Group Selection Page
HELP
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 148
Entry time: 18 Apr 2017, 13:06
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
XTD Tunnels open until 15:00. Later XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum Loop:
Status:
- One broken Beckhoff terminal was exchanged before the weekend. This was the first failure of this type in 2 years
- After this the system ran without hickup over the Easter weekend
- The fix applied for ion pumps that avoids triggering an interlock condition when there is a communication failure on the serial output should be also applied now to other vacuum device, e. g. the turbo pumps
EPS Loop:
Status:
- Requires an update to be done asap so that N. Gerassimova can continue tests with the PBLMs afterwards
Motion Loop:
Status:
- Movement of the PBLM motors (ELMO controller) is not satisfactory yet. Motors start and stop but the movement is uneven and stops not always requested
- There is no test set up in the lab. So tests have to be done in the tunnels (XTD9)
PBLMs:
- All systems in XTD2 were tested and cameras calibrated including some at the beginning of XTD9
- Work continues on remaining systems in XTD9
- System with motor movement is still unsatisfactory (see above)
Imagers
Status:
- 2 Imagers in XTD2 have no trigger signal. Suspicion is that this might be configuration problem. P. Gessler will investigate
- One pop-in (245) in XTD9 cannot be reached with IP. Suspicion is incorrect network configuration -> K. Fillipakopoulos
SPB Tunnel components
- Signal pins of the Attenuator crate were tested. DC voltage is seen there at different levels on different pins. This looks problematic -> P. Gessler
Karabo:
Status:
- Ran stably over the weekend
Tasks for today:
Note: All loops should be left running and no changes to Karabo.
- Take equipment and junk out of tunnels
- Check trigger cabling for imagers in XTD2
- Check PBLM motor movement and continue testing in XTD9
Other topics
- Controlled access to tunnels is possible after 1500. Coordination with T. Haas and the DESY run coordination
|