SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 529
Entry time: 30 May 2018, 10:55
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
AE
- CRLs in XTD1 being implemented
- GATT and EPS loop in SASE3 being updated
SCS
- Tests continue - No issues so far
SQS
- ELMO controllers have to be configured for the mirror motors test. Slit motors have lower priority. Cables can be tested w/o being physically connected to the motors, but to configure the ELMO controllers the cables have to be connected to the real motors. Tomorrow AE is available to support these activities.
- Basler cameras set up and working.
ITDM
- SPB AGIPD test today or tomorrow
CAS
- Hot fix for SPB released yesterday. This will address the issue of crushings when instantiating a new device. Has to be tested with SPB.
- XTD 6 will have no electricity for the racks today since Wille is completing the cabling. MTCA being shut down accordingly.
|