Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 566     Entry time: 26 Sep 2018, 10:42
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Maintenance of the AGIPD ongoing.

FXE

  • Beamtime was successful
  • FXE imagers cannot be seen by the people in the BKR and that's a problem to efficiently communicating with them about e.g. beam stability issues. According to CAS a Karabo client is available for that purpose. The issue should be addressed by the PRC with the help of CAS. 

SQS

  • Interlock definitions - clarifications with AE ongoing.
  • Loop 7-10-14 being deployed
  • Some crates for the first loops were taken off for modifications. They will be back this week.
  • Trigger signal has to be provided by AE. TB will ask BF today.

SCS

  • Some cables for XGM had to be pulled last minute. In the XGM foreseen crate there was no space for additional terminals and another BKF module was chosen. Now some cables are too short. MTeichmann will adress the issue to the EETf
  • Fast CCD interlock definitions: MT will check whether SCS is on schedule. Info needed by the DET group.
  • Digitizers expected this week. 
  • DAQ tests will be done.

MID

  • Loop4 is working now. VAC section being pumped.
  • Request to CAS for GUI training. Training will be announced for the 04.10.

HED

  • HR mono commissioning ongoing. Some switches will be recabled now by KS. Has to be done asap. Motors direction has been checked and is correct.
  • Pulse picker will be ready tomorrow. ==> Since all the tunnels are open at the same time, there is a conflict of resources pointed out by CAS.

AE

  • SASE3 VAC loop will be updated again today, then SASE2 VAC
  • MPS update for SCS and SQS being worked out. Today updates will be ready.
  • FXE MONO the damaged crates will be changed and loop will be update today. Commossioning starting as soon as teh motors are replaced (today or tomorrow)
  • Scroll pump feedback issue: the feedback signals coming from the controllers were not correctly read. AE foud a solution and already presented a CR fo fox the crates.==> the time slot has to be agreed with SQS and SCS.
  • New framework should be deployed forst in the SA2 tunnels. Will be discussed offline with CY.

ITDM

CAS

 