Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 148     Entry time: 18 Apr 2017, 13:06
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 meeting 

XTD Tunnels open until 15:00. Later XTD2 and XTD4 are closed, XTD9/10 remain open

Vacuum Loop:

Status:

  • One broken Beckhoff terminal was exchanged before the weekend. This was the first failure of this type in 2 years
  • After this the system ran without hickup over the Easter weekend
  • The fix applied for ion pumps that avoids triggering an interlock condition when there is a communication failure on the serial output should be also applied now to other vacuum device, e. g. the turbo pumps

 

EPS Loop:

Status:

  • Requires an update to be done asap so that N. Gerassimova can continue tests with the PBLMs afterwards

Motion Loop:

Status:

  • Movement of the PBLM motors (ELMO controller) is not satisfactory yet. Motors start and stop but the movement is uneven and stops not always requested
  • There is no test set up in the lab. So tests have to be done in the tunnels (XTD9)

PBLMs:

  • All systems in XTD2 were tested and cameras calibrated including some at the beginning of XTD9
  • Work continues on remaining systems in XTD9
  • System with motor movement is still unsatisfactory (see above)

Imagers

Status:

  • 2 Imagers in XTD2 have no trigger signal. Suspicion is that this might be configuration problem. P. Gessler will investigate
  • One pop-in (245) in XTD9 cannot be reached with IP. Suspicion is incorrect network configuration -> K. Fillipakopoulos

SPB Tunnel components

  • Signal pins of the Attenuator crate were tested. DC voltage is seen there at different levels on different pins. This looks problematic -> P. Gessler

Karabo:

Status:

  • Ran stably over the weekend 

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Take equipment and junk out of tunnels
  • Check trigger cabling for imagers in XTD2
  • Check PBLM motor movement and continue testing in XTD9

Other topics

  • Controlled access to tunnels is possible after 1500. Coordination with T. Haas and the DESY run coordination

 

ELOG V3.1.4-7c3fd00