SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
|
Message ID: 518
Entry time: 25 Apr 2018, 18:10
In reply to: 517
|
Author: |
Alessandro Silenzi |
Location: |
General |
Severity: |
Information |
Subject: |
Re: Status report after dispatch meeting 13:00 |
|
|
Regarding CAS Support for SASE2 Lasing:
CAS is happy to support in the frame of the On Call Duty system as it has been provided in the past.
Adriano Violante wrote: |
SPB
- Loops update: 1-4+8 this week. 5-7 Wed. next week. 11-13 end next week.
- Smaract motors for PAM are needed and Nerea is on it.
- It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests. Jola sick until 1st week of May. To be seen then.
- During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE. Interlock definitions have to be checked next week when HSinn is back.
- During the switch on of the detector many Karabo devices had a problem even if no error messages were displayed. The problems disappeared restarting the devices. The errors could not be reproduced. Ot top of that it is possible to collect data only from 15 modules out of 16. The one missing changes every time the device is restarted. ASilenzi on it.
- Technofoft motor with magnetic switches do not work. In the tunnel the same configuration works, Will be investigated by AE/CAS/SPB
- Motors upstream move sometimes by themselves. Discussion ongoing between AE SPB and CAS. To be adressed offline.
XPD
- Access of XTD1 today @14:00 to fix some EPS switches
- SASE2 firsta lasing should be tried this week end + monday. CAS support requested. ASIlenzi checks with CAS whether this is possible.
AE
- SCS exp: first loop running. 2 creates missing but loop is up.
- MPS connection tunnels SASE2 done
ITDM
- Online storage update patch to be installed today. The system should remain online but in some cases one could have some downtime (1-2 hrs)
- MPS connection tunnels SASE2 done.
General
On Wednesday the meeting will be held at 13:00. Starting from next monday it will go back to 9.30
|
|