Message ID: 465     Entry time: 31 Jan 2018, 14:56
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB/SFX:

  • Fixing of Karabo scenes ongoing
  • Loop 5 need to be updated after discussion with DET group (Jolanta Stuk)
  • A meeting with AE will take place today to discuss the synchronous movement of the mirrors motor. 
  • The test on the NKB chamber of the indipendent movement should take place. It has to be double checked that such motors are implemented in Karabo.

CAS SASE3 (C. Youngman):

  • SASE3 tunnels closing today at 14:00. All the critical tasks were done. 
  • The day before the first lasing, a ZZ access is strongly requested. The request will be discussed in the PSO meeting.

ITDM:

  • Tomorrow the DAQ will be available for the AGIPD. LPD to follow. The goal is to have SASE1 ready next week as a whole.