Message ID: 511     Entry time: 16 Apr 2018, 14:20
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

Summary of Karabo 2.2.3 deployment dates:

  • Karabo 2.2.3 deployed in SASE3 tunnels last friday ==> no major issues. DAQ can be deployed
  • Karabo in SASE2 Tunnels to be deployed today at 14:00
  • Karabo in SASE1 Tunnels to be deployed tomorrow at 08:00
  • Karabo in SPB/SFX experiment to be deployed today and tomorrow
  • Karabo in FXE experiment to be deployed on Wednesday

SPB

  • By tomorrow the mirror installation will be done.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests.
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE

AE

  • Timing servers update - this Thurdsay, starting at 14:00 for 1 hour the trigger and train id signals will be not available.

ITDM

  • Infiniband port fixing ongoing
  • GPFS bug to be fixed with a patch that should be issued on 24.04. To be checked whether it is still OK to install the patch or it is too late.

General

  • PSPO will ask HSinn for a detailed schedule concerning closing of the tunnels to fine tune the activities going on this week in the SASE2 and 3 tunnels