Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 410     Entry time: 01 Nov 2017, 11:24
Author: Adriano Violante 
Location: XHEXP 
Severity: Information 
Subject: Status after 9.30 dispatch meeting 

Instruments

  • SPB:
    • When PLC loops are restarted, still many device parameters are not properly recovered. This generates a lot of work for the team. Recently an entire day was lost.
      • The procedure now foresees a notice to the relevant group before each loop update. In particular, CAS will be asked for the last version of the parameters export to be re-implemented. The relative script was also updated and some bugs were fixed.
    • Loop 4 (maybe also 3) - MKB system - needs to be updated. This will be done as soon as the last eplan export is available.  
    • XTD9 loop needs to be updated with proper encoder names. CAS takes care of the missing names.
    • AGIPD Interlock system (loop 5) shows some issues concerning valves. It is not clear whether this is due to real problems with the interlock definitions or just to the fact that the system is not yet in vacuum. Chember will be pumped today and then the final test will be done.
  • FXE:
    • Preparation for the users run ongoing. PP laser treatment test ongoing.

Tunnels

  • XTD10/SASE3
  • XTD9/SASE1
    • Si-Mono: work has been done during the week end. The idea is to have it running without tilt stages.

Laser

  • Delay control is available through KARABO but requires ca 2 days testing: ongoing.

Electronics

  • Currently the work that is still needed for SASE3 is being evaluated
  • Planning for the next shut down is going on

CAS

  • Working on DOOCS/KARABO integration together with DESY. Ongoing. General frame being built. Then priority on the FEL imager needed for first lasing.
  • A. Silenzi and S. Hauff worked on the AGIPD procedures: Cooling down procedure successfully tested.
  • Work continues on reading and writing data for the GreatEyes detector: The idea is now to test the parallel operation of LPD, Gotthard and Greateyes detector.

ITDM

  • The folders for the next user run are being set up next week. GPFS is now fixed.
  • SPB requested 18 new cameras. This effort needs to be carefully coordinated. CAS and ITDM are working on that.