Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 511
Entry time: 16 Apr 2018, 14:20
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
Summary of Karabo 2.2.3 deployment dates:
- Karabo 2.2.3 deployed in SASE3 tunnels last friday ==> no major issues. DAQ can be deployed
- Karabo in SASE2 Tunnels to be deployed today at 14:00
- Karabo in SASE1 Tunnels to be deployed tomorrow at 08:00
- Karabo in SPB/SFX experiment to be deployed today and tomorrow
- Karabo in FXE experiment to be deployed on Wednesday
SPB
- By tomorrow the mirror installation will be done.
- It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests.
- During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE
AE
- Timing servers update - this Thurdsay, starting at 14:00 for 1 hour the trigger and train id signals will be not available.
ITDM
- Infiniband port fixing ongoing
- GPFS bug to be fixed with a patch that should be issued on 24.04. To be checked whether it is still OK to install the patch or it is too late.
General
- PSPO will ask HSinn for a detailed schedule concerning closing of the tunnels to fine tune the activities going on this week in the SASE2 and 3 tunnels
|