Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 361
Entry time: 11 Aug 2017, 10:07
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1/3 Readiness Meeting |
|
|
General
- The focus of activities next week for the AE and vacuum groups is on getting as much done in XTD10 as possible. There is a conflict with the aim to bring AGIPD to SPB and start commissioning. A lot of preparatory work was done for the latter this week already. Nevertheless this conflict needs to be monitored carefully. There will be a daily stand up meeting at 11:30 in front of the MCR to monitor the ongoing work. The SASE1 displatch meetings on Monday and Wednesday at 09:30 are correspondingly cancelled
FXE
- Philipp Lang reported on the status of the LPD commissioning. The detector is essentially ready to take data with 14 out of 16 super modules on the weekend. A few software issues remain but should not stop the activities.
- FXE is working on commissioning their greateyes camera
- Loop 7 needed to be re-worked for the van Hamos spectrometer
- Work is stil required for the Alio stage in the monochromater in XTD9. This will probably not be ready for first user operation.
- During the shutdown week work will focus on getting the instrument laser hutch going with the Tangerine laser. After the XFEL beam is back, first pump-probe experiments should be possible
- This afternoon radiation safety tests with 30 bunches and different materials shall take place
SPB
- One SmarACT motor is now running. The problem was identified as a combination of a connection and a Karabo issue
- The next step is to reconnect the remaining motors correctly and then all SmarACT motors should be operational (The firmware is set up for all)
- Updates need to be done for loop 5 (AGIPD chiller) and loop 7 (interlock). Since this can only be done after 1500 once the sample chamber is vented, this work was postponed to Monday
- SPB also provided an updated priority list to AE in order to fine tune the remaining work until user operation
Detectors
- Moving AGIPD will start early on Monday and the detector shall arrive in SPB around lunch time
- Immediate works shall be mechanical, connection of vacuum, chillers, power and cooling.
- A. Sztuk points out that the integration plan from SPB is very optimistic
Tunnels
- The goal of next week is to get the vacuum and the imagers into the PLC and eventually KARABO controls
- Detailed schedule planning was unfortunately stopped yesterday due to the fire next door but will be done today
- There is a scheduled power outage next week in the tunnels. Here is the respective email with information.
- The problem with the fast valves in SASE1 (spurious trips of the interlock) has not re-occured after the controllers were exchanged. They have been sent to the manufacturer
Laser
- Progress was set back last week due to un-announced work on the 11 C cooling circuit. This necessitated a re-alignment of the lasers
- Otherwise commissioning work in SASE1 is progressing
Electronics
- The points discussed are included with the affected groups
Software
- The storage for images from the cameras in the tunnels was changed due to a disk space crisis. Currently 150TB are available. This should be enough for some time
- CAS support for XTD10 work is need only after Thursday next week once the PLC work is done
- Karabo 2.1.14 was released. Currently 2.1.13 is deployed.
- Currently the data from LPD cannot be archived. Work on this topic was stopped yesterday due to the fire. Should happend today
|