SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
|
Message ID: 456
Entry time: 22 Jan 2018, 13:28
Reply to this: 457
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
General remarks:
- Stable beam only to be expected starting from 1.03. for SASE1 instruments commissioning
- There is no guarantee for parasitic beam delivery to the experiments. If it happens at all it will most probably be during the last week of Feb. This has to be agreed on the fly with the BKR and H.S/ T.T.
SPB/SFX:
- Preparing D.02 for mirrors installation (next week)
- Karabo being updated
Advanced Electronics:
- Trigger delivered by DESY should be back and stable at 10Hz.
- ATM for timing has to be replaced in the balcony rooms. Bruno Fernandes is trying to find a way to reduce the downtime down to 30 minutes. Will be scheduled in the next days.
ITDM:
- 1 line card has to be replaced. Probably happens on Wednesday this week during the DAQ tests.
- Tuesday afternoon the online storage units will me remounted with the same path of the offline ones.
- This week a proposal for the in-house commissioning is going to be circulated.
|