Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
SPB
SQS
XO
ToBeMigrated2XWiki
ToBeMigrated2GitlabPages
ToBeMigratedByGroup
Migrated2Zulip
Archived2PDF
not2MigrateOrArchive
SCS
SXP Migrated2Zulip
Photon Commissioning Team
XRO
DOC
HED Migrated2Zulip
WP74
MID
PSPO_XO
XO_Operation
SQS Migrated2Zulip
FXE Migrated2Zulip
DET
Sample Environment
SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness
Technical integration and coordination
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
332
Entry time:
14 Jul 2017, 09:31
Author:
Jan Grünert
Location:
General
Severity:
Information
Subject:
WP74 SASE1/3 readiness status and outlook
SASE1 / SASE3 readiness --- WP74
2017-07-14
SASE1:
commissioning of Kmono started yesterday at 10h for some hours
Kmono will be used for undulator commissioning as soon as Kmono is commissioned itself, and machine is ready for this
Support to SASE tuning given to machine (ongoing)
Maybe today: support during SASE gain studies
During last week (service week) : GLT-Anbindung XTD2 established
SASE3:
During last week shutdown :
progress on DP installation, XGM cabling almost done, much imager and timing cabling done
When XTD10 is closed (as now) we currently cannot do much because there is no PLC loop in SASE3.
Non-Beckhoff technical commissioning started (e.g. some progress on MPOD HV-power supply)
WP74 must do a lot of technical commissioning in XTD10. Our work is by far not done when all our vacuum screws are tightened. There are different WP74 components in XTD10 than in SASE1 (not just a simple copy). WP74 requires the Beckhoff loops for tech. commissioning.
Alignment of DP „islands“ to be done in next shutdown.
Planned for next shutdown: installation of PES in XTD10, finishing of cabling