Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 527     Entry time: 23 May 2018, 12:44
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

General

  • Please remember to send the list of the tasks you planned for the next shutdown to Monica Areste by the end of the week.
  • Please remember to send the list of the alignment works needed until July to Gerd Wellenreuther.

AE

SQS loop 3 is almost ready. 1 crate is currently in the AE lab but should be installed soon. The loop 3 is needed by SQS for the motor tests with FMB Oxford next week.

SQS

  • Due to a pump that stopped working (Caverion) this morning there was water on the floor of the laser hutch and part of the experiment hutch.  Some cables (not powered and packed) saw water. These are being checked. Also lasermet boxes on the wall saw water. Lasermet is checking that.
  • For the testing SQS requested the test box to AE 

SPB

  • Final DAQ test ongoing. Slow data acquisition OK. This is needed for the users program this week. Fast data acquisition (inc. AGIPD) will be tested next week.

ITDM

  • Patch released for Slow data acquisition FXE/SPB. LPD acquisition OK. AGIPD issues being investigated.

 