Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 542
Entry time: 04 Jul 2018, 14:47
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 13:00 |
|
|
SPB
- Mirrors installation ongoing. Lid is open. Movements are being locally tested. Test of synch. motion with PLC to happen likely tomorrow.
- AGIPD firmware being updated. On friday all the tests should be finished and on Monday the deployment of Karabo 2.2.4. could happen.
AE
- SCS support ongoing
- SQS Loop 4 being prepared
- New Interlock definitions are being / will be added for SASE1 and 3
- SASE3 VAC loop updated today
- MPS plc has to be rebooted and the kernel has to be updated. The intervention will be done today between 16:00 and 17:00. No timing during the intervention. B. Fernandes will send a mail to the readiness mailing list before and after the completion of the work.
ITDM
- Maxwell cluster foxing postponed until 15:00
CAS
- An issue with the middle layer ofthe new release was found. Hotfix being developed and will be released today or tomorrow. NO ITDM migration affected.
|