Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 148
Entry time: 18 Apr 2017, 13:06
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 09:30 meeting |
|
|
XTD Tunnels open until 15:00. Later XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum Loop:
Status:
- One broken Beckhoff terminal was exchanged before the weekend. This was the first failure of this type in 2 years
- After this the system ran without hickup over the Easter weekend
- The fix applied for ion pumps that avoids triggering an interlock condition when there is a communication failure on the serial output should be also applied now to other vacuum device, e. g. the turbo pumps
EPS Loop:
Status:
- Requires an update to be done asap so that N. Gerassimova can continue tests with the PBLMs afterwards
Motion Loop:
Status:
- Movement of the PBLM motors (ELMO controller) is not satisfactory yet. Motors start and stop but the movement is uneven and stops not always requested
- There is no test set up in the lab. So tests have to be done in the tunnels (XTD9)
PBLMs:
- All systems in XTD2 were tested and cameras calibrated including some at the beginning of XTD9
- Work continues on remaining systems in XTD9
- System with motor movement is still unsatisfactory (see above)
Imagers
Status:
- 2 Imagers in XTD2 have no trigger signal. Suspicion is that this might be configuration problem. P. Gessler will investigate
- One pop-in (245) in XTD9 cannot be reached with IP. Suspicion is incorrect network configuration -> K. Fillipakopoulos
SPB Tunnel components
- Signal pins of the Attenuator crate were tested. DC voltage is seen there at different levels on different pins. This looks problematic -> P. Gessler
Karabo:
Status:
- Ran stably over the weekend
Tasks for today:
Note: All loops should be left running and no changes to Karabo.
- Take equipment and junk out of tunnels
- Check trigger cabling for imagers in XTD2
- Check PBLM motor movement and continue testing in XTD9
Other topics
- Controlled access to tunnels is possible after 1500. Coordination with T. Haas and the DESY run coordination
|