SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
|
Message ID: 564
Entry time: 17 Sep 2018, 14:30
In reply to: 563
|
Author: |
Dennis Goeries |
Location: |
General |
Severity: |
Information |
Subject: |
Re: Status report after dispatch meeting 09.30 |
|
|
The GUI crashes reported by FXE will be fixed with the hotfix release coming ~tomorrow.
It is related to very high or low values in plotting widgets scratching the maximum floating point number (1e308 ~ infinity).
-- Wajid & Dennis
Adriano Violante wrote: |
SPB
-
Bug in the AGIPD cooling macro (setpoint resets itself to -59 C) - Jola knows about the problem. AS: Macro will be fixed.
-
AGIPD dark calibration: when new darks were injected with calling Steffen's script "xfel-calibrate", error message "Disk quota exceeded" popped up caused by a GPFS-related issue -> issue was solved. In general the script was not tested (scratch space was used!). One should not release script without ITDM knowing and haveing thested it before.
FXE
- Commissioning going on in the last days. Not able to get 14 keV beam for next users experiments. They will stick with 9.3 keV.
- Karabo stability issue (GUI) reported in the commissionig logbook.
SQS
- Problem with the digitizers bandwidth has now been solved.
- Loop 6 running w/o smaract stages.
- Flow switches issues solved . Rewiring of PLC needed
- Pfeiifer flow valves ready to be stested this week.
- Loop assignment changed. Change request handed in. As soon as it is approved it will be clear what loop to bring up next.
​SCS
- Loop 7 is running. Needs to be connected to Karabo.
- Loop 8 running too.
- Readiness of loop 1 and 4 ==> Interlock conditions need to be implemented.
- It is unclear whether the homing capability has been implemented already and can be used. Discussion ongoing. The use case has to be clarified.
- Network storage for the control PCs in the control room is requested. Scope definition and discussions with CAS and ITDM will be done offline.
MID
- Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. This week Slit and ATT will be commissioned. No big issues so far.
- Loop 4 being prepared by AE. Will be ready next week.
HED
- Work in tunnel ongoing
- HRMono- ready to start grouting. Mono will be here next week.
DET
- FXE/SPB GPUs crash issue - to be checked with ITDM - ITDM was not contacted.
ITDM
- DAQ was upgraded to the user friendly version in SASE3. After having discussed with FXE in the meeting, it was decided to install it also in FXE.
- DAQ training requested by SQS
CAS
- Karabo 2.2.5. patch being prepared. Will solve minor bugs and the crash due to empty data files.
- 28 Mpot update requests were received by CY. Need to be planned and coordinated with H.Santos.
|
|