Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
|
Message ID: 564
Entry time: 17 Sep 2018, 14:30
In reply to: 563
|
Author: |
Dennis Goeries |
Location: |
General |
Severity: |
Information |
Subject: |
Re: Status report after dispatch meeting 09.30 |
|
|
The GUI crashes reported by FXE will be fixed with the hotfix release coming ~tomorrow.
It is related to very high or low values in plotting widgets scratching the maximum floating point number (1e308 ~ infinity).
-- Wajid & Dennis
Adriano Violante wrote: |
SPB
-
Bug in the AGIPD cooling macro (setpoint resets itself to -59 C) - Jola knows about the problem. AS: Macro will be fixed.
-
AGIPD dark calibration: when new darks were injected with calling Steffen's script "xfel-calibrate", error message "Disk quota exceeded" popped up caused by a GPFS-related issue -> issue was solved. In general the script was not tested (scratch space was used!). One should not release script without ITDM knowing and haveing thested it before.
FXE
- Commissioning going on in the last days. Not able to get 14 keV beam for next users experiments. They will stick with 9.3 keV.
- Karabo stability issue (GUI) reported in the commissionig logbook.
SQS
- Problem with the digitizers bandwidth has now been solved.
- Loop 6 running w/o smaract stages.
- Flow switches issues solved . Rewiring of PLC needed
- Pfeiifer flow valves ready to be stested this week.
- Loop assignment changed. Change request handed in. As soon as it is approved it will be clear what loop to bring up next.
​SCS
- Loop 7 is running. Needs to be connected to Karabo.
- Loop 8 running too.
- Readiness of loop 1 and 4 ==> Interlock conditions need to be implemented.
- It is unclear whether the homing capability has been implemented already and can be used. Discussion ongoing. The use case has to be clarified.
- Network storage for the control PCs in the control room is requested. Scope definition and discussions with CAS and ITDM will be done offline.
MID
- Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. This week Slit and ATT will be commissioned. No big issues so far.
- Loop 4 being prepared by AE. Will be ready next week.
HED
- Work in tunnel ongoing
- HRMono- ready to start grouting. Mono will be here next week.
DET
- FXE/SPB GPUs crash issue - to be checked with ITDM - ITDM was not contacted.
ITDM
- DAQ was upgraded to the user friendly version in SASE3. After having discussed with FXE in the meeting, it was decided to install it also in FXE.
- DAQ training requested by SQS
CAS
- Karabo 2.2.5. patch being prepared. Will solve minor bugs and the crash due to empty data files.
- 28 Mpot update requests were received by CY. Need to be planned and coordinated with H.Santos.
|
|