Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 522     Entry time: 07 May 2018, 10:36
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Loops 5,7,11, update and Karabo deployed.
  • Loops 12,13,8 update ongoing.

SQS

  • Loop1 cabled up. Today the formware will be uploaded.
  • Loop 2 will probably be ready on Wednesday

SCS

  • Out ov 50 valves tested 5 showed problems. Investigation ongoing to understand where is the problem (PLC, Cables, Valves)
  • In Loop 2 a problem with a crate containing Elmo controlers was found. AE on it. Next loop to be tested will be Loop 4.
  • 1 crate does not have enough power to power up all the terminals. CR already prepared. Will be solved soon.

AE

  • By the middle of the week the valves will be included in the interlock systems (SASE1 issue)
  • The EPS interlock definitions for the tunnels in SASE2 are being finalized by AE, XPO, XPD

ITDM

  • Failure of one IBM server for online storage. Fixing ongoing.

DET

  • Online preview and charge injection issues are being solved restarting the DAQ and re-deployng Karabo.