Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 487     Entry time: 12 Mar 2018, 13:18
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB (Weinhausen):

  • During the night there was an interlock issue. The fast shutter was triggering the MPS interlock system. After several calls and request of support from SPB to the photon run coordinator and the machine run coordinator the problem was found and the interlock signal bypassed. This was due to some incomplete cabling of the fast valve. While this was knwe, after the last updated the correct configuration was not set up in the controlling PLC.
  • In general one has to note that the experiments do not have access to the MPS panels and there is no well established procedure when MPS interlocks are concerned. This will be reported in the PSO meeting.

FXE (Gawelda):

  • Before the beam shutdown FXE observed that the beam was very unstable.
  • 2 ion pumps went in error and the interlock was triggered. Again in this case is not clear who is responsible for the re setting of the interlock and the pumps.
  • Servers had to be restarted due to wrong train id after the cooling water accident
  • 0.5 MHz operation of the LPD successfully tested. 

SASE2 Tunnels (Youngman)

  • It is reported that the technical coordination of the necessary activities is missing.
  • A list of activities was sent by CYoungman to TTschentscher concerning SASE2 tunnels. In total 10 working days are needed to complete these tasks. This includes 1 week implementation and 1 week commissioning. Carefully planning with DESY is needed to avoid that the necessary 10 working days are scheduled around Easter, which will result in less effective days.

 

CAS (Santos)

  • HSantos is preparing a deployment plan for Karabo whoch includes the requirements and deadlines to be fulfilled by the other support groups (ITDM, DET, AE). The idea is to have this plan presented on Friday for discussion.

 

 