Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 465
Entry time: 31 Jan 2018, 14:56
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
SPB/SFX:
- Fixing of Karabo scenes ongoing
- Loop 5 need to be updated after discussion with DET group (Jolanta Stuk)
- A meeting with AE will take place today to discuss the synchronous movement of the mirrors motor.
- The test on the NKB chamber of the indipendent movement should take place. It has to be double checked that such motors are implemented in Karabo.
CAS SASE3 (C. Youngman):
- SASE3 tunnels closing today at 14:00. All the critical tasks were done.
- The day before the first lasing, a ZZ access is strongly requested. The request will be discussed in the PSO meeting.
ITDM:
- Tomorrow the DAQ will be available for the AGIPD. LPD to follow. The goal is to have SASE1 ready next week as a whole.
|