Subject: Tunnel access schedule updated 

Dear all,

I updated the tunnel access schedule with the most recent information provided by M. Dommach and H. Sinn. If you plan any works in the tunnels please check their availability on

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd