. 

Photon Run Coordinator (N. G. Kujala):

  • SASE1
    • Machine delivery 300 pulses upto XTD2 without M1 mirror in beam on Wednesday evening.
    • On Thursday 300 pulses deliver to FXE for radiation test.
    • Collected data using DAQ with 100, 200 and 300 pulses.
    • Large area Detector40 x 40 mm was set-up for radiation test at FXE for .
    • Damage test with 300pulses in FXE hutch with 0.5mm steel, 0.2mm copper and B4C block   
    • Vacuum at XTD2 absorber was stable and temp was also stable for 300 pulses
    • Harald setup piezo motors for M3 of SASE1.
    • Yesterday night beam delivery to SPB with single bunch.
    • ZZ for XTD9 on Tuesday by SPB for CRL test/check.
    • Vacuum on FXE branch in XTD9 was tripped on Tuesday early at 1am, which lost beam permission. Manually I have reset interlock.
  • SASE3
    • SASE3 commissioning is going on.
    • Commissioning the XGM and IMG correlations with Gas ATT and without Gas ATT;
    • SoftMono mirrors is commissioning
    • Gas attenuator commissioned and Raul made look-up table for pressure setting
  • 30bunches were operated in SASE3 with Gas attenuator

SPB

  • Ready for first commissionig
  • AGIPD power and cooling procedures OK
  • Feedback problems between Karabo and AGIPD. Being worked out

 

SQS:

  • Hardware installation starting Mid. March after  cleaning of the hutch
  • FMB will install the mirror tanks in April. Has to be synchronized with the remaning work in the hutches
  • Meetings with AE soon to strat planning the commissioning

 

 

FXE (P. Zalden / A. Galler):

  • Ready to accept first beam
  • Radiation tests done

 

SCS (J.T. Delitz)

  • Removing of wood cover: 05.02.2018
  • Cleaning: end of week 11.
  • End of march beginning of the installation of the first components (ALAS and TIM)
  • Waiting of the exact date for Interlock test to specify more exact the dates for the KB mirror system installation.

PP-Laser (M. Lederer):

  • LAS is now commissioning 3-stage NOPAs for both FXE and SPB.
    ​so far all in plan to finish in March

Vacuuum (R. Villanueva):

  • SASE1 
    • Nothing remarkable: the whole vacuum system works in a very stable way. We only had one incident on the output of 1-2 ion pumps that trigger once the interlock. For that we are investigating the causes .
  • SASE 3.
    • The whole vacuum loop (as required for the first lasing) down to the instrument front-end is under control and no special issues have appeared yet.
    • The SASE3 Gas Attenuator is under manually operation and most of the Photon Commissioning Members are familiar with it. Next steps are aligned with the deployment of the Pressure Feedback Control PID control available at Karabo level and to continue with the software-related tasks.
  • SASE2.
    • XTD1------->The complete vacuum string down to the front-end in the shaft building is under vacuum but in local mode operation (including XGM subsystem)
    •          ------->During this almost past week we already initiated the PLC local tests (i.e. US & DS Differential Pumping are already done), and in KW10 we aim to move on with the rest of the system (ion pumps and vacuum sector gate valves).
    •          ------->Absorber, V0 and Fast Valve wiring are in good progress and we think they could be ready for local tests by the beginning of next week.
    •          ------->The interlock tests are planned also for KW10.
    •          ------->Depending of the progresses of AE and CAS, we may even be able to deploy the first control scenes in Karabo.
    •  
    • XTD6 ------->The assembly works of the whole beamline there progress adequately and without remarkable "show-stoppers" that couldn´t be managed.
    •          ------->Vacuum Group and Optics group (N. Kohlstrunk) are having also special attention and dedication to the SDU vacuum chamber conditioning and preparation works for its upcoming in-vacuum mechanics installation.

 

XPD (T. Maltezopoulos ):

  • XGM in XTD1 is connected to DOOCS (together with DESY)
  • Synchronization of XGM@XTD1 microTCA next week
  • Local tests at XTD1 XGM were finished (together with AE)
  • XTD2, XTD9, and XTD10 XGMs are running 24/7
  • Change to 300 bunches went without problems
  • XTD9 XGM need SRG recalibration ... done meanwhile
  • Wajid, Joakim, Tommaso, and Theo will repeat  SASE3 DAQ Imager/XGM correlation today (need single shot operation)

 

 

Advanced Electronics (P. Gessler):

 

  • Broken terminal between SASE3 MOV2 PLC Loop and Master Loop were replaced last Friday without any side effects. The Train ID is now also provided from the MOV2 loop.
  •  So far, no PLC related export from the SASE2 Tunnel eplans of the vacuum, beam transport and diagnostics PLC crates are possible. Therefore we will build up the XLS file for the start up of the VAC and XGM loops next week. However, the related group plus AE and EETF should meet to evaluate, if an export is possible until end of March in order to use it for further installation work. Otherwise XLS files have to be crates manually again with support from all involved groups. Also consistent documentation is required between diagnostics on one side and vacuum and beam transport eplans.

SASE2 Tunnels (C. Youngman)

  • Table with the set priorities and deadlines available in Indico.

ITDM (K. Wrona):

  • Run Configuration Groups required for the user experiments for FXE and SPB/SFX have been defined and tested
  • Discussion after the meeting: Since the Karabo-DOOCS interface for XGM will be changed and it will affect also how the data arrive at DAQ data aggregators we need to modify and (re)test the BEAM_COND group.

 

 

Detectors (J. Sztuk-Dambietz, P. Lang):

  • AGIPD will operate with the old firmware due to problems with the new one
  • No calibration data available as of today
  • AGIPD is in a safe state

 

CAS (S. Brockhauser):

  • Gotthard for HIREX being operated
  • Progress on GATT commissioning by Valerii