Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 241
Entry time: 17 May 2017, 11:55
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
Interlock in XTD10 is broken today and tunnel is open until 15:00
General:
- Unfortunately, info on access to XTD10 came too late for Vacuum group to organise the work in XTD10
- Technical issues and coordination between AE/CAS and PCT/Instruments continues to happen via SASE1 Readiness Log
Vacuum:
- Issue of spurious beam aborts due to short term vacuum spikes in XGM is solved (respective gauges taken out of interlock?)
- Change to interlock logic was requested by H. Sinn: V0 always closes if one gate valve closes) The reason is that after V0 is closed the accelerator has beam permission and can continue
- This logic will now be implemented in the next update by AE
Imagers:
- Problems with several photonics cameras for data collection exist. The data transfer is sensitive to packet losses. Hence dedicated servers need to be set up to avoid loss of data.
- ITDM has provided one additional server in balcony room. Eventually a dedicated server should be set up in the tunnel
- Maybe the way the camera sends the data could also be optimised
- Auto-scaling switch problem has not been tackled yet and is considered second priority after solving general readout problem
PLC:
- Fix for MC2 lib for TECHNOSOFT motors is ready. Tests together with N. Gerassimova can start today after motion loop update
- SPB can perform a parallel test on the PSLITs
- Motion loop and vacuum loop updates are scheduled for 12:00.
KARABO:
- A bug was found where device clients drop messages and hence the GUI looses the state of the device
- There is a fix that needs to be deployed. This should happen in parallel to the cycling of the loops between 12:00 and 14:00
Next Steps:
- Cycling of vacuum and motion loop at 12:00. T. Freyermuth informs the Photon Commissioning team
- Update of Karabo betweem 12:00 and 14:00
- Tests of PBLM with updated MC2 lib today
- Tests of PSLITS with updated MC2 lib by SPB
|