Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 13 Jun 2018, 10:48 
    Reply   Re: Status report after dispatch meeting 09.30, posted by Hugo Silva Santos on 13 Jun 2018, 11:07 
Message ID: 533     Entry time: 13 Jun 2018, 10:48     Reply to this: 534
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SCS

  • Tests  continue - List of issues sent to AE.(4/5 in total). Some of thema are related to cabling. EET will be notified.

SQS

  • Loop 1 - 2 issues with cables found. EET to act on that. Motors test continue
  • Loop 3 - Motors test continue
  • Loop 2 is up and running.
  • Loop 4  probably will run tomorrow.
  • In general, (motors, gauges...) parameters have to be saved in order to be restored when a loop is restarded. Info have to go from SQS to AE about which parameters have to be saved.

AE

  • EPS in SASE2 running. MOV2 will be up until tomorrow.

ITDM

  • Transceiver changed ion SCS yesterday, for SQS will be done today. No rpoblems with the network have been noticed/reported by SCS.

CAS

  • Karabo version 2.2.4. being tested with PLCs. 

EET

  • Firmwares fo all the SCS loops have been generated.
  • Firmwares up to Loop 5 for SQS have been generated.