SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 521
Entry time: 02 May 2018, 11:17
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SPB
- After re-compiling the relative karabo device, the configuration procedure of the AGIPD is now smoothand reliable.
- PLCs update ongoing. AGIPD is in a safe state to allow the PLC update.
SQS
- Meeting today at 11:00 with AE, EET, CAS to define the next steps of the end to end tests.
AE
- SASE2 tunnels - Only VAC conditions are transmitted from the EPS loop to the MPS. All the other conditions were supposed to be not necessary for first lasing and were not implemented. Nevertheless this was not clear for the people working in the BKR (especcially for diagnostics) during the last days. It has to be discussed with the PRC (H. Sinn this week) whether these have to be implemented on a short time. In pronciple AE can do it if requested. Otherwise the definitions will be implemented in the next shutdown.
ITDM
- Failure of one IBM server for online storage. Thanks to the implemented redundancy this will not affect the operation. The performances have to be checked. IBM has been contacted.
- On monday evening ITDM OCD received a call from BKR because of some problems with the DAQ in the tunnels. It seems that this was due to the fact that the system was not properly tested by the "users" before. Seems to be solved now.
|