PSPO:
- G. Wellenreuther inform that DESY is commissioning a new gun in the injector that could take longer than expected. Harald Sinn is in a meeting today to disccuss this issue, any change in the scheduled will be reported.
SPB:
- Lost motor positions in the tunnel, CRL in defined state. Good state in general no major problems expected.
- Detector was clabled again.
- Loop updates still pending, SPB request to have loops ready during this week.
FXE: No one attended
Vacuum:
- SASE1:
- Some works in CRL for XTD1.
- Working in FXE grating chamber, necessary to update Vacuum loop.
- SASE3:
- M1 and M2 mirrors were installed before X-mas. Mirrors installation in K-mono to be finished next week.
- Created new loop this affects Vacuum loop, update necessary.
- XGM loop need to be updated.
- Motion loop 1 is working, some works in MCP motors on going.
Diagnostics:
- Technical commissioning of MCP on going together with the Russian collegues.
- MCP SASE2 will be transported to XTD6 on Wednesday afternoon.
AE:
- Working to implement redundancy into FXE loops.
- To agree a date with FXE to work in the grating chamber at the end of XTD10.
- Motion loop for SASE1 will be interrupted this afternoon at 14:00 to add some terminals for mirror 2.
Software:
- Deployment of Karabo 2.2.0 will start this Wednesday in FXE.
- Next dates for Karabo deployment are: 15th January for the Tunnels, 22nd January for SPB.
TS:
- Torsten Schoen inform that it is necessary to carry out an 'Emergency off button' test during the Shutdown.
- SPB agreed to perfom the test the 22nd January in the morning.
- For FXE the proposal is to perfom the test the 17th January, to be confirmed with AE and FXE.
|