Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 332     Entry time: 14 Jul 2017, 09:31
Author: Jan Grünert 
Location: General 
Severity: Information 
Subject: WP74 SASE1/3 readiness status and outlook 

SASE1 / SASE3 readiness --- WP74

2017-07-14

SASE1: 

  • commissioning of Kmono started yesterday at 10h for some hours
  • Kmono will be used for undulator commissioning as soon as Kmono is commissioned itself, and machine is ready for this
  • Support to SASE tuning given to machine (ongoing)
  • Maybe today: support during SASE gain studies
  • During last week (service week) : GLT-Anbindung XTD2 established

SASE3:

  • During last week shutdown : 
    • progress on DP installation, XGM cabling almost done, much imager and timing cabling done
  • When XTD10 is closed (as now) we currently cannot do much because there is no PLC loop in SASE3.
  • Non-Beckhoff technical commissioning started (e.g. some progress on MPOD HV-power supply)
  • WP74 must do a lot of technical commissioning in XTD10. Our work is by far not done when all our vacuum screws are tightened. There are different WP74 components in XTD10 than in SASE1 (not just a simple copy). WP74 requires the Beckhoff loops for tech. commissioning.
  • Alignment of DP „islands“ to be done in next shutdown.
  • Planned for next shutdown: installation of PES in XTD10, finishing of cabling