Dear all,

I had some minor updates of the TAS during the last days, please check again.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Be reminded that there will be virtually no access to XTD2, XTD4 and XTD10 before the 14.8. shutdown, so plan your work accordingly. Access requests please to M. Dommach, cc T. Tschentscher.

Cheers, Gerd