Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 579     Entry time: 19 Nov 2018, 10:39
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Gotthard needs to be tested.
  • Pulse picker will be used and commissioning still has to be done.
  • Sample chamber encoder drift issue. Has to be investigated further. 

FXE

SQS

  • Beam during last WE: no major issues
  • Interlocks will be updated tomorrow
  • Some issues concerning direction of motors need to be fixed with AE.
  • AVC300 valve. Firmware will be available this week.
  • Digitizers and photonics camera are needed. Work ongoing

SCS

  • Motors for the Fast CCD cameras are not working properly and interlock about pressure for the detector is needed ==> Loop 7 needs to be updated, AE will take care of that.
  • When the CCD will inject data into the DAQ ITDM will be informed.
  • There was a request to CAS to provide values for the Monochromator at a rate faster that 10 Hz. This requires evaluation of the feasibility by the experts (CAS/AE). For the time being the middle layer will not be changed. 

MID

  • AGIPD commissioning:
    • Loop 11 needed. Today tests by AE. Until Tue. evening all the intelock tests should be done. From Wed. on operation.
    • uTCA crate needs to be operational too. According to AE can be done.
    • Thu. on: DQA tests.

HED

XRO

  • Temporary solution concerning Karabo topics management to alllow the reading of the Monochromator values by SCS. The definitive fix will come in the future.

XPD

  • XTD10 XGM repaired
  • XTD1 ph. science camera was replaced with the one previously installed in SASE1. Repair ongoing.
  • the company went bankrupt and was bought by a new company. For info contact A. Koch.

​​VAC

AE

  • OCD: intervention request during the WE to fix a train id issue. Should be ok now but the problem still needs to be reproduced and undertstood.

ITDM

CAS

  • Release tests with ITDM ongoing.

AoB