Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 529     Entry time: 30 May 2018, 10:55
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

AE

  • CRLs in XTD1 being implemented
  • GATT and EPS loop in SASE3 being updated

SCS

  • Tests continue - No issues so far

SQS

  • ELMO controllers have to be configured for the mirror motors test. Slit motors have lower priority. Cables can be tested w/o being physically connected to the motors, but to configure the ELMO controllers the cables have to be connected to the real motors. Tomorrow AE is available to support these activities.
  • Basler cameras set up and working.

ITDM

  • SPB AGIPD test today or tomorrow

CAS

  • Hot fix for SPB released yesterday. This will address the issue of crushings when instantiating a new device. Has to be tested with SPB. 
  • XTD 6 will have no electricity for the racks today since Wille is completing the cabling. MTCA being shut down accordingly.