Message ID: 469     Entry time: 07 Feb 2018, 09:47
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB/SFX

- An AGIPD crate providing power broke down and has been fixed already by Kai-Eric Ballack. This delayed the data acquisition test planned by Jola. These are being done today.

 -Synch motion of mirrors will be tested with fake mirrors in D.09 as soon as the control is ready. Work is ongoing.

-First mirron in the SPB optics hutch will be installed today. 

- New Karabo release working smoothly so far.

FXE

- CRL in the tunnel being commissioned

 -Leak close to the diamond window being fixed. If everything goes fine ready for parasitic beam on Wed next week.

VAC

-Vacuum interlock tripped twice in the last 12 hours. Issue has to be clarified with CAS.

AE

-Reconfiguration of the SmarACT controllers between rotary and linear motion is being carried out. Marcin and Mahadi are the main players here.

ITDM

-Major safety update of the cluster has to be done. ITDM proposal is to do it next week. SPB and FXE opted for the early morning (between 8 and 10). Exact date will be announced by ITDM as soon as possible.