Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 542     Entry time: 04 Jul 2018, 14:47
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Mirrors installation ongoing. Lid is open. Movements are being locally tested. Test of synch. motion with PLC to happen likely tomorrow.
  • AGIPD firmware being updated. On friday all the tests should be finished and on Monday the deployment of Karabo 2.2.4. could happen. 

AE

  • SCS support ongoing
  • SQS Loop 4 being prepared
  • New Interlock definitions are being / will be added for SASE1 and 3 
  • SASE3 VAC loop updated today
  • MPS plc has to be rebooted and the kernel has to be updated. The intervention will be done today between 16:00 and 17:00. No timing during the intervention. B. Fernandes will send a mail to the readiness mailing list before and after the completion of the work.

ITDM

  • Maxwell cluster foxing postponed until 15:00

CAS

  • An issue with the middle layer ofthe new release was found. Hotfix being developed and will be released today or tomorrow. NO ITDM migration affected.

 

 